Agenda

  • Section 1 - Facilities Project Update
  • Section 2 - Demographics Report
  • Section 3 - Proposed Prioritization Plan
  • Section 4 - Proposed Bond Resolution
  • Section 5 - Polling and Bond Planning Timeline
  • Section 6 - DUSD Growth
  • Section 7 - Recommendations

2

slide-3
SLIDE 3

Facilities Updates

Frederiksen Elementary School Murray Elementary School Dublin High School Engineering/Science Building

3

slide-4
SLIDE 4

Frederiksen Elementary School

4

slide-5
SLIDE 5

Murray Elementary School

5

slide-6
SLIDE 6

Murray Elementary School

6

slide-7
SLIDE 7

Science and Engineering Building

7

slide-8
SLIDE 8

Facilities Updates

8

slide-9
SLIDE 9

9

slide-10
SLIDE 10

10

slide-11
SLIDE 11

11

slide-12
SLIDE 12

12

slide-13
SLIDE 13

13

slide-14
SLIDE 14

14

slide-15
SLIDE 15

15

slide-16
SLIDE 16

16

slide-17
SLIDE 17

17

slide-18
SLIDE 18

18

slide-19
SLIDE 19

19

slide-20
SLIDE 20

20

slide-21
SLIDE 21

21

slide-22
SLIDE 22

22

slide-23
SLIDE 23

23

slide-24
SLIDE 24

24

slide-25
SLIDE 25

Staff Recommendations

25

  • Build a 6-8 middle school at Dublin Crossings
  • Complete New High School, Phase II
  • Rebuild Nielsen Elementary School
  • Build permanent classrooms and renovate

cafeteria at Dougherty Elementary

slide-26
SLIDE 26

Staff Recommendations

  • Technology Upgrade Districtwide
  • Districtwide Safety
  • Cottonwood Creek Gym and Additional

Program Support

26

slide-27
SLIDE 27

27

Recommendation

  • Staff recommends that the Board of Trustees
  • rder a Bond Election for March 2020 in the

amount of $290 Million to fund priority District projects.

slide-28
SLIDE 28

Proposed Implementation Plan

28

slide-29
SLIDE 29

Proposed Bond Resolution

  • Proposed Bond Measure Resolution -

March 2020

29

slide-30
SLIDE 30

30

slide-31
SLIDE 31

31

slide-32
SLIDE 32

32

slide-33
SLIDE 33

33

slide-34
SLIDE 34

DUSD Growth

* Current enrollment data provided by the district ** All enrollment data from ed-data.org For comparison, DUSD 17/18 enrollment was 11,294 (165% over 0/10 enrollment numbers)

DISTRICT 09/10 ENROLLMENT CURRENT ENROLLMENT PERCENT CHANGE GO DEBT AS OF JUNE 30, 2018 LIVERMORE* 12,989 13,932 (19/20) 7.3 148,505,000 SAN RAMON* 27,937 31,924 (19/20) 14.3 411,375,000 FREMONT** 32,304 35,777 (17/18) 10.7 381,700,000 CASTRO VALLEY** 8,922 9,312 (17/18) 4.4 113,736,361 OAKLAND** 46,616 50,231 (17/18) 7.7 905,315,000 DUBLIN* 4,257 12,695 (19/20) 198.2 437,094,766 PLEASANTON* 14,838 14,693 (19/20)

  • 0.97

93,645,035

slide-35
SLIDE 35

Staff Recommendations

35

  • Build a 6-8 middle school at Dublin Crossings
  • Complete New High School, Phase II
  • Rebuild Nielsen Elementary School
  • Build permanent classrooms and renovate

cafeteria at Dougherty Elementary

slide-36
SLIDE 36

Staff Recommendations

  • Technology Upgrade Districtwide
  • Districtwide Safety
  • Cottonwood Creek Gym and Additional

Program Support

36

slide-37
SLIDE 37

37

Recommendation

  • Staff recommends that the Board of Trustees
  • rder a Bond Election for March 2020 in the

amount of $290 Million to fund priority District projects.