get ready for winter
play

Get Ready For Winter And hold on to your profits Rob Snaith 30 - PowerPoint PPT Presentation

Get Ready For Winter And hold on to your profits Rob Snaith 30 November 2016 k Housekeeping Fire alarm Toilets Phones off or silent Facilitators k Agenda 09.15 Welcome 09.20 Carry out a winter readiness health check


  1. Building the business case: worked example WC Lighting in a single-shift factory 50 wks/yr 5 days/wk Improvement measure: introduce PIR control Existing New Number of halogen lamps 8 4 Wattage 50W 50W (no change) Total wattage 400W 200W Operating hours per annum 2,500 50 (visits) x 5/60 x 5 x 50 = 1041 Total kWhpa 1,000 208 Annual Cost at 13p/kWh £130 £27 SAVING £76 per annum Cost of PIR Fitted £70 Simple Payback period 76 / 70 = 11 months k

  2. Building the business case: summary Rationale • Description of the measure • Costs including quotes • Payback • Any other benefits • Any H&S considerations • k

  3. Understanding and controlling your current energy use for space heating k

  4. Types of heat k

  5. What is thermal comfort? Different for every person – Air temperature – Radiant temperature of surfaces – Relative humidity – Air movement – Metabolic heat / activity level – Clothing – Well being k

  6. Personal comfort systems Low power devices provide • heating and cooling Claim up to 50% savings on • heating costs for offices Allow individuals to control their • own thermal-environment k

  7. What are sources of heating? People • Thermal mass • Insolation • IT • Cooling equipment • Process equipment • Heating system • k

  8. Understanding the units Energy is measured in kWh – kilowatt-hour One kWh is one unit on an electricity or gas bill A kilowatt-hour is the energy used by a 1000 watts appliance running for an hour Gas Example Electricity Example A 27kW domestic gas boiler A 1-bar electric fire has a runs at a duty rate of 30% on power rating of 1kW a cold evening so the average power rating is 8.1kW Running for one hour uses 1kWh Running for one hour uses Assuming 13p per kWh 8.1kWh = 13p per hour Assuming 4p per kWh = 32p per hour k

  9. Electric heating Some buildings will use direct resistive heating • either for direct panel heaters or air-conditioning units If you only have one electricity bill then you can make • a quick estimate that 50% of electricity is used for heating and 50% is used for all other electricity needs Some electrically heated sites will have a separate • circuit supply storage heaters on a cheaper rate. k

  10. Worked example Q: Average gas cost for last 3 years is £6,300 – how many kWh of gas is being used if last bill says the unit rate is £0.04? A: Answer gas kWh = [gas cost £] / [unit cost in £/kWh] = £6,300/£0.04 = 157,500 kWh k

  11. Worked example Q: We know that 5 x 2kW electric bar fires are also being used as supplementary heating for 8 hours on 100 days per year. • How much is this costing compared to the gas? • The unit rate for electricity is £0.12/kWh A: kWh of electricity = 10kW x 8 hours x 100 hours = 8000kWh Cost of electricity = 8000kWh x £0.12/kWh = £960 k

  12. External factors Identify other influences on your data: • Cost • Outside temperature or weather conditions e.g. degree days (www.eci.ox.ac.uk/research/energy/degreedays.php#degreeday) k

  13. Benchmarking To allow comparison between buildings it is useful • to compare kWh/m 2 /year (kilowatt-hours per square meter per year) So for a 20m x 50m factory = 1000m 2 • Considering the previous example with 157,500kWh • Consumption per m 2 = 157,500/1000 = • 157.5kWh/m 2 /year k

  14. Benchmarks for heating (CIBSE TM46) Building type Fossil-thermal typical benchmark kWh/m 2 /year General office 120 Large non food shop 170 Bar, pub 350 Hotel 330 Workshop 180 Fitness and Health Centre 440 Storage Facility 150 k

  15. Reduce uncontrolled air leakage Doors • Windows • Other draughts • Check ventilation levels are correct • for current activities k

  16. Reduce uncontrolled air leakage Consider LEV (local extract ventilation) for dusty or fume • filled environments to reduce heat losses k

  17. Consider mechanical heat recovery Air-to-Air heat exchangers can save up to 50% of heating consumption • k

  18. Heating distribution and control k

  19. What do we mean by heat distribution? The system that delivers heat from source to • point of use Usually ‘wet system’ with radiators • Or air source heat pump • Offers good potential for savings via improved • controls k

  20. Insulate pipework • – In plant rooms (easy fix velcro attachments are available for awkward flanges and bends) – Consider insulating distribution pipework if it does not contribute useful heat Keep space around space heaters free • – Avoid files, desks and furniture up against heaters – Leave 15cm between radiators and furniture Record your heating system settings • – Use a simple record sheet to record date and change made – Put dates in the diary (clock changes), Xmas holidays to change settings as needed k

  21. Warm air distribution systems May be HVAC system with gas boiler or ASHP • – Some HVAC systems can be adapted to make use of free cooling (cold outside air) and excess heat internal to the buildings (e.g. server rooms) – Consult a specialist Consider VSDs (Variable Speed Drives) for HVAC and circulation • pumps Ensure a dead band of 4 degrees C is set between heating and • cooling k

  22. Typical heating controls Time clocks • System thermostat • Localised thermostats such as thermostatic radiator valves (TRVs) • Zone controls (BEMS) • k

  23. Types of time control Time clock • – Set start and finish times each day 7 day timer • – Set for earlier start on Monday morning Optimised heating controller • – Uses inside and outside temperature sensors – Learns your building heat up time for different temperatures – Switches on as late as possible k

  24. Switch your heating off early • – Many buildings store heat effectively – People and IT can maintain the building temperature from mid-afternoon – Try moving your switch off time back an hour Consider hot-desking • – Heat from occupants is concentrated in one area – Switch off heating earlier in un-occupied areas Make sure colleagues understand controls • k

  25. Set appropriate temperatures • – Office / low activity 20 ° C – Workshop / high activity 16-18 ° C – Turning down setpoint by 1 ° C could save circa 8% Locate thermostats carefully • – Not near doors – Not in sun k

  26. Control heat gains In shops • – Large heat gains from display lighting and refrigeration In offices • – From occupants and electrical equipment In factories • – From processes such as cooking, welding In many lightweight buildings • – Solar gains through thin walls and glazing k

  27. De-stratification fans Useful for high ceiling premises with a large variation • in temperature with height and a reasonably well insulated and air tight building k

  28. Interlocked heating controls • Fast opening roller-shutter doors • Air curtains • Flexible doors • k

  29. Boiler replacement and fuel switching k

  30. Fuel switching Consider switching if you are using a high price • fuel such as oil (but has reduced recently), LPG or electricity (day tariff). Alternatives are • Natural gas • Biomass • Heat Pumps – Air, Ground or Water – source. • k

  31. Biomass Burns wood in one of three forms • Logs (Large scale, low fuel costs) • Chips • Pellets (Smaller scale, higher fuel • cost) High level of automation • Very low carbon factor • If sustainable fuel! • k

  32. Biomass – free procurement guide www.resourceefficientscotland.com/resource/ procurement-support-how-carry-out-successful-biomass-heating-project k

  33. Heat Pumps Air Source – coefficient of performance (COP) • of 2 to 3 Ground Source – COP of 3 to 5 • Move heat rather than create it • k

  34. Renewable Heat Incentive Government funded subsidy for renewable heat projects • Paid quarterly per kWh of heat produced • Rate fixed at commissioning and then paid for 20 years • (index linked) Helps pay for higher costs of renewable equipment • Typical paybacks around 8-12 years • k

  35. Radiant Heat Heat surfaces not space • k

  36. k

  37. Understanding and controlling your current energy use for lighting k

  38. How does lighting work? Type Operation Efficiency Lifetime (Lumens per in hours Watt) Incandescent/ Electric resistance heats filament to ~2500 15 1000 Tungsten degrees C in inert gas. Fluorescent High voltage used to ionise mercury into a 50-100 10,000 – Lighting vapour. This causes electrons to emit UV 20,000 photons which is converted to visible light by phosphor coating on the inside of the tube LED Voltage applied to a semiconductor junction Up to 100* 40,000 emits photons k

  39. Types of lighting Incandescent (Tungsten) CFL Halogen Fluorescent T12: 38mm 1.5” (2p) T8: 25mm 1” (1p) T5: 16mm 5 / 8 ” (5p) k

  40. Types of lighting 2 LEDs k

  41. Types of lighting 3 Discharge Lighting SON / Sodium Vapour Lamp Metal Halide k

  42. Characteristics of lighting k

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend