Federal Way Link Extension Project Update 3/28/2019 Subhead - - PowerPoint PPT Presentation

federal way link extension
SMART_READER_LITE
LIVE PREVIEW

Federal Way Link Extension Project Update 3/28/2019 Subhead - - PowerPoint PPT Presentation

Federal Way Link Extension Project Update 3/28/2019 Subhead Bullet 2 3 4 5 6 Project Financials Sound Transit Baseline Budget: $2.451B FTA Required Additional Contingency (P65) $460M FFGA Project Budget: $3.161B Includes: 20


slide-1
SLIDE 1

Federal Way Link Extension

Project Update

3/28/2019

slide-2
SLIDE 2

2

Subhead

  • Bullet
slide-3
SLIDE 3

3

slide-4
SLIDE 4

4

slide-5
SLIDE 5

5

slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

Project Financials

Sound Transit Baseline Budget: $2.451B FTA Required Additional Contingency (P65) $460M FFGA Project Budget: $3.161B

  • Includes: 20 LRV’s, financing cost and additional contingency

Federal Share – 25% of $3.161B = $790M

slide-8
SLIDE 8

8

Top Risks

  • Federal Funding Uncertainty
  • 3rd Party Approvals
  • Property Acquisition
  • Construction Market Conditions
  • Differing Site Conditions
slide-9
SLIDE 9

9

Next Steps

TBD: FTA Approves Engineering Q2 2019: Sound Transit submits FFGA Application Q2 2019: Board considers Design Build Contract Q3 2019: FTA and Sound Transit execute FFGA 2020 - Complete ROW Acquisition 2024 - Begin Revenue Service

slide-10
SLIDE 10

Thank you.

soundtransit.org