gardiner dam s historic movement and ongoing stability
play

Gardiner Dams Historic Movement and Ongoing Stability Evaluation - PowerPoint PPT Presentation

10/18/2018 10/18/2018 Gardiner Dams Historic Movement and Ongoing Stability Evaluation Jody Scammell, M.Sc., P. Eng. Director, Dam Safety and Major Structures 1 10/18/2018 2 10/18/2018 Outline South Saskatchewan River Project


  1. 10/18/2018 10/18/2018 Gardiner Dam’s Historic Movement and Ongoing Stability Evaluation Jody Scammell, M.Sc., P. Eng. Director, Dam Safety and Major Structures 1

  2. 10/18/2018 2

  3. 10/18/2018 Outline • South Saskatchewan River Project Introduction • Lake Diefenbaker Reservoir • Gardiner Dam – Foundation Conditions – Major Components – Movements – Previous Stability Evaluations • Grant Devine Dam Stability Evaluation • Expected Results – Not expected results 3

  4. 10/18/2018 SSRP Introduction Gardiner Dam Qu’Appelle River Dam 4

  5. 10/18/2018 SSRP Introduction • 1894 first consideration for large irrigation • 1968 completed • Total cost $120 million (1968 value) • Replacement value $2.41 Billion • Owned and operated by Water Security Agency • Operation, maintenance and monitoring complete by 8 onsite staff 5

  6. 10/18/2018 Lake Diefenbaker Reservoir 6

  7. 10/18/2018 Reservoir Drainage Basin • Three Regions • Effective Distribution – Eastern Rockies 50% Area / 80% Flow – Foothills 50% Area / 20% Flow – Prairies • 60% Snowmelt • 38% Rainfall runoff • 2% Glacier melt 7

  8. 10/18/2018 Reservoir Operation • Runoff patterns – Low winter flow – Spring peak, April – Summer peak, May/June – Recession, Aug/Sept 8

  9. 10/18/2018 Reservoir • Lake Diefenbaker • 225 km long (near Eston, SK) • 760 km shoreline Volume 9.25x10 9 m 3 • Usable Storage 3.95x10 9 m 3 • • Up to 58 m deep 9

  10. 10/18/2018 2013 Release • Largest flow released 1600 m 3 /s spillway • 2000 m 3 /s total • 6000 558 Lake Diefenbaker April 1, 2013 to March 31, 2014 5000 556 4000 554 Elevation (m) Flow (m3/s) 3000 552 Inflow Outflow Elevation median 2000 550 1000 548 0 546 10

  11. 10/18/2018 Gardiner Dam 11

  12. 10/18/2018 12

  13. 10/18/2018 Gardiner Dam Main (River) Major Components Embankment Plateau Embankment Coteau Creek Embankment Tunnels Spillway 13

  14. 10/18/2018 Gardiner Dam Embankments • Three zoned compacted- Coteau Creek earth filled embankments Embankment • Total Length 5000 m • Crest Elevation 562.4 m • Max height 64 m • Upper Slopes 2H:1V • Lower Slopes 85H:1V Main (River) Plateau Embankment Embankment 14

  15. 10/18/2018 Gardiner Dam Foundation 15

  16. 10/18/2018 Gardiner Dam Foundation • Till • River Sand – Eroded except on – In valley bottom abutments • Bedrock – Bearpaw Formation – Snakebite Shale – Ardkenneth Sandstone 16

  17. 10/18/2018 Gardiner Dam Foundation • Snakebite Shale Description – Upper Cretaceous Origin – Marine Deposited – Dark Grey Shale, flat horizontal lying strata – Jointed, Slickensided, and Bentonite seams – Highly Plastic – Presheared 17

  18. 10/18/2018 Gardiner Dam Foundation 18

  19. 10/18/2018 Gardiner Dam Foundation 19

  20. 10/18/2018 Gardiner Dam Movement 20

  21. 10/18/2018 Gardiner Dam Horizontal Movement • Occurring since start of construction • Shear plane located in shale foundation near the contact with the underlying sandstone – Approximately 114 m below the crest of the dam El.448 m 21

  22. 10/18/2018 Gardiner Dam Horizontal Movement • Movement rates and magnitude vary by position from the dam crest • Maximum movement rate and magnitude is occurring at toe of main embankment 22

  23. 10/18/2018 Historic Instrumentation Horizontal Movement • The movement is occurring on a defined shear plane in the shale 23

  24. 10/18/2018 Gardiner Dam Horizontal Movement • Movement rate generally slowing • On an annual frequency the movement rates indicate a trend with the reservoir 24

  25. 10/18/2018 Historic Instrumentation Time Comparison • The piezometric level fluctuates with reservoir 25

  26. 10/18/2018 Previous Analysis • 1979 • 1948-1953 – Finite element stress – Limit Equilibrium deformation analysis – Total Stress Analysis – Computational limited • 1954-1965 • 1980-2009 – Limit Equilibrium – Simple mechanical – Effective Stress Analysis model with a spring and – Redesigned as the back damper to predict analysis of local slopes movement related to historic movement 26

  27. 10/18/2018 Previous Analysis • It appeared there is a • 2009-2013 correlation between total • Analytical Model stress loading on the shale • Simple sliding block and pore water dissipation. evaluation 27

  28. 10/18/2018 Previous Analysis Next Steps What does this all mean • Detailed Finite Difference • We don’t understand the Model (FDM) movement mechanisms • Understand long term • The stability of the structure deformations and impacts is not fully understood on structures 28

  29. 10/18/2018 Detailed FDM Analysis Moving Forward Grant Devine (Alameda) Dam 2011-2014 • Similar problem as Gardiner • Process will be very similar but was moving faster 29

  30. 10/18/2018 Detailed FDM Analysis Moving Forward • Stop construction to Grant Devine (Alameda) Dam redesign • Unanticipated shear • Added toe berms displacements during construction Glacial Till (Foral/Battleford) Formation) Bedrock – interbedded sandstones, siltstones and clay shales (Ravenscrag Formation) 30

  31. 10/18/2018 Detailed FDM Analysis Moving Forward Detailed Geological Framework • Need to understand the • Develop a representative materials in the foundation model 31

  32. 10/18/2018 Detailed FDM Analysis Moving Forward 32

  33. 10/18/2018 Detailed FDM Analysis Moving Forward Start with a 2D – Establish appropriate • 2D model is required to constitutive model of soil minimize complications • Once model behavior is • Calibrate model understood then move on to – Lab tested material 3D properties – Actual deformation measurements 33

  34. 10/18/2018 Detailed FEM Analysis Moving Forward Move forward with 3D • Start with properties from calibrated 2D model • Calibrate again – Actual deformation 3D FLAC Model measurements – Measured porewater pressure Oblique Section – Shear Strain Contours 34 Cut Along Oblique Section

  35. 10/18/2018 Expected Results • Limitations • Understanding of long term movements – Not expecting be able to estimate annual • Understanding of the displacement stability of the structure – A traditional Factor of • Estimate of total Safety is not possible deformation and rate • Impact on the ancillary structures – Spillway – Relief Well Drainage Conduit 35

  36. 10/18/2018 Summary • The dam is performing well • With over 50 years of satisfactory performance • Monitoring and there is valuable lessons to maintenance activities are be learned from this project ongoing • This project is a valuable • The embankment is moving asset to the province and downstream with rates will remain to be in the slowing future 36

  37. 10/18/2018 37

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend