harwell stakeholder group
play

Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site - PowerPoint PPT Presentation

Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site Manager Magnox Harwell Update Safety and Environment Programme Update Future Programme Magnox Socio- Economic Scheme Safety and Environment Events; Data to


  1. Harwell Stakeholder Group 25 April 2019 Laura Street, Harwell Site Manager

  2. Magnox Harwell Update • Safety and Environment • Programme Update • Future Programme • Magnox Socio- Economic Scheme

  3. Safety and Environment Events; • Data to EA forwarded after date required by EPR Permit following change of supplier for environmental monitoring (Air samples) • Security x-ray scanner IRR17 compliance issue (registration) • F-gas refrigeration system not on site inventory • Environmental monitoring programme spreadsheets control issue

  4. Safety and Environment Conventional Safety • Total Recordable Incident Rate is Zero – Continued focus on Target Zero; POWSAs • Wellbeing S.T.A.R. • Working at Height • Complacency is the enemy ENGAGE BRAIN! • Staying Safe, focus on return to work Post-job LCFs brief

  5. Safety and Environment • Environmental Management – New Environment Manager at Harwell/Winfrith and team expanding – Continued early engagement with EA on issues where regulatory effort (such as permit variations) will be required. • Environmental Monitoring – Doses remain very low – Liquid and Gaseous Discharges remain well below permitted limits.

  6. Programme Update • LETP • ILW Box Store • NM Programme • 462 Retrievals/Can Processing • WEP • Other Projects • Other hot topics 6

  7. LETP Remediation • Over 28,000 bags of waste generated and shipped • Scheduled for completion early 2020 https://youtube/NMa8wQfgxHk 7

  8. Current Progress (HIBS) Site Works • Civil construction complete • Installation work continues  Vent control panel at factory for testing before coming to site.  Other minor works – painting to walls and floors; render South face; clearing snags. Test and Commissioning • Test and commissioning paperwork – 40% complete • B462 and support teams on-board for T&C and handover • Lifetime Quality Records (LTQR) – first submission commented on 8

  9. 462 Can Retrievals • 385 cans retrieved from 47 tubes in 18/19 FY. <238 tubes remaining. • RM1 restart delayed due to resource availability. Technical review of radon abatement process is making progress. • 692 cans processed on Head End Cell in 18/19 FY.

  10. 462 Waste Encapsulation Plant (WEP) • WEP Inactive Commissioning complete. • Licence Instrument for WEP Active Commissioning received from the Regulator. • Active Commissioning underway (commenced April 2019).

  11. Offsite Discharge Pipeline • Removal works continue and complete in the summer.

  12. B220 Lab Facility • Characterisation start deferred until FY 2020/21 • Asbestos removal deferred until FY 2020/21 • Continue to develop Characterisation strategy and detail works info • Progress initiative for RAL to take steel cells for re-use • Progress NDA initiative of working with’ RAIN’ on remote monitoring 03/07/2019 16

  13. Legacy Waste Consigned ~920m3 of Legacy Radioactive Waste from site during 2018/19

  14. Harwell – Future Programme (next 12 months) 462 Waste Retrievals: • Continue retrieving Cans and Processing through Head End Cells • Develop Options for POCO of tubes including sludge removal • Survey and potentially size reduce long cans • Operation of Polymer Encapsulation process in Head End cells for Problem wastes • Return RM1 to service with Radon abatement system NM Transfer Project: • Resume movement of CHILW drums in Novapaks • Continue FHISO movements of CHILW drums • Commission and start movements of LEU drums in Novapaks • Continue movement of CLDs in FHISOs • Start inactive commissioning of CLDs in TN Gemini • Continue movement of Dragon Waste in Modular Flask Other 462: • Further categorisation work on RIPPLE crates. • Complete construction of ILW Store • Continue WEP Active Commissioning 18

  15. Harwell – Future Programme (next 12 months) LETP Phase 2 Land Remediation: • Continue main remediation work, waste assay and waste disposal Others: • Continue maintaining redundant facilities • Continue B220 decommissioning planning • Legacy Waste Target to consign 440 m3 19

  16. Other Hot Topics • Transition- No announcement for H/W CD Continue to plan for September • Scope deferrals – BEPO – B220 • Facility Management – Concerns around corporate stability of current provider – FM Contract re-tender

  17. Magnox socio-economic scheme: 2018/19 : Total Funding available across Magnox £977,678 Total spend £743,512 across all Magnox sites Harwell 2018-19 Good Neighbour funding to date: £5,780 out of £6,000 allocated/site: * Hendred Community Choir £218 * Family Fun Day – Full Steam Ahead £500 * HLRA – Table tennis Table £672 * Life Education Thames Valley “Harold and the Life Bus” Project - £840 * Young Carers Social Activities & Training £1,000 * Harwell Community Primary School – Cycle and Scooter Storage £750 * Sutton Courtney C of E Primary School - Eco Warriors Let’s Get Recycling! £1,000 HHYFC Tournament £800. Three levels of funding available: Up to £1,000 for small projects neighbouring Magnox sites Up to £10,000 capital expenditure towards a sustainable project Over £10,000 to support large projects that help to wards mitigating the impact of decommissioning Please note: When applying for Good Neighbour funding please be aware that you only have to complete the first three questions. Other application over £1k – all seven questions have to be answered Larger applications welcome – if you’re not sure about applying then please call either Emma Burwood for Good Neighbour applications or Haf Morris for anything over £1,000 – details on the website. For further information and to check if you are eligible to apply go to: www.magnoxsocioeconomic.com

  18. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend