I-39/90/94 Wisconsin River Bridge Project Public Involvement Meeting April 18 th , 2019 Project Location Project Termini: Black Road to south of I-39/94 & I-39/WIS 78 County: Columbia Towns: Dekorra and Caledonia Wisconsin Department of


slide-1
SLIDE 1

Public Involvement Meeting April 18th, 2019

I-39/90/94 Wisconsin River Bridge Project

slide-2
SLIDE 2

Project Location

Project Termini: Black Road to south of I-39/94 & I-39/WIS 78 County: Columbia Towns: Dekorra and Caledonia

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 1

slide-3
SLIDE 3

Route Importance

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 2

slide-4
SLIDE 4

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project

Route Importance

3

slide-5
SLIDE 5

Purpose and Need of the Project

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 4

slide-6
SLIDE 6

Primary Need of the Project

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 5

slide-7
SLIDE 7

Primary Need of the Project

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project

The bridge has been repaired 7 times in the last 58 years.

6

slide-8
SLIDE 8

Secondary Needs of the Project

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project

vpd = vehicles per day

7

slide-9
SLIDE 9

Secondary Needs of the Project

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 8

slide-10
SLIDE 10

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project

Secondary Needs of the Project

9

slide-11
SLIDE 11

Project Area Resources

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project

Section 4(f) – Public Lands

Land given special consideration during transportation projects

Wetlands

Identified during field surveys

Archeological Areas

Identified during field surveys

ATC Structures

American Transmission Company power line to the east of the Interstate

Existing Buildings

Identified using aerial imagery

10

slide-12
SLIDE 12

Rehabilitation Alternative

  • Repair the bridge in its current location
  • Replace the concrete deck and repair

steel supports

East Alternative

  • Construct a new bridge just east of the

existing bridge

  • Shift I-39/90/94 to east to match the new

bridge

  • Evaluate County U and V bridges for

possible replacement

West Alternative

  • Construct a new bridge just west of the

existing bridge

  • Shift I-39/90/94 to west to match the

new bridge

  • Evaluate County U and V bridges for

possible replacement

Preliminary Alternatives

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 11

slide-13
SLIDE 13

Potential Construction Staging Concept

Wisconsin of Transportation

I-39/90/94 Wisconsin River Bridge Study

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 12

Existing WI River Bridge

slide-14
SLIDE 14

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 13

Potential Construction Staging Concept

slide-15
SLIDE 15

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 14

Potential Construction Staging Concept

slide-16
SLIDE 16

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 15

Potential Construction Staging Concept

slide-17
SLIDE 17

Project Schedule

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 16

slide-18
SLIDE 18

Contact Information

Wisconsin Department of Transportation I-39/90/94 Wisconsin River Bridge Project 17