SEPTEMBER 5 - 7, 2018
High Voltage Pad-mount Transformer SEPTEMBER 5 - 7, 2018 What is - - PowerPoint PPT Presentation
High Voltage Pad-mount Transformer SEPTEMBER 5 - 7, 2018 What is - - PowerPoint PPT Presentation
High Voltage Pad-mount Transformer SEPTEMBER 5 - 7, 2018 What is the High Voltage Padmount Transformer(HVPT) Substation? Traditional substation vs. HVPT SEPTEMBER 5 - 7, 2018 HVPT History In order to reduce its outlay in distribution,
SEPTEMBER 5 - 7, 2018
What is the High Voltage Padmount Transformer(HVPT) Substation?
Traditional substation vs. HVPT
SEPTEMBER 5 - 7, 2018
HVPT History
- In order to reduce its outlay in distribution, Manitoba
Hydro investigated alternative solutions that would save in capital costs and land use while increasing reliability and safety.
- Manitoba Hydro was also facing the need to
replace/refurbish many substations reaching their End of Life.
- The idea to make a High Voltage “Distribution Style”
transformer was explored.
SEPTEMBER 5 - 7, 2018
HVPT History
- Working with Partner Technologies Inc., Manitoba Hydro
researched and created the HVPT to realize their
- bjectives.
Transformer Sizes Different Primary Voltages Different Secondary Voltage 1.5 MVA to 20 MVA Up to 138 kV 5 to 34.5 kV
- Can be larger, however loses some of the benefits
- In Research: 230 kV Primary Voltage. Can be done but
hasn’t been yet.
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
HVPT Details
- A HVPT has no energized external
parts.
- No fencing required.
- Suitable for any climate;
environmentally friendly.
- Utility, residential, commercial and
industrial applications.
- All station components separate – i.e.
regulators, switch gear, capacitors, and station service transformers.
SEPTEMBER 5 - 7, 2018
Benefits – Land Savings
- Up to 75% in land savings. No need for a large station
structure, station yard and fencing.
- In an industrial setting, the HVPT transformer can be
installed in spaces as small as 20 sq. meters.
SEPTEMBER 5 - 7, 2018
Benefits - Reliability
- Smaller than your conventional substation, HVPT stations can
be installed closer to your site.
- Shorter feeders, minimize voltage drops and losses and increase
reliability.
- Lack of External Bushings and Parts reduces Wildlife Outages
SEPTEMBER 5 - 7, 2018
Benefits - Safety
- The transformer comes with a tamper resistant enclosure
to ANSI C57.12.18 standards. This ensures the transformer is safe from damage from elements, humans, and wildlife.
- The public is also protected without the need for fencing.
- The grounding designs exceed
the requirements of IEEE 80 to ensure public safety.
SEPTEMBER 5 - 7, 2018
Benefits - Theft
Manitoba Hydro has seen a decrease in copper theft at HVPT Substations.
SEPTEMBER 5 - 7, 2018
Benefits – Weather
- Storm resistant - covered in dry
nitrogen, no on-load tap changer, no conservator, sealed tank, no fans.
- Operating Temperature Range
(for MH) is -40C to +40C(-40F to 104F)
- Can be operated outside of this
range
SEPTEMBER 5 - 7, 2018
Benefits – Installation & Maintenance
- The HVPT station fits onto a trailer and can be shipped
completely assembled to your site.
- No on site ‘dressing’ of transformer required.
- The transformer can then be
simply removed and transferred to different locations.
- Only routine condition monitoring
is required.
- Transformers can be “swapped out”
and in operation in 24 hours
SEPTEMBER 5 - 7, 2018
Benefits - Timeframe
- An HVPT Substation’s Design is very simple (7 – 12
drawings vs 50)
- Construction can take less than 2 weeks (including
verification testing
- ~26 to 30 weeks from inception to
install
- Long lead items
SEPTEMBER 5 - 7, 2018
Benefits - Cost
- Installation costs up to 50% less than a conventional
substation while providing full functionality.
- Cost savings include:
- Less land procurement
- Less additional materials
(no fencing, ancillary parts)
- Quicker installation
- Defer Capital costs
- Avoid stranded assets
SEPTEMBER 5 - 7, 2018
Disadvantages
- Data – Switchgears, ACRs, Regulators
- Lack of Fans (ONAN/ONAF)
- Onboard tap changer - Regulators
SEPTEMBER 5 - 7, 2018
Innovative Supply Options
- Use of the HV Padmounts provides a cost effective
solution able to accommodate the quickly changing demands of the developer/customer
- Flexibility and short lead times avoids stranded
assets
- Incorporating automation eliminates concerns
regarding multiple smaller supply sites allowing for the distributed station concept to be viable
- “Building Block Approach”
SEPTEMBER 5 - 7, 2018
Innovative Supply Options
SEPTEMBER 5 - 7, 2018
Innovative Supply Options
- Waverley West subdivision is
approximately 2600 acres
- Expected to accommodate
40,000 residents in 13,000 homes
- Expected to be completely
developed in 10 to 30 years
- Load estimates vary between
70 and 110 MVA
- High level of uncertainty as to
load growth rate and horizon load
SEPTEMBER 5 - 7, 2018
Case Study – Modular Employment
- Instead of two 60-MVA substations taking up 8 acres of
land, Manitoba Hydro installed ten 10-MVA HVPT stations surrounding the new 13,000 lot Waverley West development.
- Drastically increased the utilization rate (N-1). (60% to
90%)
- Initial savings per station amounted up to $1 million with
total net present value savings between $13 and $15 million.
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
10 MVA Site
SEPTEMBER 5 - 7, 2018
2x 10 MVA Site
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
Installation of an HVPT
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
Dead-Front Terminations
Solid Dielectric Primary Connections
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018