Five Corners Sewers Phase II Construction Update

Neighborhood Meeting

Easton Middle School Auditorium

98 Columbus Avenue

May 29, 2019

1

slide-2
SLIDE 2

Welcome!

Tonight's Topics:

  • 1. Brief Background & Project Update
  • 2. Project Schedule
  • 3. Traffic Management – (Beta)
  • 4. Public Outreach
  • 5. Next Steps

2

slide-3
SLIDE 3

Phase 2 Sewer Collection System

3

slide-4
SLIDE 4

Phase 2 Design & Construction Schedule

 Sept 2015: Design began for Phases 1 & 2  July 2017: 50% Design Complete  Aug. 2017: PEF Applications to DEP  April 2018: 75% Design Complete & Permitting  May 2018: Annual Town Meeting – Construction Appropriation & Easements for Phase 2  Oct. 2018: Final Plans/SRF Funding  Feb. 2019: SRF Permission to Advertise  Apr. 2019: Received Construction Bids May 2019: Constr. Contract signed with C. Naughton Jun 2019: Begin Construction Summer/Fall 2020: Initial Sewer Connections Commence Fall 2020: Finish Construction/Final Paving

4

slide-5
SLIDE 5

Phase 2 Detailed Construction Schedule

  • Effectively 2 construction seasons (2019/2020)
  • Sewer & water installed on Foundry (2019)
  • Onsite Representative for coordination/issues/concerns
  • Traffic Management is key (will adjust as needed)

May 2019 Pre-Construction Meeting (with Contractor) May 2019 Public Workshop (address concerns before construction) June 2019 Sewer Construction Begins June 2019 Set up temporary water / Begin Traffic Detour on Foundry St June/July 2019 Betterment Update / Workshop

  • Dec. 2019 – April 2020

Winter shutdown (Traffic Detour Suspended) April 2020 – Fall 2020 Continued sewer construction – completed over summer. Summer/Fall 2020 Sewer Connections may begin Fall 2020 Final paving-all streets (Traffic Detour) 5

slide-6
SLIDE 6

Foundry Street Detour

Foundry Street Eastbound Closure

6

slide-7
SLIDE 7

Foundry Street Detour

Temporary Signals at Highland Street

7

slide-8
SLIDE 8

Foundry Street Detour

Route 106 Eastbound Detour Route

8

slide-9
SLIDE 9

Foundry Street Detour

Highland Plaza/Avalon Exit Detour Route

9

slide-10
SLIDE 10

Foundry Street Detour

Foundry Street Eastbound Closure

10

slide-11
SLIDE 11

Foundry Street Detour

Foundry St/Five Corners Area Local Access Detour

11

slide-12
SLIDE 12

Temporary Traffic Signal

  • Foundry Street southbound widened to

provide a left turn lane to Highland Street

  • Advance phase provided for southbound

left turn

  • Pedestrian accommodation provided

Foundry Street at Highland Street

  • Two phase operation: Bay Road, Highland

Street

  • Detection provided – signal will be responsive

to traffic demand

Bay Road at Highland Street

12

slide-13
SLIDE 13

Signal Timing Adjustments

 Timing Adjustments at Foundry St (Rte 106/123)/Eastman St (Rte 106)/Robert Dr (Highland Plaza/Avalon)  Timing/Phasing Adjustments at Five Corners  Extensive observation and monitoring during detour operations  Opportunity to adjust and be responsive to operational concerns

13

slide-14
SLIDE 14

Other Construction Impacts

 Short duration detour used for Poquanticut Ave/South St (north of Foundry)  Poquanticut SB traffic maintained, NB traffic detoured via South St  Remaining streets constructed with short term one-way alternating traffic with police details  South St (south of Foundry)  Depot St  Foundry St (east of Five Corners)  Bay Road (both north and south of Five Corners)  Access to abutting properties maintained  48 hour notice required when impacts are necessary

14

slide-15
SLIDE 15

Construction Coordination / Public Outreach

  • Easton Town Crier Updates (email)
  • Variable Message Boards (in advance of and during

construction)

  • DPW Project Website:

www.fivecornerssewer.com

15

slide-16
SLIDE 16

Construction Coordination

  • Variable Message Boards (already deployed)
  • Waze Traffic Partner
  • Coordinate with Schools, Police & Fire
  • Maintain access to all properties –
  • Weekly coordination with Police Details to

maximize business access / minimize impacts

  • Extra customized signage as needed
  • Highland Street Detour – Police Presence

16

slide-17
SLIDE 17

Public Inquiries - Points of Contact

  • DPW Project Website: www.fivecornerssewer.com
  • Email: fivecorners@easton.ma.us
  • Phone: (888) 527-6797
  • Onsite/Field Contact: Chris Munroe (Field Rep)

Munroec@peercpc.com (802) 598-1155

Our Team is available to you twenty-four hours a day, seven days a

  • week. Should you have any questions or concerns, please reach out to

us using one of the above methods.

17

slide-18
SLIDE 18

Next Steps

  • Construction Begins:
  • Week of May 28th – Construction Staging
  • Week of June 3rd – Begin Temporary Water System
  • Immediately Following:
  • Set up traffic detour:
  • 1 lane traffic on Foundry (westbound)
  • Detour on Highland (eastbound)
  • Betterment Update Workshop
  • Return your Sewer Service Form to:

Chris Munroe (Field Rep) Munroec@peercpc.com (802) 598-1155

18

slide-19
SLIDE 19

Questions / Discussion

  • DPW Project Website: www.fivecornerssewer.com
  • Email: fivecorners@easton.ma.us
  • Phone: (888) 527-6797
  • Onsite/Field Contact: Chris Munroe (Field Rep)

Munroec@peercpc.com (802) 598-1155

19