Hex Chrome Exposures from Hex Chrome Exposures from Metal Cladding - - PowerPoint PPT Presentation

hex chrome exposures from hex chrome exposures from metal
SMART_READER_LITE
LIVE PREVIEW

Hex Chrome Exposures from Hex Chrome Exposures from Metal Cladding - - PowerPoint PPT Presentation

Hex Chrome Exposures from Hex Chrome Exposures from Metal Cladding Work in a Boiler O t b October 2012 2012 Luminant Corporate Safety David Friedman, CIH, MSPH, ARM Background Information Situation occurred at a lignite plant in Central


slide-1
SLIDE 1

Hex Chrome Exposures from Hex Chrome Exposures from Metal Cladding Work in a Boiler

O t b 2012 October 2012 Luminant Corporate Safety David Friedman, CIH, MSPH, ARM

slide-2
SLIDE 2

Background Information

  • Situation occurred at a lignite plant in Central Texas.
  • The plant has two units and the work was done in a 3 year-old boiler

which is part of a 580 MW unit which is part of a 580 MW unit.

  • The unit has a circulating fluidized bed boiler and the circulating fuel and

ash create a lot of wear and tear on the boiler walls.

  • The boiler walls were not originally coated when the unit was constructed

in 2009.

  • Inspections of the boiler had revealed that a significant amount of erosion
  • Inspections of the boiler had revealed that a significant amount of erosion

had occurred since 2009

  • A decision was made to have the boiler walls coated with a high-chrome

t l l ddi d i th S i 2012 t metal cladding during the Spring 2012 outage.

1

slide-3
SLIDE 3

Circulating Fluidized Bed Boiler

2

slide-4
SLIDE 4

Arrowhead Nozzles at Bottom of Boiler

3

slide-5
SLIDE 5

Cladding Process

  • The vendor applied the cladding with a high velocity continuous combustion

(HVCC) metal spray process.

  • The HVCC process involves melting a high-chrome wire inside a hand-held
  • The HVCC process involves melting a high-chrome wire inside a hand-held

gun and spraying the atomized metal onto the surface.

  • Before the tubes are coated they are blasted with a non-silica containing

material

  • In order to access the tubing for the blasting and coating multi-level scaffolds

are set up throughout the interior of the boiler. are set up throughout the interior of the boiler.

4

slide-6
SLIDE 6

Scaffolding Set Up in Boiler

5

slide-7
SLIDE 7

Blasting of Boiler Tubes in Preparation for Coating

6

slide-8
SLIDE 8

Cladding Application

7

slide-9
SLIDE 9

Close Up of Application Process

8

slide-10
SLIDE 10

Finished Product with Paint

9

slide-11
SLIDE 11

Chromium

A commonly occurring metal A commonly occurring metal Present in different valence (oxidation) states Elemental (does not exist in nature)

Elemental (does not exist in nature)

Cr +2 (Divalent) Cr+3 (Trivalent) Cr +6 (Hexavalent)

– Water soluble W t i l bl – Water insoluble

Valence state and solubility greatly affects toxicity Can oxidize or reduce depending on conditions Can oxidize or reduce depending on conditions Hex Chrome will reduce from Cr +6 to less toxic Cr+3

10

slide-12
SLIDE 12

Hex Chrome Health Effects

Routes of exposure Skin contact Cancer

– Evidence is primarily from chromate production, chromate

Inhalation Ingestion

chromate production, chromate pigment & chrome plating; less compelling for welding

Soluble forms

– Perforation of nasal septum – Nasal irritation – Nasal ulcerations

Trivalent form

– Asthma – Bronchitis – Allergic skin reactions

Trivalent form Irritant Less toxic than Hex Chrome

Allergic skin reactions – Skin ulcers – Irritant contact dermatitis

11

slide-13
SLIDE 13

Overview of the OSHA Standard

1910.1026 –General Industry 1926.1126-Construction 1915.1026-Shipbuilding A performance oriented standard Applies only to the hexavalent form of chromium (Cr+6) Exemptions Pesticides that contain Cr+6 Portland cement Where the employer has objective data that a material, operations or

process cannot release Cr+6 at levels that would exceed 0.5 ug/m3 under any expected conditions of use

12

slide-14
SLIDE 14

Exposure Limits and Some Other Requirements

  • PEL= 0 005 mg/m3 or 5 µg/m3 as an 8 hour TWA
  • PEL= 0.005 mg/m3 or 5 µg/m3 as an 8 hour TWA
  • Action level (AL)= 0.0025 mg/m3 or 2.5 µg/m3 as an 8 hour

TWA

  • If results are > PEL, monitoring must be done at least every

3 months If lt PEL d AL it i t b d t

  • If results are < PEL and > AL, monitoring must be done at

least every 6 months

  • If > AL for 30 + days per year, med surveillance is required

y p y , q

  • PPE – Skin and Eye Protection if hazard is present
  • Change areas & Washing facilities also required

g g q

  • Training about standard, hazards and protective measures
  • Note: These are not all the requirements, consult the

f f

13

standard for more detailed information

slide-15
SLIDE 15

Spring 2012 Outage Activities

  • Contractor A coated the boiler with a metallic spray that
  • Contractor A coated the boiler with a metallic spray that

contained a high percentage (20 to 30%) of chrome. The coating process involved melting the wire so it could be d li id sprayed as a liquid.

  • The heating process oxidized the chrome metal into hex

g p chrome and the spraying created very high airborne hex chrome levels.

  • Contractor A also blasted the boiler before the coating

application was done

  • A large containment was placed in the boiler around the

spraying and a mechanical exhaust ventilation system was p y g y used.

14

slide-16
SLIDE 16

Spring 2012 Outage Activities Continued

  • Contractor A support employees wore full-face respirators
  • Contractor A support employees wore full-face respirators

when in the boiler. Employees wore supplied air blast hoods (Bullard 88 VX) when blasting and supplied air hoods (B ll d CC20) d f ll f i t h i / (Bullard CC20) and full-face respirators when spraying / cladding.

  • Area air samples in the containment during the spraying

had results ranging from about 200 to 5000 µg/m3.

  • Personal air samples, collected under the spray hoods had

results ranging from 1.2 to 5.5 µg/m3.

  • The Protection Factor for the blast hood and spray hood is

1000 so they will protect up to 5000 µg/m3 (1000 x PEL) y p p µg ( )

15

slide-17
SLIDE 17

Spring 2012 Outage Activities Continued

  • Contractor A employees were working on scaffolding
  • Contractor A employees were working on scaffolding

which needed to periodically be moved and repositioned. Th ff ld i d b C t t B d

  • The scaffold moving was done by Contractor B and a

question was brought up about how much hex chrome exposure Contractor B employees would have when doing p p y g this.

  • There was no air monitoring data on the exposures so it

There was no air monitoring data on the exposures so it was not clear as to what type of PPE and training would be needed for Contractor B employees.

  • A hex chrome video was shown to Contractor B employees

which apparently caused a lot of concern and a number of pp y Contractor B employees walked off the job.

16

slide-18
SLIDE 18

Spring 2012 Outage Activities Continued

  • Contractor B hired an Industrial Hygiene consultant to
  • Contractor B hired an Industrial Hygiene consultant to

conduct air sampling when the scaffolding was being moved and while it was being cleaned (blown down) prior to its di tli dismantling.

  • A crew of Contractor B employees was trained and

p y provided with coveralls and full-face respirators to wear during the scaffolding cleaning and moving.

  • The air samples showed hex chrome levels during the blow

down ranged from about 0.2 to 16 µg/m3.

  • Hex chrome levels during the scaffold moving ranged from

about 0.4 to 20 µg/m3. µg

17

slide-19
SLIDE 19

2012 Outage – Scrubber

  • In addition to the boiler coating work a large portion of the
  • In addition to the boiler coating work, a large portion of the

bottom of a scrubber was cut out for repairs.

  • The scrubber was made of stainless steel and the cutting

The scrubber was made of stainless steel and the cutting was done by an arc gouger.

  • A wooden deck “dance floor” was installed above the cutting

g area so contractors could work on the spray nozzles. The dance floor was not air tight.

  • Mechanical ventilation- air horns were placed on the level of

the scrubber to force air in and pull it out.

  • Area hex chrome air samples were collected on the dance

floor and next to the air horns. No samples were collected on the contractors running the arc gougers. g g g

18

slide-20
SLIDE 20

2012 Outage – Scrubber

  • The hex chrome results collected during the scrubber arc

gouging work ranged from below detectable limits (less than 0 27 µg/m3) to about 0 3 µg/m3 0.27 µg/m ) to about 0.3 µg/m .

19

slide-21
SLIDE 21

Conclusions

  • Contractor A’s employees had proper respiratory

t ti d i l ddi ( ti ) protection during cladding (coating) process.

  • Exposures during scaffold cleaning and moving ranged

from less than the AL of 2.5 µg/m3 to as much as 4 times the PEL of 5 µg/m3.

  • Based on these results employees need to wear P100

filtering face piece respirators (dust masks) or half-mask i t ith P100 filt h l i d i th respirators with P100 filters when cleaning and moving the scaffolding.

  • Employees also need coveralls and access to showers and

change rooms.

20

slide-22
SLIDE 22

Conclusions Cont.

  • Metallic spray coating produces much more hex chrome

than arc gouging does.

  • Air sampling data is very important to select respirators, PPE

d f l t and for regulatory purposes.

  • When planning jobs that involve spray coating, arc gouging,

welding or oxy acetylene cutting with high chrome materials welding or oxy acetylene cutting with high –chrome materials its important to consider the hex chrome exposures to all persons in the work area.

  • Only necessary personnel should be in the work area when

hex chrome is being generated. When possible work should b h d l d t li it th b f l be scheduled to limit the number of personnel.

  • Ventilation should be used as much as possible to reduce

exposures exposures.

21

slide-23
SLIDE 23

Conclusions Cont.

  • Employers need to decide if employees need medical

surveillance- will employees be exposed > AL for more than 30 days per year? E l d t b t i d b t h d f h h

  • Employees need to be trained about hazards of hex chrome

and the proper control methods.

  • The training should be appropriate for their tasks The video
  • The training should be appropriate for their tasks. The video

shown to Contractor B Employee’s pertained to welding and not incidental exposures such as cleaning and moving scaffolding.

  • Environmental compliance specialists should be consulted

d i th l i i th t t i l t i h during the planning since the waste material may contain hex chrome that can effect the disposal methods.

22

slide-24
SLIDE 24

Any Questions ? Any Questions ?

23

slide-25
SLIDE 25

Thank You Thank You

24