10/18/2018
10/18/2018
Gardiner Dam’s Historic Movement and Ongoing Stability Evaluation
Jody Scammell, M.Sc., P. Eng. Director, Dam Safety and Major Structures
1
Gardiner Dams Historic Movement and Ongoing Stability Evaluation - - PowerPoint PPT Presentation
10/18/2018 10/18/2018 Gardiner Dams Historic Movement and Ongoing Stability Evaluation Jody Scammell, M.Sc., P. Eng. Director, Dam Safety and Major Structures 1 10/18/2018 2 10/18/2018 Outline South Saskatchewan River Project
10/18/2018
Jody Scammell, M.Sc., P. Eng. Director, Dam Safety and Major Structures
1
10/18/2018
2
10/18/2018
– Foundation Conditions – Major Components – Movements – Previous Stability Evaluations
– Not expected results
3
10/18/2018
4
Gardiner Dam Qu’Appelle River Dam
10/18/2018
large irrigation
value)
Billion
Water Security Agency
and monitoring complete by 8 onsite staff
5
10/18/2018
6
10/18/2018
– Eastern Rockies – Foothills – Prairies
50% Area / 80% Flow 50% Area / 20% Flow
7
10/18/2018
– Low winter flow – Spring peak, April – Summer peak, May/June – Recession, Aug/Sept
8
10/18/2018
9
10/18/2018
10
546 548 550 552 554 556 558 1000 2000 3000 4000 5000 6000 Elevation (m) Flow (m3/s) Inflow Outflow Elevation median
Lake Diefenbaker
April 1, 2013 to March 31, 2014
10/18/2018
11
10/18/2018
12
10/18/2018
13
Plateau Embankment
Main (River) Embankment
Coteau Creek Embankment Spillway Tunnels
10/18/2018 Plateau Embankment
Main (River) Embankment
Coteau Creek Embankment
earth filled embankments
14
10/18/2018
15
10/18/2018
– Eroded except on abutments
16
– In valley bottom
– Bearpaw Formation – Snakebite Shale – Ardkenneth Sandstone
10/18/2018
– Upper Cretaceous Origin – Marine Deposited – Dark Grey Shale, flat horizontal lying strata – Jointed, Slickensided, and Bentonite seams – Highly Plastic – Presheared
17
10/18/2018
18
10/18/2018
19
10/18/2018
20
10/18/2018
the underlying sandstone – Approximately 114 m below the crest of the dam El.448 m
21
10/18/2018
magnitude vary by position from the dam crest
and magnitude is occurring at toe of main embankment
22
10/18/2018
Horizontal Movement
the shale
23
10/18/2018
slowing
the movement rates indicate a trend with the reservoir
24
10/18/2018
Time Comparison
fluctuates with reservoir
25
10/18/2018
– Limit Equilibrium – Total Stress Analysis
– Limit Equilibrium – Effective Stress Analysis – Redesigned as the back analysis of local slopes
26
– Finite element stress deformation analysis – Computational limited
– Simple mechanical model with a spring and damper to predict movement related to historic movement
10/18/2018
evaluation
27
correlation between total stress loading on the shale and pore water dissipation.
10/18/2018
What does this all mean
movement mechanisms
is not fully understood
28
Next Steps
Model (FDM)
deformations and impacts
10/18/2018
Grant Devine (Alameda) Dam 2011-2014
but was moving faster
29
10/18/2018
Grant Devine (Alameda) Dam
displacements during construction
30
redesign
Glacial Till (Foral/Battleford) Formation) Bedrock – interbedded sandstones, siltstones and clay shales (Ravenscrag Formation)
10/18/2018
Detailed Geological Framework
materials in the foundation
31
model
10/18/2018
32
10/18/2018
Start with a 2D
minimize complications
– Lab tested material properties – Actual deformation measurements
33
– Establish appropriate constitutive model of soil
understood then move on to 3D
10/18/2018
Move forward with 3D
calibrated 2D model
– Actual deformation measurements – Measured porewater pressure
34 3D FLAC Model Cut Along Oblique Section Oblique Section – Shear Strain Contours
10/18/2018
movements
stability of the structure
deformation and rate
structures – Spillway – Relief Well Drainage Conduit
35
– Not expecting be able to estimate annual displacement – A traditional Factor of Safety is not possible
10/18/2018
maintenance activities are
downstream with rates slowing
satisfactory performance there is valuable lessons to be learned from this project
asset to the province and will remain to be in the future
36
10/18/2018
37