Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site - - PowerPoint PPT Presentation
Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site - - PowerPoint PPT Presentation
Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site Manager Magnox Harwell Update Safety and Environment Programme Update Future Programme Magnox Socio- Economic Scheme Safety and Environment Events; Data to
Magnox Harwell Update
- Safety and
Environment
- Programme Update
- Future Programme
- Magnox Socio-
Economic Scheme
Safety and Environment
Events;
- Data to EA forwarded after date required by EPR Permit
following change of supplier for environmental monitoring (Air samples)
- Security x-ray scanner IRR17 compliance issue (registration)
- F-gas refrigeration system not on site inventory
- Environmental monitoring programme spreadsheets control
issue
Safety and Environment
Conventional Safety
- Total Recordable Incident Rate is Zero
– Continued focus on Target Zero;
- Wellbeing
- Working at Height
- Complacency is the enemy
- Staying Safe, focus on return to work
ENGAGE BRAIN!
POWSAs S.T.A.R. LCFs
Post-job brief
Safety and Environment
- Environmental Management
– New Environment Manager at Harwell/Winfrith and team expanding – Continued early engagement with EA on issues where regulatory effort (such as permit variations) will be required.
- Environmental Monitoring
– Doses remain very low – Liquid and Gaseous Discharges remain well below permitted limits.
Programme Update
- LETP
- ILW Box Store
- NM Programme
- 462 Retrievals/Can
Processing
- WEP
- Other Projects
- Other hot topics
6
7
LETP Remediation
- Over 28,000 bags of
waste generated and shipped
- Scheduled for
completion early 2020 https://youtube/NMa8wQfgxHk
Site Works
- Civil construction complete
- Installation work continues
- Vent control panel at factory for testing before
coming to site.
- Other minor works – painting to walls and
floors; render South face; clearing snags. Test and Commissioning
- Test and commissioning paperwork – 40%
complete
- B462 and support teams on-board for T&C
and handover
- Lifetime Quality Records (LTQR)– first
submission commented on
Current Progress (HIBS)
8
462 Can Retrievals
- 385 cans retrieved from 47 tubes in 18/19
- FY. <238 tubes remaining.
- RM1 restart delayed due to resource
- availability. Technical review of radon
abatement process is making progress.
- 692 cans processed on Head End Cell in
18/19 FY.
462 Waste Encapsulation Plant (WEP)
- WEP Inactive Commissioning complete.
- Licence Instrument for WEP Active Commissioning
received from the Regulator.
- Active Commissioning underway (commenced April 2019).
Offsite Discharge Pipeline
- Removal works continue and
complete in the summer.
B220 Lab Facility
- Characterisation start deferred until FY 2020/21
- Asbestos removal deferred until FY 2020/21
- Continue to develop Characterisation strategy and detail works info
- Progress initiative for RAL to take steel cells for re-use
- Progress NDA initiative of working with’ RAIN’ on remote monitoring
03/07/2019 16
Legacy Waste
Consigned ~920m3 of Legacy Radioactive Waste from site during 2018/19
Harwell – Future Programme (next 12 months)
18
462 Waste Retrievals:
- Continue retrieving Cans and Processing through Head End Cells
- Develop Options for POCO of tubes including sludge removal
- Survey and potentially size reduce long cans
- Operation of Polymer Encapsulation process in Head End cells for Problem
wastes
- Return RM1 to service with Radon abatement system
NM Transfer Project:
- Resume movement of CHILW drums in Novapaks
- Continue FHISO movements of CHILW drums
- Commission and start movements of LEU drums in Novapaks
- Continue movement of CLDs in FHISOs
- Start inactive commissioning of CLDs in TN Gemini
- Continue movement of Dragon Waste in Modular Flask
Other 462:
- Further categorisation work on RIPPLE crates.
- Complete construction of ILW Store
- Continue WEP Active Commissioning
Harwell – Future Programme (next 12 months)
19
LETP Phase 2 Land Remediation:
- Continue main remediation work, waste assay and waste
disposal Others:
- Continue maintaining redundant facilities
- Continue B220 decommissioning planning
- Legacy Waste Target to consign 440 m3
Other Hot Topics
- Transition-
No announcement for H/W CD Continue to plan for September
- Scope deferrals
– BEPO – B220
- Facility Management
– Concerns around corporate stability of current provider – FM Contract re-tender
Magnox socio-economic scheme:
2018/19 : Total Funding available across Magnox £977,678 Total spend £743,512 across all Magnox sites Harwell 2018-19 Good Neighbour funding to date: £5,780 out of £6,000 allocated/site: * Hendred Community Choir £218 * Family Fun Day – Full Steam Ahead £500 * HLRA – Table tennis Table £672 * Life Education Thames Valley “Harold and the Life Bus” Project - £840 * Young Carers Social Activities & Training £1,000 * Harwell Community Primary School – Cycle and Scooter Storage £750 * Sutton Courtney C of E Primary School - Eco Warriors Let’s Get Recycling! £1,000 HHYFC Tournament £800. Three levels of funding available: Up to £1,000 for small projects neighbouring Magnox sites Up to £10,000 capital expenditure towards a sustainable project Over £10,000 to support large projects that help to wards mitigating the impact of decommissioning Please note: When applying for Good Neighbour funding please be aware that you only have to complete the first three questions. Other application over £1k – all seven questions have to be answered Larger applications welcome – if you’re not sure about applying then please call either Emma Burwood for Good Neighbour applications or Haf Morris for anything over £1,000 – details on the website. For further information and to check if you are eligible to apply go to: www.magnoxsocioeconomic.com