www.spenergynetworks.co.uk 1
SWS Developer Forum
3rd December 2015
SWS Developer Forum www.spenergynetworks.co.uk 1 SWS Consenting - - PowerPoint PPT Presentation
3 rd December 2015 SWS Developer Forum www.spenergynetworks.co.uk 1 SWS Consenting Update Update & Next Steps www.spenergynetworks.co.uk 2 South West Scotland Key Stages Landowner and Planning Consents www.spenergynetworks.co.uk
www.spenergynetworks.co.uk 1
3rd December 2015
www.spenergynetworks.co.uk 2
SWS Consenting Update
www.spenergynetworks.co.uk 3
South West Scotland Key Stages – Landowner and Planning Consents
www.spenergynetworks.co.uk 4
Stage 1 Key Infrastructure Works
www.spenergynetworks.co.uk 5
Stage 1 - Planning & Landowner Consents
Section 37 Consent
Land Agreements
Wayleaves / Servitudes
Conditions
www.spenergynetworks.co.uk 6
Stage 2 & 3 – Key Infrastructure Works
Stage 3
Black Hill Substation - Glenglass Substation 13km of 132kV steel tower line
Stage 2
New Cumnock Substation - Black Hill Substation 15km of 132kV steel tower line
www.spenergynetworks.co.uk 7
Stage 2 & 3 – Landowner & Planning Consents
Section 37 Consent
Land Agreements
Wayleaves / Servitudes
Conditions
www.spenergynetworks.co.uk 8
Stage 4 Key Infrastructure Works
New Cumnock Substation – Kendoon Cable Sealing End Compound (CSEC) – Margree Substation
Cumnock
line
line
www.spenergynetworks.co.uk 9
Stage 4 - Landowner and Planning consents
Section 37 Consent
Land Agreements
Wayleaves / Servitudes
Conditions
www.spenergynetworks.co.uk 10
Stage 5 - Key Infrastructure Works
Kendoon North Substation (On route of stage 4 Overhead – New Cumnock – Kendoon CSEC)
site (& route )
determination late 2016
www.spenergynetworks.co.uk 11
Consents Summary
www.spenergynetworks.co.uk 12
SWS Programme Update
www.spenergynetworks.co.uk 13
Project Progress Stage 1: Coylton-New Cumnock
www.spenergynetworks.co.uk 14
Construction of New Cumnock 275/132kV Substation
www.spenergynetworks.co.uk 15
Coylton-New Cumnock 275kV Overhead Line
www.spenergynetworks.co.uk 16
SP-RI-142 Kilmarnock South – Coylton 275kV (XY Route) Uprating
www.spenergynetworks.co.uk 17
Stage 2 New Cumnock - Blackhill Stage 3 Blackhill - Glenglass Stage 4 New Cumnock - Margree SWS Project Progress (Stages 2 – 4)
Network Overview Diagram
awarded, pre-construction site investigations and detailed design works in progress
commenced by SP contractor and landowners
progress
in progress
Dunhill / Blackhill and Glenglass substations
www.spenergynetworks.co.uk 18
SWS Project Progress (Stages 2 – 4)
substations
Blackhill and Glenglass Substation
substations
www.spenergynetworks.co.uk 19
SWS Project (Stages 2 – 4) Key Risks
impact to Stages 2, 3 and 4) agreements in principle reached.
www.spenergynetworks.co.uk 20
SWS Project Tree Cutting Overview Map
www.spenergynetworks.co.uk 21
SWS Project Blackhill Substation Layout
To Maybole
Kilmarnock South Uprating Kilmarnock South to Coylton 3rd Circuit
Coylton to Maybole OHL Uprating
Coylton to New Cumnock WA route Uprating Glenglass Double Bus Substation New Cumnock Extension Kendoon North 132kV GIS
TORI 134 - Kendoon North Collector Substation
new 275/132kV 240MVA transformer at New Cumnock 275kV substation
complete and progressing towards planning submission Q3 2016
TORI 134 Kendoon North GIS Substation
TORI 134 Kendoon North GIS Substation
Contracted generation 254.5MW with zero MW consented TORI 134 - Kendoon North Collector Substation
TORI 143 – Kilmarnock South Uprating
Substation and Installation of a third 1000MVA 400/275kV auto wid transformer
initial electrical design, detailed construction phasing and outage planning now complete the outcome of which now drives an October 2019 project completion date.
works system access in 2018 for developments currently contracted for 2018 will be maintained.
undertaken with affected Users on completion of the design work.
TORI 143 - Kilmarnock South 275kV and 400kV Uprating
TORI 143 - Kilmarnock South 275kV and 400kV Uprating
400kV GIS, award expected January 2016
award
in progress, Q2 2016 award
Q2 2016
consented
TORI 143 – Kilmarnock South Uprating
www.spenergynetworks.co.uk 27
TORI 158 - New Cumnock Substation Extension
and SGT2C)
TORI 158 – New Cumnock Substation Extension
www.spenergynetworks.co.uk 28
Sealing end tower south of Coylton substation. Existing X route shown, which will be replaced by new line. TORI 146 – Coylton to Maybole Circuit Uprating
TORI 146 - Coylton to Maybole Circuit Uprating
~150MW on offer awaiting acceptance
www.spenergynetworks.co.uk 29
Kilmarnock South to Coylton existing line. TORI 147 Kilmarnock South to Coylton
TORI 147 - Kilmarnock South to Coylton 3rd Circuit
SGT1 and SGT2 to 240MVA
environmental work
and impacts on system
80.6MW consented
www.spenergynetworks.co.uk 30
Project Progress (Stage 5 and Beyond)
TORI 160 - WA Route Uprating
requires reconductoring using HTLS, currently being trialled.
TORI 173 - Glenglass Double Busbar Substation
substation with eight bays.
www.spenergynetworks.co.uk 31
Project Progress (Stage 5 and Beyond)
Following the completion of the reinforcement works we will have increased the capacity in the SWS area south of Kilmarnock South Substation by 1000MVA firm capacity creating a combined Firm capacity of 2000MVA and 3000MVA non-firm.