Extended Detention Basin Design w w w. t r a n s p o r t a t i o n - - PowerPoint PPT Presentation

extended detention basin design
SMART_READER_LITE
LIVE PREVIEW

Extended Detention Basin Design w w w. t r a n s p o r t a t i o n - - PowerPoint PPT Presentation

Extended Detention Basin Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 1 Extended Detention w w w. t r a n s p o r t a t i o n . o h i o . g o v 2 Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and


slide-1
SLIDE 1

w w w. t r a n s p o r t a t i o n . o h i o . g o v

1

Extended Detention Basin Design

slide-2
SLIDE 2

w w w. t r a n s p o r t a t i o n . o h i o . g o v

2

Extended Detention

slide-3
SLIDE 3

w w w. t r a n s p o r t a t i o n . o h i o . g o v

3

Extended Detention Basin

L&D Vol. 2 Section 1117.3 Provides quality and quantity treatment

slide-4
SLIDE 4

w w w. t r a n s p o r t a t i o n . o h i o . g o v

4

Extended Detention Basin Treatment Processes

slide-5
SLIDE 5

w w w. t r a n s p o r t a t i o n . o h i o . g o v

5

Design Process

Treatment Goals Preliminary Det. Basin Sizing Siting Analysis

  • Det. Basin Shape and Detailed Sizing

Water Quality Outlet Primary Outlet Overflow Weir Other Considerations

slide-6
SLIDE 6

w w w. t r a n s p o r t a t i o n . o h i o . g o v

6

Siting Analysis - Considerations

Space Enough R/W treatment Tributary area too large? Safety Environmental impacts Floodplain cut/fill R/W acquisition Vehicle access

slide-7
SLIDE 7

w w w. t r a n s p o r t a t i o n . o h i o . g o v

7

Siting Analysis

It can be difficult to find space. Intersections Interchanges R/W acquisition Underground detention

slide-8
SLIDE 8

w w w. t r a n s p o r t a t i o n . o h i o . g o v

8

Design Process

Treatment Goals Preliminary Det. Basin Sizing Siting Analysis

  • Det. Basin Shape and Detailed Sizing

Water Quality Outlet Primary Outlet Overflow Weir Other Considerations

slide-9
SLIDE 9

w w w. t r a n s p o r t a t i o n . o h i o . g o v

9

Detention Basin Sizing

Calculate WQV based on tributary area WQV must be between lowest outlet primary outlet (10-yr) 10% WQV additional for forebay

Dead storage

10% WQV additional for micropool

Dead storage

slide-10
SLIDE 10

w w w. t r a n s p o r t a t i o n . o h i o . g o v

10

Project Example - WQV

slide-11
SLIDE 11

w w w. t r a n s p o r t a t i o n . o h i o . g o v

11

Stage / Storage Curve

slide-12
SLIDE 12

w w w. t r a n s p o r t a t i o n . o h i o . g o v

12

Project Example - WQV

slide-13
SLIDE 13

w w w. t r a n s p o r t a t i o n . o h i o . g o v

13

Project Example - Forebay

slide-14
SLIDE 14

w w w. t r a n s p o r t a t i o n . o h i o . g o v

14

Project Example - Forebay

slide-15
SLIDE 15

w w w. t r a n s p o r t a t i o n . o h i o . g o v

15

Project Example - Micropool

slide-16
SLIDE 16

w w w. t r a n s p o r t a t i o n . o h i o . g o v

16

Project Example - Micropool

slide-17
SLIDE 17

w w w. t r a n s p o r t a t i o n . o h i o . g o v

17

Design Process

Treatment Goals Preliminary Det. Basin Sizing Siting Analysis

  • Det. Basin Shape and Detailed Sizing

Water Quality Outlet Primary Outlet Overflow Weir Other Considerations

slide-18
SLIDE 18

w w w. t r a n s p o r t a t i o n . o h i o . g o v

18

Water Quality Outlet Design

Drain WQV in 48 hours or more 50% of WQV or less drained in 1/3rd of the drain time

0.422 ac-ft * 50% = 0.211 ac-ft 48 hrs * 1/3 = 16 hrs

Provide time for sedimentation

slide-19
SLIDE 19

w w w. t r a n s p o r t a t i o n . o h i o . g o v

19

Water Quality Outlet Design

Orifices

slide-20
SLIDE 20

w w w. t r a n s p o r t a t i o n . o h i o . g o v

20

Water Quality Outlet Design

A Hydrograph drawdown curve is necessary Calculate a stage / discharge curve Or Use Pond Pack or HydroCAD

Pond Pack is part of Bentley Hydraulics Suite

slide-21
SLIDE 21

w w w. t r a n s p o r t a t i o n . o h i o . g o v

21

Project Example – WQ Outlet

slide-22
SLIDE 22

w w w. t r a n s p o r t a t i o n . o h i o . g o v

22

Design Process

Treatment Goals Preliminary Det. Basin Sizing Siting Analysis

  • Det. Basin Shape and Detailed Sizing

Water Quality Outlet Primary Outlet Overflow Weir Other Considerations

slide-23
SLIDE 23

w w w. t r a n s p o r t a t i o n . o h i o . g o v

23

Outlet Structure

3 parts of detention basin outlet

Water quality outlet(s)

Slowly draw down the WQV

Primary outlet(s)

Convey the 10-yr design storm (L&D Vol. 2, 1117.3.3

Overflow weir

Convey the 25-yr design storm (L&D Vol. 2, 1104.2.2

slide-24
SLIDE 24

w w w. t r a n s p o r t a t i o n . o h i o . g o v

24

ODOT SCD WQ-1.1

Orifices Grate Pipe Water Quality Outlets Primary Outlets

slide-25
SLIDE 25

w w w. t r a n s p o r t a t i o n . o h i o . g o v

25

Project Example – WQ Outlet

No “Cleaning” above 799.00’

slide-26
SLIDE 26

w w w. t r a n s p o r t a t i o n . o h i o . g o v

26

Primary Outlet Design

Size pipe discharging from catch basin for the 10-yr storm Set the catch basin grate elevation Confirm that the grate has the capacity to pass the 10-yr storm

slide-27
SLIDE 27

w w w. t r a n s p o r t a t i o n . o h i o . g o v

27

Project Example – WQ Outlet

Discharge Pipe

slide-28
SLIDE 28

w w w. t r a n s p o r t a t i o n . o h i o . g o v

28

Primary Outlet Design

Size pipe discharging from catch basin for the 10-yr storm Set the catch basin grate elevation Confirm that the grade has the capacity to pass the 10-yr storm

slide-29
SLIDE 29

w w w. t r a n s p o r t a t i o n . o h i o . g o v

29

Project Example – Grate Elevation

slide-30
SLIDE 30

w w w. t r a n s p o r t a t i o n . o h i o . g o v

30

Project Example – Grate Elevation

slide-31
SLIDE 31

w w w. t r a n s p o r t a t i o n . o h i o . g o v

31

14.79 cfs 1.25 ft

slide-32
SLIDE 32

w w w. t r a n s p o r t a t i o n . o h i o . g o v

32

Overflow Weir Elevation

Grate elevation = 799.0 ft Head needed to pass 14.79 cfs = 1.25 ft Overflow weir elevation:

799.0 ft + 1.25 ft = 800.25 ft

slide-33
SLIDE 33

w w w. t r a n s p o r t a t i o n . o h i o . g o v

33

Project Example – Overflow Weir

25-yr peak flow = 16.53 cfs Assume top of basin is 0.5 ft higher than overflow weir Weir elevation = 800.25 ft Top of basin = 800.25 ft + 0.5 ft = 800.75 ft

slide-34
SLIDE 34

w w w. t r a n s p o r t a t i o n . o h i o . g o v

34

Project Example – Overflow Weir

Q = CLH1.5

Q = 16.53 cfs C = 3 (L&D Vol. 2, 1102.3.4) H = 800.75 ft – 800.25 ft = 0.5 ft

16.53 cfs = 3 * L * 0.51.5 L = 15.6 ft

slide-35
SLIDE 35

w w w. t r a n s p o r t a t i o n . o h i o . g o v

35

Project Example – Overflow Weir

slide-36
SLIDE 36

w w w. t r a n s p o r t a t i o n . o h i o . g o v

36

Overflow Weir

Flow rates over the 25-yr storm may

  • vertop the detention basin

uncontrolled. Consider erosion / scour protection Consider catastrophic failure

slide-37
SLIDE 37

w w w. t r a n s p o r t a t i o n . o h i o . g o v

37

Design Process

Treatment Goals Preliminary Det. Basin Sizing Siting Analysis

  • Det. Basin Shape and Detailed Sizing

Water Quality Outlet Primary Outlet Overflow Weir Other Considerations

slide-38
SLIDE 38

w w w. t r a n s p o r t a t i o n . o h i o . g o v

38

Consider Catch Basin Invert

Pipe Invert Orifice Invert

slide-39
SLIDE 39

w w w. t r a n s p o r t a t i o n . o h i o . g o v

39

Call Out Catch Basin Invert

slide-40
SLIDE 40

w w w. t r a n s p o r t a t i o n . o h i o . g o v

40

Other Det. Basin Considerations

Velocity / Scour Anti-Seep Collars Safety Slope Stability and Item 670 Maintenance Access FEMA Floodplain ODNR Dam Permit?

slide-41
SLIDE 41

w w w. t r a n s p o r t a t i o n . o h i o . g o v

41

Velocity / Scour

slide-42
SLIDE 42

w w w. t r a n s p o r t a t i o n . o h i o . g o v

42

Anti-Seep Collars

Reference: Dept. of Interior, 1982

slide-43
SLIDE 43

w w w. t r a n s p o r t a t i o n . o h i o . g o v

43

Anti-Seep Collars

ODOT Standard Drawing WQ-1.2

slide-44
SLIDE 44

w w w. t r a n s p o r t a t i o n . o h i o . g o v

44

Project Example – Collar Design

10-yr Elev. 800.25 ft Berm Slope 4:1 Pipe Dia. 24” Pipe Slope 0.005 ft/ft Pipe Inv. 795.0 ft Saturated Zone

slide-45
SLIDE 45

w w w. t r a n s p o r t a t i o n . o h i o . g o v

45

Project Example – Collar Design

10-yr Elev. 800.25 ft Pipe Inv. 795.0 ft Pipe Dia. 24” Pipe Slope 0.005 ft/ft Ls = 42.86 ft 10 ft Berm Slope 4:1

slide-46
SLIDE 46

w w w. t r a n s p o r t a t i o n . o h i o . g o v

46

Project Example – Collar Design

slide-47
SLIDE 47

w w w. t r a n s p o r t a t i o n . o h i o . g o v

47

Safety

Detention basins are safety risks Clear zone: grading and 12” ponding Drowning hazard Local requirements? Fencing, trash rack, aquatic bench Impacts to upstream or downstream flooding

slide-48
SLIDE 48

w w w. t r a n s p o r t a t i o n . o h i o . g o v

48

Slope Stability

Do not locate on uncompacted fill or steep slopes (2:1 or more). Vegetate sides of basin Item 670, Slope Erosion Protection Don’t plant grass under water

Forebay Micropool

slide-49
SLIDE 49

w w w. t r a n s p o r t a t i o n . o h i o . g o v

49

Maintenance Access

Regular maintenance necessary Flat bench wide enough for a truck Grass needs to be mowed Woody vegetation cut from berm Regular unclogging of WQ outlet

Every 6 months

slide-50
SLIDE 50

w w w. t r a n s p o r t a t i o n . o h i o . g o v

50

Maintenance Access

slide-51
SLIDE 51

w w w. t r a n s p o r t a t i o n . o h i o . g o v

51

FEMA Floodplain

No BMPs in FEMA Floodplain

Floodplains have open space for a reason

No fill in FEMA Floodplain

Unless compensatory cut/fill analysis

Confirm limits of det. basin berms

  • utside floodplain
slide-52
SLIDE 52

w w w. t r a n s p o r t a t i o n . o h i o . g o v

52

ODNR Dam Permit

Only for big detention basins No permit needed if:

<10’ Berm and <50 ac-ft storage; or < 15 ac-ft storage; or < 6’ Berm

slide-53
SLIDE 53

w w w. t r a n s p o r t a t i o n . o h i o . g o v

53

Re-Run the Numbers!

Many iterations After values are set, re-run the analyses and check

slide-54
SLIDE 54

w w w. t r a n s p o r t a t i o n . o h i o . g o v

54

BMP Calcs Spreadsheet

slide-55
SLIDE 55

w w w. t r a n s p o r t a t i o n . o h i o . g o v

55

Sample Plan Note W106

slide-56
SLIDE 56

w w w. t r a n s p o r t a t i o n . o h i o . g o v

56

Questions ?

Jon Prier, P.E. jonathan.prier@dot.ohio.gov 614-644-1876