Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site - - PowerPoint PPT Presentation

harwell stakeholder group
SMART_READER_LITE
LIVE PREVIEW

Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site - - PowerPoint PPT Presentation

Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site Manager Magnox Harwell Update Safety and Environment Programme Update Future Programme Magnox Socio- Economic Scheme Safety and Environment Events; Data to


slide-1
SLIDE 1

Harwell Stakeholder Group

25 April 2019 Laura Street, Harwell Site Manager

slide-2
SLIDE 2

Magnox Harwell Update

  • Safety and

Environment

  • Programme Update
  • Future Programme
  • Magnox Socio-

Economic Scheme

slide-3
SLIDE 3

Safety and Environment

Events;

  • Data to EA forwarded after date required by EPR Permit

following change of supplier for environmental monitoring (Air samples)

  • Security x-ray scanner IRR17 compliance issue (registration)
  • F-gas refrigeration system not on site inventory
  • Environmental monitoring programme spreadsheets control

issue

slide-4
SLIDE 4

Safety and Environment

Conventional Safety

  • Total Recordable Incident Rate is Zero

– Continued focus on Target Zero;

  • Wellbeing
  • Working at Height
  • Complacency is the enemy
  • Staying Safe, focus on return to work

ENGAGE BRAIN!

POWSAs S.T.A.R. LCFs

Post-job brief

slide-5
SLIDE 5

Safety and Environment

  • Environmental Management

– New Environment Manager at Harwell/Winfrith and team expanding – Continued early engagement with EA on issues where regulatory effort (such as permit variations) will be required.

  • Environmental Monitoring

– Doses remain very low – Liquid and Gaseous Discharges remain well below permitted limits.

slide-6
SLIDE 6

Programme Update

  • LETP
  • ILW Box Store
  • NM Programme
  • 462 Retrievals/Can

Processing

  • WEP
  • Other Projects
  • Other hot topics

6

slide-7
SLIDE 7

7

LETP Remediation

  • Over 28,000 bags of

waste generated and shipped

  • Scheduled for

completion early 2020 https://youtube/NMa8wQfgxHk

slide-8
SLIDE 8

Site Works

  • Civil construction complete
  • Installation work continues
  • Vent control panel at factory for testing before

coming to site.

  • Other minor works – painting to walls and

floors; render South face; clearing snags. Test and Commissioning

  • Test and commissioning paperwork – 40%

complete

  • B462 and support teams on-board for T&C

and handover

  • Lifetime Quality Records (LTQR)– first

submission commented on

Current Progress (HIBS)

8

slide-9
SLIDE 9

462 Can Retrievals

  • 385 cans retrieved from 47 tubes in 18/19
  • FY. <238 tubes remaining.
  • RM1 restart delayed due to resource
  • availability. Technical review of radon

abatement process is making progress.

  • 692 cans processed on Head End Cell in

18/19 FY.

slide-10
SLIDE 10

462 Waste Encapsulation Plant (WEP)

  • WEP Inactive Commissioning complete.
  • Licence Instrument for WEP Active Commissioning

received from the Regulator.

  • Active Commissioning underway (commenced April 2019).
slide-11
SLIDE 11

Offsite Discharge Pipeline

  • Removal works continue and

complete in the summer.

slide-12
SLIDE 12

B220 Lab Facility

  • Characterisation start deferred until FY 2020/21
  • Asbestos removal deferred until FY 2020/21
  • Continue to develop Characterisation strategy and detail works info
  • Progress initiative for RAL to take steel cells for re-use
  • Progress NDA initiative of working with’ RAIN’ on remote monitoring

03/07/2019 16

slide-13
SLIDE 13

Legacy Waste

Consigned ~920m3 of Legacy Radioactive Waste from site during 2018/19

slide-14
SLIDE 14

Harwell – Future Programme (next 12 months)

18

462 Waste Retrievals:

  • Continue retrieving Cans and Processing through Head End Cells
  • Develop Options for POCO of tubes including sludge removal
  • Survey and potentially size reduce long cans
  • Operation of Polymer Encapsulation process in Head End cells for Problem

wastes

  • Return RM1 to service with Radon abatement system

NM Transfer Project:

  • Resume movement of CHILW drums in Novapaks
  • Continue FHISO movements of CHILW drums
  • Commission and start movements of LEU drums in Novapaks
  • Continue movement of CLDs in FHISOs
  • Start inactive commissioning of CLDs in TN Gemini
  • Continue movement of Dragon Waste in Modular Flask

Other 462:

  • Further categorisation work on RIPPLE crates.
  • Complete construction of ILW Store
  • Continue WEP Active Commissioning
slide-15
SLIDE 15

Harwell – Future Programme (next 12 months)

19

LETP Phase 2 Land Remediation:

  • Continue main remediation work, waste assay and waste

disposal Others:

  • Continue maintaining redundant facilities
  • Continue B220 decommissioning planning
  • Legacy Waste Target to consign 440 m3
slide-16
SLIDE 16

Other Hot Topics

  • Transition-

No announcement for H/W CD Continue to plan for September

  • Scope deferrals

– BEPO – B220

  • Facility Management

– Concerns around corporate stability of current provider – FM Contract re-tender

slide-17
SLIDE 17

Magnox socio-economic scheme:

2018/19 : Total Funding available across Magnox £977,678 Total spend £743,512 across all Magnox sites Harwell 2018-19 Good Neighbour funding to date: £5,780 out of £6,000 allocated/site: * Hendred Community Choir £218 * Family Fun Day – Full Steam Ahead £500 * HLRA – Table tennis Table £672 * Life Education Thames Valley “Harold and the Life Bus” Project - £840 * Young Carers Social Activities & Training £1,000 * Harwell Community Primary School – Cycle and Scooter Storage £750 * Sutton Courtney C of E Primary School - Eco Warriors Let’s Get Recycling! £1,000 HHYFC Tournament £800. Three levels of funding available: Up to £1,000 for small projects neighbouring Magnox sites Up to £10,000 capital expenditure towards a sustainable project Over £10,000 to support large projects that help to wards mitigating the impact of decommissioning Please note: When applying for Good Neighbour funding please be aware that you only have to complete the first three questions. Other application over £1k – all seven questions have to be answered Larger applications welcome – if you’re not sure about applying then please call either Emma Burwood for Good Neighbour applications or Haf Morris for anything over £1,000 – details on the website. For further information and to check if you are eligible to apply go to: www.magnoxsocioeconomic.com

slide-18
SLIDE 18

Questions?