Forum Presenter: Julian Thomas Facilitator: Gerard Reilly April - - PowerPoint PPT Presentation

forum
SMART_READER_LITE
LIVE PREVIEW

Forum Presenter: Julian Thomas Facilitator: Gerard Reilly April - - PowerPoint PPT Presentation

North Queensland Area Plan Forum Presenter: Julian Thomas Facilitator: Gerard Reilly April 2017 Session timings Welcome Presentation - 45 minutes Questions - 15 minutes Afternoon tea - 15 minutes Group discussion


slide-1
SLIDE 1

North Queensland Area Plan Forum

April 2017 Presenter: Julian Thomas Facilitator: Gerard Reilly

slide-2
SLIDE 2
  • Welcome
  • Presentation - 45 minutes
  • Questions - 15 minutes
  • Afternoon tea - 15 minutes
  • Group discussion - 70 minutes
  • Wrap-up and Q&A - 20 minutes
  • Close and thanks
  • Meet and greet with the Powerlink Board

Session timings

slide-3
SLIDE 3
  • Demand and Energy - overview
  • Planning the network - amended standard
  • Deliver best solutions whether network, DSM,

local generation

  • Challenge to manage peak demand
  • Why are we interested in energy? - network

utilisation

Overview

slide-4
SLIDE 4
  • Powerlink recognises its role to provide a

secure and reliable network that can power economic growth and long term sustainability

  • f electricity supply in Queensland.

The role of transmission

slide-5
SLIDE 5

The role of transmission

slide-6
SLIDE 6
  • Powerlink undertakes two annual

planning processes:

– Transmission Annual Planning Report (TAPR) – Asset Management Plan (AMP)

  • The Asset Management Plan aligns

Powerlink’s corporate direction, asset management framework to an integrated network investment plan.

Approach to planning our network

2015 Asset Management Plan 2016 TAPR 2016 Asset Management Plan Updated Asset Condition Updated Network Planning Information Updated Area Plan Strategies Updated Risk Assessments 2017 TAPR

slide-7
SLIDE 7

Cairns North Queensland (Townsville) Northern Bowen Basin Mackay

North Queensland Area Plans

slide-8
SLIDE 8

Area plan development

Planning and network

  • ptimisation

Determination and review of investment drivers and needs Optimised needs driven investment outlook

slide-9
SLIDE 9

Area plan development

Planning and network

  • ptimisation

Determination and review of investment drivers and needs Optimised needs driven investment outlook

  • Updated demand and energy forecasts
  • Analysis of:

– Asset condition, performance and related risks – Network capability and emerging limitations (including customer connection needs) – Competition and market impacts – Operational impacts and constraints – Customer and consumer engagement.

  • Ensure compliance with system standards
  • Confirm pending investment decisions and

portfolio of approved projects

slide-10
SLIDE 10

Area plan development

Planning and network

  • ptimisation

Determination and review of investment drivers and needs Optimised needs driven investment outlook

  • Integrated review of investment needs and

risks

  • Market Engagement (such as this)
  • Development of investment options (network

reconfiguration, non-network solution, network solution or a combination of both)

  • Risk and cost benefit analysis of options
slide-11
SLIDE 11

Area plan development

Planning and network

  • ptimisation

Determination and review of investment drivers and needs Optimised needs driven investment outlook

  • 10 year outlook
  • New investment or renewal of existing assets
  • Renewal strategies include:

– Additional maintenance – Decommissioning or retirement – Refurbishment or replacement of plant (sometime with lower / higher rated equipment) – Consolidation of existing assets – Operational measures

  • Non-network solutions
slide-12
SLIDE 12

What is the future of the Energy Network in Queensland?

Future generation profiles are uncertain

  • New de-centralised generation
  • Distributed generations such as residential Solar PV
  • Unpredictability of retirement of existing generation.

New technologies make forecasting demand outlook difficult. Different levels of asset information depending on timing of risk

  • More certainty closer to end of life as more detailed

condition becomes available.

Challenges in developing the area plans

slide-13
SLIDE 13
  • Given these challenges and changes to the external

environment, Powerlink acknowledges participation with stakeholders to seek their early input during the planning process is vital

  • Area Plan forums are conducted to seek feedback from

stakeholders as an input to the investment plan for our network

  • Focused on longer term network developments and the

economic and qualitative factors influencing Powerlink’s decisions

  • Two Area Plans forums were held previously:

– Greater Brisbane Metro Area Plan – Central to Southern Queensland Interconnector

Stakeholder engagement

slide-14
SLIDE 14

275kV & 132kV Transmission Corridor

slide-15
SLIDE 15

NQ Area Plan – Network Development

1960

132kV circuit. Collinsville PS to Townsville.

Townsville South Clare Collinsville

Townsville South Clare Collinsville

Legend 132kV transmission line 132kV substation 275kV transmission line

Legend

132kV transmission line 132kV substation

slide-16
SLIDE 16

Ross Townsville South Clare Strathmore Collinsville

NQ Area Plan – Network Development

1970s-1980s

275kV SCs established between Collinsville and Ross. Ross 275/132kV substation established with

  • ne transformer

initially (there are now three).

Clare Collinsville

Legend 132kV transmission line 132kV substation 275kV transmission line

Legend Strathmore Townsville South

132kV transmission line 132kV substation 275kV transmission line 275kV substation

Ross

slide-17
SLIDE 17

`

Ross Invicta Mill Townsville South Clare South King Creek Strathmore Collinsville North

NQ Area Plan – Network Development

Clare

Legend 132kV transmission line 132kV substation 275kV transmission line

Legend Strathmore

132kV transmission line 132kV substation 275kV transmission line 275kV substation

Townsville South Invicta Mill King Creek

2000 onwards

275kV supply into NQ upgraded

  • New double circuit from

Strathmore to Ross

  • Two existing SCSTs from

Strathmore to Ross are paralleled for higher capacity

  • Strathmore 275/132kV

Substation established with

  • ne transformer.

Ross Collinsville North

slide-18
SLIDE 18

NQ Area Plan – Network Development

Clare

Legend 132kV transmission line 132kV substation 275kV transmission line

Legend Strathmore

132kV transmission line 132kV substation 275kV transmission line 275kV substation

Townsville South Invicta Mill King Creek

2000 onwards

Replacement of original substations at Clare and Collinsville at adjacent sites. Connection of major customers. Decommissioning of assets:

  • Collinsville Power Station

connections

  • Mackay to Proserpine

transmission line.

Ross Collinsville North

slide-19
SLIDE 19

NQ Area Plan – Existing Network

  • Existing capability
  • Future load growth
  • New generation
  • Assets reaching end of

life

  • Near term issues relate

to the TS-CS 132kV lines

  • Investment Decision
  • Renew these assets, or

decommission?

  • Reconfigure the

network?

  • Non-network alternative?
slide-20
SLIDE 20

NQ Area Plan – Townsville

  • Existing capability
  • Major customers
  • Investment needs
  • Easement issues
slide-21
SLIDE 21
  • Appropriately reinvest in aging assets to

maximise economic and social value, whilst achieving cost efficiencies

  • As part of these decisions, consideration is given

to:

– Cost of reinvestment – Enduring Need – Operational requirements and ability to perform maintenance – Alternative network and non network solutions – Need to Support load centres and major customers – Geographic diversity of supply to North Queensland – Support new connections in the area, including renewable resources – Manage the potential impact of ‘latent’ load of resource sector.

NQ Area Plan – Future Requirements

slide-22
SLIDE 22

Current NER Requirements

Network Planning National Electricity Rules

Transmission Annual Planning Report

Review requirement for RIT-T Augmentation or augmentation component >$6 million Initiate RIT-T

Possible non-network solutions identified in TAPR for reinvestments

  • r augmentations <$6 million

Initiate Non-network solution feasibility study process

Transmission Annual Planning Report

Non-rule requirement

slide-23
SLIDE 23

Questions?

slide-24
SLIDE 24

Afternoon tea

slide-25
SLIDE 25

Discussion Point 1

  • What factors have the potential to impact on

Powerlink’s network in the next 10 years? (e.g. change in generation mix, demand levels, customer usage, new loads). What do customers need from the network? Discussion point 2

  • What are the key drivers Powerlink should

consider in deciding the best network (reinvest, reconfigure or decommission) or non-network solutions for this area over the next 10 years?

NQ Area Plan - Discussion

slide-26
SLIDE 26

Thank you