IEEE Transformer Committee PC57.167 Distribution Transformer Monitoring - User
Mark Scarborough Electrical Engineering Consultant – DuPont January 9, 2019
IEEE Transformer Committee PC57.167 Distribution Transformer - - PowerPoint PPT Presentation
IEEE Transformer Committee PC57.167 Distribution Transformer Monitoring - User Mark Scarborough Electrical Engineering Consultant DuPont January 9, 2019 Transformer Types in DuPont Control power Distribution (substation) dry-type
Mark Scarborough Electrical Engineering Consultant – DuPont January 9, 2019
power panel type
and ASD applications
transformers
insulation fluids
30MVA)
mostly 2.4kV to 13.8KV. Few 34.5kV system.
about 250HP and above
work or power goes out.
inspection.
know what to look for.
walk the main electrical system from substation to substation daily, weekly, or monthly.
deterioration in paint system.
very good at taking samples for oil screen and DGA on an annual basis.
labs and reporting and interpretation.
some oil back in occasionally.
inspection, testing, and cleaning.
impossible until the system shuts down automatically.
a secondary voltage of 600V and below
and control contacts.
alarm contacts (sometimes directional shield).
alarm contacts.
monitoring (4-20mA signal) of space heater circuit in ATCs or control box. Space heater control? Thermostat or no thermostat?
fan starter and/or control switch.
alarms.
trip and alarm contacts.
indicator relay with alarm contacts.
vacuum gage.
phase hot spot temperature indication with peak indicator, contacts for alarm, trip and fan control and fan exerciser. (Typically this is a self contained package from the vendor.)
monitoring (4-20mA signal) of space heater circuit in ATCs or control box. Space heater control? Thermostat or no thermostat?
above.
“peak” indicator on 500kVA and above.
500kVA and above.
alarm contacts on 1000kVA and above.
accessible outside of the HV and LV compartments.
accessible outside of the HV and LV compartments.
compartments.
gage, liquid thermometer, and vacuum / pressure gages.
feed a substation or electrical room that has local DCS / PLC (control system) I/O.
DCS / PLC I/O cabinets. If it didn’t exist, then it basically didn’t get wired any where.
response?
required?
that are in critical applications.
Thinking may be able to use for transformers because not part of process control.