IEEE Transformer Committee PC57.167 Distribution Transformer - - PowerPoint PPT Presentation

ieee transformer committee pc57 167 distribution
SMART_READER_LITE
LIVE PREVIEW

IEEE Transformer Committee PC57.167 Distribution Transformer - - PowerPoint PPT Presentation

IEEE Transformer Committee PC57.167 Distribution Transformer Monitoring - User Mark Scarborough Electrical Engineering Consultant DuPont January 9, 2019 Transformer Types in DuPont Control power Distribution (substation) dry-type


slide-1
SLIDE 1

IEEE Transformer Committee PC57.167 Distribution Transformer Monitoring - User

Mark Scarborough Electrical Engineering Consultant – DuPont January 9, 2019

slide-2
SLIDE 2

Transformer Types in DuPont

  • Control power
  • Dry-type in MCCs and control panels
  • Small dry-type
  • Lighting, receptacle, instrument

power panel type

  • 5kVA – 330kVA (1 phase and 3 phase)
  • Specialty
  • Dry-type and fluid filled for rectifier

and ASD applications

  • Pole top
  • Small power
  • Some 20 – 45MVA main substation

transformers

  • Distribution (substation) dry-type
  • VPI conventional wound and cast coil
  • 750kVA – 3000kVA
  • Distribution (substation) fluid filled
  • Mineral oil, natural ester, silicone

insulation fluids

  • 750kVA – 5000kVA (some 10MVA and

30MVA)

  • Pad-mounted
  • Mineral oil and natural ester fluids
  • 100kVA – 3000kVA
slide-3
SLIDE 3

Typical Distribution System

  • Incoming power
  • Purchased power substations
  • Mostly all owned by Utilities
  • 230kV down to 12.47kV
  • Internal plant distribution
  • Typically medium voltage (1 – 35kV) but

mostly 2.4kV to 13.8KV. Few 34.5kV system.

  • Utilization
  • 480V and 575V for most applications
  • 2.4kV and 4.16kV for motor applications

about 250HP and above

  • 120V / 230V for small loads
  • Grounding
  • B-Phase
  • HGR
  • LRG
  • Soild
slide-4
SLIDE 4

Transformer Monitoring Techniques

  • Control power, small dry-type, pole top
  • Usually don’t do anything. Investigate when something doesn’t

work or power goes out.

  • Some pole tops and small dry-types may get an infrared

inspection.

  • Visual
  • Probably the most common but questionable as to what people

know what to look for.

  • Some plants require an operator or maintenance technician to

walk the main electrical system from substation to substation daily, weekly, or monthly.

  • Looking for abnormal sounds and or smells, leaks, broken gages,

deterioration in paint system.

  • Infrared Inspection
  • Typically on an annual basis for most facilities.
  • Good way to see if cooling system is working or if low fluid level.
slide-5
SLIDE 5

Transformer Monitoring Techniques

  • If transformers are fluid filled, then

very good at taking samples for oil screen and DGA on an annual basis.

  • Typical issues with sample methods and

labs and reporting and interpretation.

  • Need to realize that you have to put

some oil back in occasionally.

  • If critical application, will shut down
  • n a 2 or 4 year interval to do

inspection, testing, and cleaning.

  • Planned shutdowns sometimes are

impossible until the system shuts down automatically.

slide-6
SLIDE 6

Transformer Monitoring Techniques – Internal Specification

  • Three (3) internal standards / guidelines
  • Fluid Filled – 300kVA to 10MVA, 3 Ph, primary voltage 2,400 to 46,000V
  • Dry-Type – 300 to 7.5MVA, 3 Ph, primary voltage 2,400 to 34,500V
  • Pad Mount – 2500kVA and below, primary voltage of 34,500V and below and

a secondary voltage of 600V and below

  • Each standard describes the feature sets required on each

transformer type. User can add or take away as necessary for their application.

slide-7
SLIDE 7

Transformer Monitoring Techniques – Fluid Filled

  • Standard
  • Field Dial thermometer with alarm

and control contacts.

  • Pressure / vacuum gage.
  • Pressure relief valve.
  • Large pressure relief device with

alarm contacts (sometimes directional shield).

  • Magnetic liquid level gauge with

alarm contacts.

  • Optional / Custom
  • Push to test circuit and/or current

monitoring (4-20mA signal) of space heater circuit in ATCs or control box. Space heater control? Thermostat or no thermostat?

  • Fan controls and aux contacts off of

fan starter and/or control switch.

  • N2 bottle monitoring system with

alarms.

  • Sudden or fault pressure relay with

trip and alarm contacts.

  • Winding hot-spot temperature

indicator relay with alarm contacts.

  • Add alarm contacts to pressure /

vacuum gage.

  • Infrared view ports on ATC.
slide-8
SLIDE 8

Transformer Monitoring Techniques – Dry- Type

  • Standard
  • Winding temperature with 3-

phase hot spot temperature indication with peak indicator, contacts for alarm, trip and fan control and fan exerciser. (Typically this is a self contained package from the vendor.)

  • Infrared view ports.
  • Cooling fans w/ running status
  • Optional / Custom
  • Push to test circuit and/or current

monitoring (4-20mA signal) of space heater circuit in ATCs or control box. Space heater control? Thermostat or no thermostat?

  • Infrared view ports on ATC.
slide-9
SLIDE 9

Transformer Monitoring Techniques – Pad- Mounted

  • Standard
  • Liquid level gauge on 500kVA and

above.

  • Dial type thermometer with

“peak” indicator on 500kVA and above.

  • Vacuum / pressure gage on

500kVA and above.

  • Pressure relief device.
  • Large pressure relief device with

alarm contacts on 1000kVA and above.

  • Optional / Custom
  • Require that sample valve be

accessible outside of the HV and LV compartments.

  • Require that all gages be

accessible outside of the HV and LV compartments.

  • Infrared view ports on HV and LV

compartments.

  • Alarm contacts on liquid level

gage, liquid thermometer, and vacuum / pressure gages.

slide-10
SLIDE 10

Alarm and Trip Contacts?

  • In most cases, these transformers are located in an industrial facility and

feed a substation or electrical room that has local DCS / PLC (control system) I/O.

  • Historically, some or all of the alarm contacts would be hard wired to local

DCS / PLC I/O cabinets. If it didn’t exist, then it basically didn’t get wired any where.

  • More recently ……
slide-11
SLIDE 11

Alarm and Trip Contacts?

  • …. we have been using the I/O capabilities on microprocessor based

protective relaying and even expansion I/O modules for such devices.

slide-12
SLIDE 12

Example #1

  • 13.8kV Metal Clad Switchgear
  • Radial feed to 2500kVA transformer but

looped to additional substations.

  • Switched breaker local to each

substation.

  • Microprocessor relay local to substation

not capable of handling I/O from transformer so wired to DCS local I/O.

slide-13
SLIDE 13

Construction Interconnection Dwg

slide-14
SLIDE 14

Example #2

  • 12.47kV Metal Clad

Switchgear

  • Radial feed to 1000kVA

substation transformer near by.

  • SEL-787 protective relay for

transformer with differential.

slide-15
SLIDE 15

Construction Interconnection Dwg

slide-16
SLIDE 16

MV Switchgear Vendor Schematic

slide-17
SLIDE 17

Transformer – Vendor Drawing

slide-18
SLIDE 18

Example #3

slide-19
SLIDE 19

Signals and What Action?

  • So now we have gotten the signals to the plant DCS or PLC system.
  • A DCS screen or HMI screen is developed with the alarm points.
  • DCS / PLC system is monitored by Operation / Operations. Sometimes

they don’t know how to respond.

  • Started developing action / resolution matrix.
  • Call the on call maintenance electrician?
  • Go to field and look at the equipment?
  • System automatically send Text message to on call maintenance electrician

response?

  • Shutdown the process so the transformer can be shutdown?
  • Alarms can go into a PI Data Historian system but not aware of active

trending.

slide-20
SLIDE 20
  • Misc. Topics / Considerations
  • Confusion as to what to do with an alarm comes in. What action is

required?

  • Firewalls and cyber security.
  • Not all sites have a centralized DCS or PLC to connect to.
  • Typically do not monitor of pad mounted transformer but we have some

that are in critical applications.

  • Been some interest in:
  • On line monitoring for moisture. (On line moisture removal systems in service.)
  • On line monitoring for DGA monitoring.
  • Better monitoring of dry-type transformers. Have had some sudden failures.
  • Starting to experiment with wireless communications technology for instruments.

Thinking may be able to use for transformers because not part of process control.

  • Trending / data collection.
slide-21
SLIDE 21

Thank You.

  • Questions / Discussion