Five Corners Sewers Phase II Construction Update
Neighborhood Meeting
Easton Middle School Auditorium
98 Columbus Avenue
May 29, 2019
1
Five Corners Sewers Phase II Construction Update Neighborhood - - PowerPoint PPT Presentation
Five Corners Sewers Phase II Construction Update Neighborhood Meeting Easton Middle School Auditorium 98 Columbus Avenue May 29, 2019 1 Welcome! Tonight's Topics: 1. Brief Background & Project Update 2. Project Schedule 3. Traffic
98 Columbus Avenue
1
2
3
Sept 2015: Design began for Phases 1 & 2 July 2017: 50% Design Complete Aug. 2017: PEF Applications to DEP April 2018: 75% Design Complete & Permitting May 2018: Annual Town Meeting – Construction Appropriation & Easements for Phase 2 Oct. 2018: Final Plans/SRF Funding Feb. 2019: SRF Permission to Advertise Apr. 2019: Received Construction Bids May 2019: Constr. Contract signed with C. Naughton Jun 2019: Begin Construction Summer/Fall 2020: Initial Sewer Connections Commence Fall 2020: Finish Construction/Final Paving
4
May 2019 Pre-Construction Meeting (with Contractor) May 2019 Public Workshop (address concerns before construction) June 2019 Sewer Construction Begins June 2019 Set up temporary water / Begin Traffic Detour on Foundry St June/July 2019 Betterment Update / Workshop
Winter shutdown (Traffic Detour Suspended) April 2020 – Fall 2020 Continued sewer construction – completed over summer. Summer/Fall 2020 Sewer Connections may begin Fall 2020 Final paving-all streets (Traffic Detour) 5
Foundry Street Eastbound Closure
6
Temporary Signals at Highland Street
7
Route 106 Eastbound Detour Route
8
Highland Plaza/Avalon Exit Detour Route
9
Foundry Street Eastbound Closure
10
Foundry St/Five Corners Area Local Access Detour
11
provide a left turn lane to Highland Street
left turn
Street
to traffic demand
12
Timing Adjustments at Foundry St (Rte 106/123)/Eastman St (Rte 106)/Robert Dr (Highland Plaza/Avalon) Timing/Phasing Adjustments at Five Corners Extensive observation and monitoring during detour operations Opportunity to adjust and be responsive to operational concerns
13
Short duration detour used for Poquanticut Ave/South St (north of Foundry) Poquanticut SB traffic maintained, NB traffic detoured via South St Remaining streets constructed with short term one-way alternating traffic with police details South St (south of Foundry) Depot St Foundry St (east of Five Corners) Bay Road (both north and south of Five Corners) Access to abutting properties maintained 48 hour notice required when impacts are necessary
14
construction)
www.fivecornerssewer.com
15
maximize business access / minimize impacts
16
Munroec@peercpc.com (802) 598-1155
Our Team is available to you twenty-four hours a day, seven days a
us using one of the above methods.
17
Chris Munroe (Field Rep) Munroec@peercpc.com (802) 598-1155
18
Munroec@peercpc.com (802) 598-1155