Hinkley Connection Project Presentation to Banwell Parish Council - - PowerPoint PPT Presentation

hinkley connection project
SMART_READER_LITE
LIVE PREVIEW

Hinkley Connection Project Presentation to Banwell Parish Council - - PowerPoint PPT Presentation

Hinkley Connection Project Presentation to Banwell Parish Council 16 March 2020 Michael Painter, National Grid Gillian Burnell, National Grid Agenda 01 Who we are 02 Hinkley Connection Project 03 In your area 04 Timeline 05 Questions


slide-1
SLIDE 1

Hinkley Connection Project

Presentation to Banwell Parish Council

16 March 2020 Michael Painter, National Grid Gillian Burnell, National Grid

slide-2
SLIDE 2

2 National Grid

Agenda

01

Who we are

02

Hinkley Connection Project

03

In your area

04

Timeline

05

Questions

06

Our approach

07

Keep informed

slide-3
SLIDE 3

3 National Grid

slide-4
SLIDE 4

4 National Grid

We are connecting people to low carbon energy. We're building an electricity connection: pylons, cables and substations between Hinkley Point and Seabank power stations. It will also mean we have more capacity on

  • ur network for renewable energy from

the South West peninsular.

02 Hinkley Connection Project

slide-5
SLIDE 5

5 National Grid

  • 57 kilometres length
  • 48.5 km of overhead line
  • 8.5 km of underground cable through the

Mendip Hills AONB

  • Mostly T-pylon
  • Two substations
  • Removing 67 kilometres of WPD pylons

Project overview

slide-6
SLIDE 6

6 National Grid

Our work near Banwell includes:

  • Installing underground cables across the

Mendips

  • New substation near Sandford
  • T-pylons from Sandford to Avonmouth
  • Removing WPD’s pylons and overhead line
  • Reinstatement and landscaping

Insert pics

03 In your area

slide-7
SLIDE 7

7 National Grid

Larger/zoomable map available at: hinkleyconnection.co.uk/your-area/#sandford

slide-8
SLIDE 8

8 National Grid

New substation

We’ve appointed Siemens to build a substation near Sandford:

  • Preparations included clearing the site in autumn to

prevent animals and birds nesting in work areas

  • Balfour Beatty has nearly completed the temporary haul

road from Towerhead to the site

  • Construction starts end of March 2020 and expected to

be complete in early 2024

  • First activities will be setting up site, installing staff

welfare and office facilities

slide-9
SLIDE 9

9 National Grid

Installing underground cables

Balfour Beatty is our contractor and work is progressing well:

  • Main construction started in March 2019 - road accesses

(A38 and A368) completed

  • Tarnock site compound complete
  • Haul road north of A368 to substation site nearly

complete

  • Trenching started - twelve underground cables in four

trenches (three cables per trench) approximately 1.6m wide by 1.1m deep

  • Using ducts to protect soil structure, minimise impacts on

wildlife and environment and protect our staff

  • Significant archaeology finds at Max Mill Lane
slide-10
SLIDE 10

10 National Grid

Building T- Pylons

Balfour Beatty has been appointed to build the

  • verhead line north to Avonmouth
  • Main construction starts in early 2021 and expected to be

complete in 2024

  • First activities will be building road access and temporary

haul road

  • Currently carrying out ground investigation surveys where

the pylons, temporary haul road and accesses will be built

  • Other preparations over the coming months: ecological

mitigation and clearing some vegetation and hedgerows, as well as erecting stock fencing

slide-11
SLIDE 11

11 National Grid

Removing overhead lines

When the new substation at Sandford is operational and supplying power to WPD’s network, we’ll remove WPD’s pylons from the AONB – leaving this area pylon free for the first time since the 1960s

  • Pylons will be dismantled and removed
  • Foundations will be left in place to minimise

disruption to local environment

  • Expected completion by 2025
  • Balfour Beatty will carry out this work
  • In 2022, we will build short connections to the

existing 132,000 volt overhead line to Weston- super-Mare and to the substation at Churchill. This will take around 12 months

Pic of WPD pylon

slide-12
SLIDE 12

12 National Grid

04 Timeline

slide-13
SLIDE 13

Questions

slide-14
SLIDE 14

14 National Grid

05 Our approach – Traffic management

  • Work to build temporary road accesses and haul road off

A368 is essentially complete

  • Building the haul road allows us to move traffic directly
  • ff A roads – limiting use of local road network.
  • Traffic will be routed directly from M5 (junction 22) along

A38 to A368

  • All construction vehicles are clearly identified with project

stickers/signage

Insert pics

slide-15
SLIDE 15

15 National Grid

05 Our approach - We want to be a good neighbour

Creating opportunities to talk and meet with residents and businesses.

Before construction begins in each area, we’re:

  • Providing updated project briefings to parish

and town councils

  • Writing to residents and businesses with

updates

  • Holding drop-in events
  • Promoting our 24/7 community helpline
slide-16
SLIDE 16

16 National Grid

Our experts make sure habitats, plants and animals are protected:

  • Surveying work areas for protected species and

avoiding important habitats.

  • Encouraging protected species to move or

physically moving them if habitat cannot be avoided

  • Creating buffer zones to avoid disturbing nesting

protected birds and installing barn owl boxes

  • In the Mendips we’ve installed bat flyways to retain

linear features such as hedgerows which bats use to navigate

05 Our approach - Care for the environment

slide-17
SLIDE 17

17 National Grid

Free STEM sessions for schools

  • KS1, KS2 & KS3 practical workshops

Hinkley Connection Education Fund

  • Funding to support 131,018 pupils and 538

schools (inc. Banwell and Winscombe Primary Schools)

  • £354,000 awarded since 2018.

Adult skills

  • 175 local unemployed people trained. 66 have

secured employment. Community Grant Fund

  • Over £200,000 to 12 community projects to date
  • Includes Winscombe Cricket Club, Axbridge Town

Hall and a community hall in Cheddar.

05 Our approach - Engineering positive futures

slide-18
SLIDE 18

18 National Grid

Our dedicated community relations team is on hand to respond to queries and complaints.

  • By telephone 0800 377 7347 (24 hours)
  • Via the website www.hinkleyconnection.co.uk
  • By email hinkleyconnection@nationalgrid.co.uk
  • By post FREEPOST H POINT CONNECTION

We value your interest in the project

06 Keep informed