SLIDE 1 FRA-70-14.54 I-70/I-71 Project: Phase 2E
Presented By:
January 23, 2019
SLIDE 2
- Overview
- Cooperation between Contractors
- Maintenance of Traffic
- Structures
- Utilities - Mooberry
- Environmental Commitments
Agenda
SLIDE 3
Columbus Crossroads I-70/71
SLIDE 4 Current I-70/71 Eastbound
- I-70 has 1 continuous through lane
- I-71 makes 2 lane changes
900
1700 1500
SLIDE 5 900
1700 1500
70/71 EB After Phase 2E
- I-70 will have 2 continuous through lanes
- I-71 will make 1 lane change
SLIDE 6 70/71 After Phase 4R
- I-70 will have 2 continuous through lanes
- I-71 will have 2 continuous through lanes
- Ramp traffic departs before the overlap
SLIDE 7 N Coordination with Other Projects
Livingston C
2G Coordination
- No work on I-70W until May 2019
3B Coordination
4R Coordination
- New through lane on 70E
- Livingston C
- 3rd St bridge work
- Communications/ITS
SLIDE 8
N COTA Nationwide Children’s Hospital Communication with Stakeholders
SLIDE 9 City of Columbus
- New ramp 70E to Parsons
- 70E to 18th St ramp closes
- New ramp Fulton to 70E
- Fulton 1 way from High St
- New landscaping on
Moobery and Parsons
SLIDE 10
Downtown Street Circulation
Mound WB, Fulton EB and New Ramps
SLIDE 11 Phase 1
- Main Street on ramp to WB I-70 will remain closed
- 4th & Fulton intersection to close for 2 weeks
- New ramp from 70 E to Parsons completed
MOT During Phase 2E
SLIDE 12 MOT During Phase 2E
Livingston C
- Open 70 E ramp to Parsons
- Close Third St ramp to 70 E
- Bridge work moved to later phase
SLIDE 13 Phase 2
- 60 day closure of Parsons
MOT During Phase 2E
SLIDE 14 Phase 3
- Mooberry Street construction begins -
- ne-way traffic for 60 days
MOT During Phase 2E
SLIDE 15 Phase 4
- Shift EB I-70 traffic to new EB lanes
- Construction of Fulton ramp to EB I-70
MOT During Phase 2E
SLIDE 16 Phase 5
- Open Fulton ramp to EB I-70
- Make Fulton 1-way EB from High St
- Finish freeway construction on east side of
interchange
MOT During Phase 2E
Keeping ramps open
SLIDE 17
Major Structures Overview – Retaining Walls
SLIDE 18
Major Structures Overview – Retaining Walls
I-11 - Replace wood lagging with precast concrete
SLIDE 19
Major Structures Overview – Retaining Walls
MSE Walls
SLIDE 20
Major Structures Overview – Retaining Walls
CIP walls with a precast alternate
SLIDE 21
Major Structures Overview – Retaining Walls
CIP walls without a precast alternate I-13-2 Needed a crashworthy wall at Mooberry, and the moment slab would have complicated access to utilities.
SLIDE 22
Major Structures Overview - Bridges
SLIDE 23
Major Structures – Lowest level
SLIDE 24
Major Structures – Lowest Level
FRA-70-14.98 – Built for traffic in a future phase
SLIDE 25
Major Structures – “Tunnels”
FRA-70-14.98 – Built for traffic in a future phase
SLIDE 26
Major Structures – Lowest Level
FRA-70-14.79 – Partially built due to sight distance underneath
SLIDE 27 Major Structures – “Squiggle Bridge”
FRA-70-14.61 – Complex Structure
- Large skew
- Haunched profile
- Curved ends
- Staggered cross frames
Approach slab and rear abutment were constructed in a previous phase.
SLIDE 28 MAJOR STRUCTURES
I-70 over Parsons Avenue
FRA-70-14.93 L&R – WB deck to be built in a future phase.
SLIDE 29 Parsons Ave. Bridge
BRIDGE ENHANCEMENTS
I-70 over Parsons Avenue
SLIDE 30 N ITS – Both ODOT FMS and Columbus CTSS
Livingston C
Columbus CTSS
- Down time is only allowed a few hours one day per month
- Currently Columbus is booking ahead 4 months
Temporary A and Temporary B
- Temporary A is the result of the Livingston C project being
behind schedule. Coordinate with Livingston C project.
- Temporary B is long term temporary after PID 105322
Pre-emption to be non-performed
SLIDE 31
N Drainage Upcoming Addenda
Ref 168 – 60” will be expanded to other methods besides jack and bore with steel encasement A pay item reference for Item 503 will be added for shoring bore pits Catch basin will be specified as cast in place.
SLIDE 32 70
N
Near East Side NHD Hanna Neil House
Commercial NHD
Church Delmonte Apartments
70
Former Ohio Asylum for the Blind (Columbus Health Center)
Environmental Commitments
SLIDE 33
N
70
Construction Noise Mitigation See General Notes for requirements, including provisions necessary for weekend and nighttime operations
Environmental Commitments
SLIDE 34
70
N
70
NCH Orthopedic Building NCH Research 2 Building
Environmental Commitments
SLIDE 35
Tree Removal for 3B N
Construction Debris Removed
SLIDE 36
Questions?