SLIDE 1
Geodynamics Cooper Basin Project: Status and forward plan 2010 and - - PowerPoint PPT Presentation
Geodynamics Cooper Basin Project: Status and forward plan 2010 and - - PowerPoint PPT Presentation
Geodynamics Cooper Basin Project: Status and forward plan 2010 and beyond Gerry Grove-White | Geodynamics Limited Important notice Any forward looking information in this presentation has been prepared on the basis of a number of assumptions
SLIDE 2
SLIDE 3
The Geodynamics vision
“Geodynamics will become a world-leading Australian geothermal energy company, supplying competitive zero carbon energy and base-load power”
SLIDE 4
Reminder of why we are here
- Significant global EGS resource in the
Cooper Basin
- Potential for 10,000 MW of baseload
emission free electricity generation capacity
- Long term goal of sub $100 / MWh power
cost (delivered into grid)
- Size and quality of resource outweighs
any distance concerns Long term goal of the Joint Venture with Origin Energy remains to bring this considerable energy resource to market
SLIDE 5
Reminder of why we are here
TEMPERATURE IS KING!
- Cooper Basin has hottest known
rocks of its type in the world
- Commercial viability of all renewable
sources will come down to the most efficient use of capital
- Lowest Capex per unit of useful
energy will be most competitive
- Geodynamics believes the Cooper
Basin EGS resource will be the lowest cost renewable source in Australia – delivered sub $100 / MWh
SLIDE 6
Reminder of why we are here
SLIDE 7
Recap – Past 12 months
„Proof of Concept‟ achieved
- Culmination of work to date
- Long term closed loop test between
Habanero 1 and 3
- Pumping issues overcome – invaluable
lessons learned
- Independent sign off by world leading
experts
- Important to distinguish between „Proof of
Concept‟ and commercial demonstration
- Dr. Doone Wyborn is giving a detailed paper
- n the process during the technical sessions
SLIDE 8
Recap – Past 12 months
Wells drilled at Jolokia and Savina
- Confirmation of granite body at ~3,800 m
depth
- Intersected saturated, over-pressured
fractures in granite
- Good temperatures at 4,900 m (J1)
- Progress in validating the geological
model 9 km and 19 km from Habanero
- Assist in reserves delineation
SLIDE 9
Recap – Past 12 months
Habanero 3 well control incident
- Timing unfortunate
- Successfully controlled
- Professional independent investigation
- Hydrogen embrittlement of steel casing
caused casing to fail
- Absence of complete data meant
wrong grade of steel selected in presence of H2S and CO2 concentrations
- Better to find out now than when 100
wells are operating cont…
SLIDE 10
Recap – Past 12 months
Implications of Habanero 3 Incident
- Habanero wells secured
- Different grade of steel required for well
casings
- No material impact on well cost from
different material
- Management action plan to improve
planning and QA processes
- Revised work program
- Delay to 1MW Power Plant
commissioning
- GeothermEx confirmation that „Proof of
Concept‟ remains valid despite Habanero 3 Incident
SLIDE 11
Recap – Past 12 months
Successful REDP Application
- $90 million secured
- Staged payments over project delivery
period
- Strong endorsement in the Company and
the project from the Federal Government
- Objective to deliver 25MW Commercial-
sized Demonstration Plant - minimum size to satisfy lenders
- Will lead to commercial expansion in the
Cooper Basin
SLIDE 12
Commercial-sized Demonstration Plant
Commercial demonstration plant – concept design
SLIDE 13
Timeline to Commercialisation
Key Points:
- CDP required to secure financing
- Importance of getting to FID on CDP
- Realistic expectations on rig availability and construction timeframes
- Co-incidence of transmission line commissioning and commercial expansion
SLIDE 14
Getting to FID on the CDP
Final Investment Decision to build a CDP cannot be taken until Joint Venture parties are comfortable that commercial expansion will / can occur. Need to demonstrate:
- Repeatability of process across tenement / reserves
delineation
- Heat extraction at commercial flow rates greater than
„Proof of Concept‟ tests
- Pathway to long term economics through reduced
costs
- Execution capability
SLIDE 15
Work program: 18-24 months
Complete Jolokia 1
- Stimulation
- Demonstrate injectivity rates
Drill Jolokia 2
- Stimulation
- Establish connection with J1
- Long term doublet testing
Drill well 1 – second doublet
- Location to be determined
- Fracturing at multiple levels
- Flow test
Drill well 2 – second doublet
- Demonstrate multi-fracture
drilling
- Establish connection
- Undertake flow testing
Geothermal Licences in the Cooper Basin
SLIDE 16
Technology development / deployment
The following technologies are being developed / deployed over the next 18 to 24 months:
- High temperature logging for prospective fracture zone identification
- Preferential fracturing (controlling where fractures occur) including the
basic science behind fractures and frequency of fractures within the granite
- Down hole isolation
- High temperature elastomers
- Multi fracture drilling
- Drilling technologies such as impact drilling and thermal spalation
- Near field well bore flow enhancement
- Down hole flow control
- Managed pressure and underbalanced drilling
- Well completions and pressure drop reductions
- 2 Phase expanders
- Pump technology
- Heat exchanger design and computer models
- Stibnite management
SLIDE 17