high voltage pad mount transformer
play

High Voltage Pad-mount Transformer SEPTEMBER 5 - 7, 2018 What is - PowerPoint PPT Presentation

High Voltage Pad-mount Transformer SEPTEMBER 5 - 7, 2018 What is the High Voltage Padmount Transformer(HVPT) Substation? Traditional substation vs. HVPT SEPTEMBER 5 - 7, 2018 HVPT History In order to reduce its outlay in distribution,


  1. High Voltage Pad-mount Transformer SEPTEMBER 5 - 7, 2018

  2. What is the High Voltage Padmount Transformer(HVPT) Substation? Traditional substation vs. HVPT SEPTEMBER 5 - 7, 2018

  3. HVPT History • In order to reduce its outlay in distribution, Manitoba Hydro investigated alternative solutions that would save in capital costs and land use while increasing reliability and safety. • Manitoba Hydro was also facing the need to replace/refurbish many substations reaching their End of Life. • The idea to make a High Voltage “Distribution Style” transformer was explored. SEPTEMBER 5 - 7, 2018

  4. HVPT History • Working with Partner Technologies Inc., Manitoba Hydro researched and created the HVPT to realize their objectives. Transformer Sizes Different Primary Different Secondary Voltages Voltage 1.5 MVA to 20 MVA Up to 138 kV 5 to 34.5 kV • Can be larger, however loses some of the benefits • In Research: 230 kV Primary Voltage. Can be done but hasn’t been yet. SEPTEMBER 5 - 7, 2018

  5. SEPTEMBER 5 - 7, 2018

  6. HVPT Details • A HVPT has no energized external parts. • No fencing required. • Suitable for any climate; environmentally friendly. • Utility, residential, commercial and industrial applications. All station components separate – i.e. • regulators, switch gear, capacitors, and station service transformers. SEPTEMBER 5 - 7, 2018

  7. Benefits – Land Savings • Up to 75% in land savings. No need for a large station structure, station yard and fencing. • In an industrial setting, the HVPT transformer can be installed in spaces as small as 20 sq. meters. SEPTEMBER 5 - 7, 2018

  8. Benefits - Reliability • Smaller than your conventional substation, HVPT stations can be installed closer to your site. Shorter feeders, minimize voltage drops and losses and increase • reliability. • Lack of External Bushings and Parts reduces Wildlife Outages SEPTEMBER 5 - 7, 2018

  9. Benefits - Safety • The transformer comes with a tamper resistant enclosure to ANSI C57.12.18 standards. This ensures the transformer is safe from damage from elements, humans, and wildlife. • The public is also protected without the need for fencing. • The grounding designs exceed the requirements of IEEE 80 to ensure public safety. SEPTEMBER 5 - 7, 2018

  10. Benefits - Theft Manitoba Hydro has seen a decrease in copper theft at HVPT Substations. SEPTEMBER 5 - 7, 2018

  11. Benefits – Weather • Storm resistant - covered in dry nitrogen, no on-load tap changer, no conservator, sealed tank, no fans. • Operating Temperature Range (for MH) is -40C to +40C(-40F to 104F) • Can be operated outside of this range SEPTEMBER 5 - 7, 2018

  12. Benefits – Installation & Maintenance • The HVPT station fits onto a trailer and can be shipped completely assembled to your site. • No on site ‘dressing’ of transformer required. • The transformer can then be simply removed and transferred to different locations. • Only routine condition monitoring is required. • Transformers can be “swapped out” and in operation in 24 hours SEPTEMBER 5 - 7, 2018

  13. Benefits - Timeframe • An HVPT Substation’s Design is very simple (7 – 12 drawings vs 50) • Construction can take less than 2 weeks (including verification testing • ~26 to 30 weeks from inception to install • Long lead items SEPTEMBER 5 - 7, 2018

  14. Benefits - Cost • Installation costs up to 50% less than a conventional substation while providing full functionality. • Cost savings include: • Less land procurement • Less additional materials (no fencing, ancillary parts) • Quicker installation • Defer Capital costs • Avoid stranded assets SEPTEMBER 5 - 7, 2018

  15. Disadvantages • Data – Switchgears, ACRs, Regulators • Lack of Fans (ONAN/ONAF) • Onboard tap changer - Regulators SEPTEMBER 5 - 7, 2018

  16. Innovative Supply Options • Use of the HV Padmounts provides a cost effective solution able to accommodate the quickly changing demands of the developer/customer • Flexibility and short lead times avoids stranded assets • Incorporating automation eliminates concerns regarding multiple smaller supply sites allowing for the distributed station concept to be viable • “Building Block Approach” SEPTEMBER 5 - 7, 2018

  17. Innovative Supply Options SEPTEMBER 5 - 7, 2018

  18. Innovative Supply Options • Waverley West subdivision is approximately 2600 acres • Expected to accommodate 40,000 residents in 13,000 homes • Expected to be completely developed in 10 to 30 years • Load estimates vary between 70 and 110 MVA • High level of uncertainty as to load growth rate and horizon load SEPTEMBER 5 - 7, 2018

  19. Case Study – Modular Employment • Instead of two 60-MVA substations taking up 8 acres of land, Manitoba Hydro installed ten 10-MVA HVPT stations surrounding the new 13,000 lot Waverley West development. • Drastically increased the utilization rate (N-1). (60% to 90%) • Initial savings per station amounted up to $1 million with total net present value savings between $13 and $15 million. SEPTEMBER 5 - 7, 2018

  20. SEPTEMBER 5 - 7, 2018

  21. SEPTEMBER 5 - 7, 2018

  22. 10 MVA Site SEPTEMBER 5 - 7, 2018

  23. 2x 10 MVA Site SEPTEMBER 5 - 7, 2018

  24. SEPTEMBER 5 - 7, 2018

  25. SEPTEMBER 5 - 7, 2018

  26. SEPTEMBER 5 - 7, 2018

  27. SEPTEMBER 5 - 7, 2018

  28. SEPTEMBER 5 - 7, 2018

  29. SEPTEMBER 5 - 7, 2018

  30. Installation of an HVPT SEPTEMBER 5 - 7, 2018

  31. SEPTEMBER 5 - 7, 2018

  32. SEPTEMBER 5 - 7, 2018

  33. SEPTEMBER 5 - 7, 2018

  34. SEPTEMBER 5 - 7, 2018

  35. SEPTEMBER 5 - 7, 2018

  36. SEPTEMBER 5 - 7, 2018

  37. Dead-Front Terminations Solid Dielectric Primary Connections SEPTEMBER 5 - 7, 2018

  38. SEPTEMBER 5 - 7, 2018

  39. SEPTEMBER 5 - 7, 2018

  40. Thank you! Q & A SEPTEMBER 5 - 7, 2018

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend