BIA Meeting Caradoc Street (Co. Rd 81) Reconstruction
March 27, 2019
Caradoc Street (Co. Rd 81) Reconstruction March 27, 2019 - - PowerPoint PPT Presentation
BIA Meeting Caradoc Street (Co. Rd 81) Reconstruction March 27, 2019 Construction Limits Scope of Work Roadwork Storm Sewers Sanitary Sewers and Services Watermains and Services Landscaping Features Utility Pole
March 27, 2019
Roadwork Storm Sewers Sanitary Sewers and Services Watermains and Services Landscaping Features Utility Pole Upgrades
Bury aerial hydro and Rogers service crossings to
east side
Traffic Signal
Union Gas – Start April 22 Entegrus – June for placement of new taller
Rogers – After civil contractor installs duct,
Civil Works
July 1dewatering and temporary watermain July 15th in-water work
Signs to be erected that will direct the public to the
various commercial establishments on Caradoc Street and on Front Street
Size of signs is up for discussion Text on signs to be provided by BIA ie)
TSC Kathy’s Country Kitchen Linda’s Nails Parking
Number & Location of signs to be determined
Questions?