Los Angeles Community College District Harbor College HARBOR TEACHER PREPARATORY ACADEMY (HTPA) Design Build Project Delivery January 13, 2015 PART 1 HTPA PROJECT DESCRIPTION HTPA Proposed Project Site N Existing HTPA Campus & Site


  1. Los Angeles Community College District Harbor College HARBOR TEACHER PREPARATORY ACADEMY (HTPA) Design Build Project Delivery January 13, 2015

  2. PART 1 HTPA PROJECT DESCRIPTION

  3. HTPA Proposed Project Site N

  4. Existing HTPA Campus & Site

  5. Existing HTPA Campus & Site Harbor College Storage Containers HTPA Classroom Modular School Administration Modular Basketball half court

  6. Existing HTPA Campus & Site Walkway and Playfield east of site Entrance to existing HTPA Campus and adjacent parking Existing HTPA T oilet Modular Existing Harbor Storage building

  7. HTPA Proposed Project Scope 38,540 sf 11 Classrooms – 14,525 sf Performing Arts- Music and Drama Classroom – 2250 sf PE/ Athletics Ancillary- Aerobics, Office and Lockers – 3888 sf Library and Media Center – 2481 sf Multipurpose Room (with Practice Gym & Platform Stage) – 6356 sf Special Education – 600 sf Food Services – 2395 sf Administration- 2200 sf Health Offices- 975 sf Maintenance & Operations Office and Support- 838 sf

  8. Harbor Storage Facility Scope 6750 sf Storage for extra books, computers, tables, chairs – 5800 sf Secure Storage for records – 800 sf

  9. HTPA T otal Authorized Project Budget Development Agreement Project Budget (03/01/14) -$ 23,495,810 Estimate HTPA Building Storage Building Total Construction 38,540 sf 6750 sf Budget cost/sf cost/sf (Contingency not Incl.) Development Agreement $371/sf $130/sf $15.18 M (03/01/14)

  10. Project Schedule Contract duration- 46 months- 24 July 2014 to 24 May 2018 Start End Activity Project Procurement Jan 2015 June 2015 Design June 2015 April 2016 Construction Dec 2016 May 2018

  11. PART 2 Current Status - Programming completed. Pending LAUSD approval. - RFQ development in progress. Release scheduled for January 16, 2015

  12. PART 3 Risks - Student drop off areas are congested during construction - Schedule delays (Procurement / DSA) - Unforeseen hazardous materials

  13. PART 4 Next Steps - RFP release scheduled for February 16, 2015 - BOT award for Design builder scheduled for June 10, 2015 - FMP&OC Presentation

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.