Forum Presenter: Julian Thomas Facilitator: Gerard Reilly April - PowerPoint PPT Presentation

North Queensland Area Plan Forum Presenter: Julian Thomas Facilitator: Gerard Reilly April 2017 Session timings Welcome Presentation - 45 minutes Questions - 15 minutes Afternoon tea - 15 minutes Group discussion


  1. North Queensland Area Plan Forum Presenter: Julian Thomas Facilitator: Gerard Reilly April 2017

  2. Session timings • Welcome • Presentation - 45 minutes • Questions - 15 minutes • Afternoon tea - 15 minutes • Group discussion - 70 minutes • Wrap-up and Q&A - 20 minutes • Close and thanks • Meet and greet with the Powerlink Board

  3. Overview • Demand and Energy - overview • Planning the network - amended standard • Deliver best solutions whether network, DSM, local generation • Challenge to manage peak demand • Why are we interested in energy? - network utilisation

  4. The role of transmission • Powerlink recognises its role to provide a secure and reliable network that can power economic growth and long term sustainability of electricity supply in Queensland.

  5. The role of transmission

  6. Approach to planning our network • Powerlink undertakes two annual 2015 Asset Management Plan planning processes: – Transmission Annual Planning Report (TAPR) – Asset Management Plan (AMP) 2016 TAPR Updated Asset Updated Risk • The Asset Management Plan aligns Condition Assessments Powerlink’s corporate direction, 2016 Asset Management Plan asset management framework to an Updated Network Updated Area integrated network investment plan. Planning Plan Strategies Information 2017 TAPR

  7. North Queensland Area Plans Cairns North Queensland (Townsville) Mackay Northern Bowen Basin

  8. Area plan development Determination and review of investment drivers and needs Planning and network optimisation Optimised needs driven investment outlook

  9. Area plan development • Updated demand and energy forecasts Determination and • Analysis of: review of investment drivers and needs – Asset condition, performance and related risks – Network capability and emerging limitations (including customer connection needs) – Competition and market impacts Planning and network – Operational impacts and constraints optimisation – Customer and consumer engagement. • Ensure compliance with system standards Optimised needs driven • Confirm pending investment decisions and investment outlook portfolio of approved projects

  10. Area plan development • Integrated review of investment needs and Determination and risks review of investment drivers and needs • Market Engagement (such as this) • Planning and network Development of investment options (network optimisation reconfiguration, non-network solution, network solution or a combination of both) • Risk and cost benefit analysis of options Optimised needs driven investment outlook

  11. Area plan development • 10 year outlook Determination and review of investment • New investment or renewal of existing assets drivers and needs • Renewal strategies include: – Additional maintenance Planning and network – Decommissioning or retirement optimisation – Refurbishment or replacement of plant (sometime with lower / higher rated equipment) – Consolidation of existing assets Optimised needs driven – Operational measures investment outlook • Non-network solutions

  12. Challenges in developing the area plans What is the future of the Energy Network in Queensland? Future generation profiles are uncertain • New de-centralised generation • Distributed generations such as residential Solar PV • Unpredictability of retirement of existing generation. New technologies make forecasting demand outlook difficult. Different levels of asset information depending on timing of risk • More certainty closer to end of life as more detailed condition becomes available.

  13. Stakeholder engagement • Given these challenges and changes to the external environment, Powerlink acknowledges participation with stakeholders to seek their early input during the planning process is vital • Area Plan forums are conducted to seek feedback from stakeholders as an input to the investment plan for our network • Focused on longer term network developments and the economic and qualitative factors influencing Powerlink’s decisions • Two Area Plans forums were held previously : – Greater Brisbane Metro Area Plan – Central to Southern Queensland Interconnector

  14. 275kV & 132kV Transmission Corridor

  15. NQ Area Plan – Network Development Townsville South Townsville South 1960 132kV circuit. Collinsville PS to Clare Townsville. Clare Legend Legend 132kV transmission line 132kV transmission line 132kV substation 132kV substation Collinsville Collinsville 275kV transmission line

  16. NQ Area Plan – Network Development Townsville South Townsville South Ross Ross 1970s-1980s 275kV SCs established between Collinsville and Ross. Clare Clare Ross 275/132kV substation established with one transformer initially (there are now three). Legend 132kV transmission line Legend 132kV substation 132kV transmission line 275kV transmission line 132kV substation Collinsville 275kV substation Strathmore 275kV transmission line Collinsville Strathmore

  17. NQ Area Plan – Network Development Townsville South Townsville South Ross Ross 2000 onwards Invicta Invicta Mill Mill 275kV supply into NQ ` upgraded - New double circuit from Strathmore to Ross Clare Clare South - Two existing SCSTs from Strathmore to Ross are paralleled for higher capacity - Strathmore 275/132kV Substation established with one transformer. Legend King Creek King Creek 132kV transmission line Legend 132kV substation 132kV transmission line Collinsville 275kV transmission line 132kV substation 275kV substation North Strathmore Collinsville 275kV transmission line Strathmore North

  18. NQ Area Plan – Network Development Townsville South Ross 2000 onwards Invicta Mill Replacement of original substations at Clare and Collinsville at adjacent sites. Clare Connection of major customers. Decommissioning of assets: - Collinsville Power Station connections Legend King Creek - Mackay to Proserpine 132kV transmission line transmission line. Legend 132kV substation 132kV transmission line Collinsville 275kV transmission line 132kV substation 275kV substation North Strathmore 275kV transmission line

  19. NQ Area Plan – Existing Network • Existing capability • Future load growth • New generation • Assets reaching end of life - Near term issues relate to the TS-CS 132kV lines • Investment Decision - Renew these assets, or decommission? - Reconfigure the network? - Non-network alternative?

  20. NQ Area Plan – Townsville • Existing capability • Major customers • Investment needs • Easement issues

  21. NQ Area Plan – Future Requirements • Appropriately reinvest in aging assets to maximise economic and social value, whilst achieving cost efficiencies • As part of these decisions, consideration is given to: – Cost of reinvestment – Enduring Need – Operational requirements and ability to perform maintenance – Alternative network and non network solutions – Need to Support load centres and major customers – Geographic diversity of supply to North Queensland – Support new connections in the area, including renewable resources – Manage the potential impact of ‘latent’ load of resource sector.

  22. Current NER Requirements National Electricity Rules Network Planning Transmission Annual Planning Report Transmission Annual Planning Report Review Possible non-network solutions identified requirement in TAPR for reinvestments for RIT-T or augmentations <$6 million Augmentation or augmentation component >$6 million Non-rule requirement Initiate RIT-T Initiate Non-network solution feasibility study process

  23. Questions?

  24. Afternoon tea

  25. NQ Area Plan - Discussion Discussion Point 1 • What factors have the potential to impact on Powerlink’s network in the next 10 years? (e.g. change in generation mix, demand levels, customer usage, new loads). What do customers need from the network? Discussion point 2 • What are the key drivers Powerlink should consider in deciding the best network (reinvest, reconfigure or decommission) or non-network solutions for this area over the next 10 years?

  26. Thank you

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.