extended detention basin design
play

Extended Detention Basin Design w w w. t r a n s p o r t a t i o n - PowerPoint PPT Presentation

Extended Detention Basin Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 1 Extended Detention w w w. t r a n s p o r t a t i o n . o h i o . g o v 2 Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and


  1. Extended Detention Basin Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 1

  2. Extended Detention w w w. t r a n s p o r t a t i o n . o h i o . g o v 2

  3. Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and quantity treatment w w w. t r a n s p o r t a t i o n . o h i o . g o v 3

  4. Extended Detention Basin Treatment Processes w w w. t r a n s p o r t a t i o n . o h i o . g o v 4

  5. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 5

  6. Siting Analysis - Considerations Space Enough R/W treatment Tributary area too large? Safety Environmental impacts Floodplain cut/fill R/W acquisition Vehicle access w w w. t r a n s p o r t a t i o n . o h i o . g o v 6

  7. Siting Analysis It can be difficult to find space. Intersections Interchanges R/W acquisition Underground detention w w w. t r a n s p o r t a t i o n . o h i o . g o v 7

  8. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 8

  9. Detention Basin Sizing Calculate WQ V based on tributary area WQ V must be between lowest outlet primary outlet (10-yr) 10% WQ V additional for forebay Dead storage 10% WQ V additional for micropool Dead storage w w w. t r a n s p o r t a t i o n . o h i o . g o v 9

  10. Project Example - WQ V w w w. t r a n s p o r t a t i o n . o h i o . g o v 10

  11. Stage / Storage Curve w w w. t r a n s p o r t a t i o n . o h i o . g o v 11

  12. Project Example - WQ V w w w. t r a n s p o r t a t i o n . o h i o . g o v 12

  13. Project Example - Forebay w w w. t r a n s p o r t a t i o n . o h i o . g o v 13

  14. Project Example - Forebay w w w. t r a n s p o r t a t i o n . o h i o . g o v 14

  15. Project Example - Micropool w w w. t r a n s p o r t a t i o n . o h i o . g o v 15

  16. Project Example - Micropool w w w. t r a n s p o r t a t i o n . o h i o . g o v 16

  17. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 17

  18. Water Quality Outlet Design Drain WQ V in 48 hours or more 50% of WQ V or less drained in 1/3 rd of the drain time 0.422 ac-ft * 50% = 0.211 ac-ft 48 hrs * 1/3 = 16 hrs Provide time for sedimentation w w w. t r a n s p o r t a t i o n . o h i o . g o v 18

  19. Water Quality Outlet Design Orifices w w w. t r a n s p o r t a t i o n . o h i o . g o v 19

  20. Water Quality Outlet Design A Hydrograph drawdown curve is necessary Calculate a stage / discharge curve Or Use Pond Pack or HydroCAD Pond Pack is part of Bentley Hydraulics Suite w w w. t r a n s p o r t a t i o n . o h i o . g o v 20

  21. Project Example – WQ Outlet w w w. t r a n s p o r t a t i o n . o h i o . g o v 21

  22. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 22

  23. Outlet Structure 3 parts of detention basin outlet Water quality outlet(s) Slowly draw down the WQ V Primary outlet(s) Convey the 10-yr design storm (L&D Vol. 2, 1117.3.3 Overflow weir Convey the 25-yr design storm (L&D Vol. 2, 1104.2.2 w w w. t r a n s p o r t a t i o n . o h i o . g o v 23

  24. ODOT SCD WQ-1.1 Grate Primary Outlets Water Orifices Quality Outlets Pipe w w w. t r a n s p o r t a t i o n . o h i o . g o v 24

  25. Project Example – WQ Outlet No “Cleaning” above 799.00’ w w w. t r a n s p o r t a t i o n . o h i o . g o v 25

  26. Primary Outlet Design Size pipe discharging from catch basin for the 10-yr storm Set the catch basin grate elevation Confirm that the grate has the capacity to pass the 10-yr storm w w w. t r a n s p o r t a t i o n . o h i o . g o v 26

  27. Project Example – WQ Outlet Discharge Pipe w w w. t r a n s p o r t a t i o n . o h i o . g o v 27

  28. Primary Outlet Design Size pipe discharging from catch basin for the 10-yr storm Set the catch basin grate elevation Confirm that the grade has the capacity to pass the 10-yr storm w w w. t r a n s p o r t a t i o n . o h i o . g o v 28

  29. Project Example – Grate Elevation w w w. t r a n s p o r t a t i o n . o h i o . g o v 29

  30. Project Example – Grate Elevation w w w. t r a n s p o r t a t i o n . o h i o . g o v 30

  31. 1.25 ft 14.79 cfs w w w. t r a n s p o r t a t i o n . o h i o . g o v 31

  32. Overflow Weir Elevation Grate elevation = 799.0 ft Head needed to pass 14.79 cfs = 1.25 ft Overflow weir elevation: 799.0 ft + 1.25 ft = 800.25 ft w w w. t r a n s p o r t a t i o n . o h i o . g o v 32

  33. Project Example – Overflow Weir 25-yr peak flow = 16.53 cfs Assume top of basin is 0.5 ft higher than overflow weir Weir elevation = 800.25 ft Top of basin = 800.25 ft + 0.5 ft = 800.75 ft w w w. t r a n s p o r t a t i o n . o h i o . g o v 33

  34. Project Example – Overflow Weir Q = CLH 1.5 Q = 16.53 cfs C = 3 (L&D Vol. 2, 1102.3.4) H = 800.75 ft – 800.25 ft = 0.5 ft 16.53 cfs = 3 * L * 0.5 1.5 L = 15.6 ft w w w. t r a n s p o r t a t i o n . o h i o . g o v 34

  35. Project Example – Overflow Weir w w w. t r a n s p o r t a t i o n . o h i o . g o v 35

  36. Overflow Weir Flow rates over the 25-yr storm may overtop the detention basin uncontrolled. Consider erosion / scour protection Consider catastrophic failure w w w. t r a n s p o r t a t i o n . o h i o . g o v 36

  37. Design Process Treatment Goals Preliminary Det. Basin Sizing Siting Analysis Det. Basin Shape and Detailed Sizing Water Quality Outlet Primary Outlet Overflow Weir Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 37

  38. Consider Catch Basin Invert Orifice Invert Pipe Invert w w w. t r a n s p o r t a t i o n . o h i o . g o v 38

  39. Call Out Catch Basin Invert w w w. t r a n s p o r t a t i o n . o h i o . g o v 39

  40. Other Det. Basin Considerations Velocity / Scour Anti-Seep Collars Safety Slope Stability and Item 670 Maintenance Access FEMA Floodplain ODNR Dam Permit? w w w. t r a n s p o r t a t i o n . o h i o . g o v 40

  41. Velocity / Scour w w w. t r a n s p o r t a t i o n . o h i o . g o v 41

  42. Anti-Seep Collars Reference: Dept. of Interior, 1982 w w w. t r a n s p o r t a t i o n . o h i o . g o v 42

  43. Anti-Seep Collars ODOT Standard Drawing WQ-1.2 w w w. t r a n s p o r t a t i o n . o h i o . g o v 43

  44. Project Example – Collar Design Berm Slope 4:1 10-yr Elev. 800.25 ft Pipe Inv. Pipe Dia. 24” 795.0 ft Saturated Pipe Slope 0.005 ft/ft Zone w w w. t r a n s p o r t a t i o n . o h i o . g o v 44

  45. Project Example – Collar Design Berm Slope 4:1 10-yr Elev. 800.25 ft 10 ft Pipe Inv. Pipe Dia. 24” 795.0 ft Pipe Slope 0.005 ft/ft Ls = 42.86 ft w w w. t r a n s p o r t a t i o n . o h i o . g o v 45

  46. Project Example – Collar Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 46

  47. Safety Detention basins are safety risks Clear zone: grading and 12” ponding Drowning hazard Local requirements? Fencing, trash rack, aquatic bench Impacts to upstream or downstream flooding w w w. t r a n s p o r t a t i o n . o h i o . g o v 47

  48. Slope Stability Do not locate on uncompacted fill or steep slopes (2:1 or more). Vegetate sides of basin Item 670, Slope Erosion Protection Don’t plant grass under water Forebay Micropool w w w. t r a n s p o r t a t i o n . o h i o . g o v 48

  49. Maintenance Access Regular maintenance necessary Flat bench wide enough for a truck Grass needs to be mowed Woody vegetation cut from berm Regular unclogging of WQ outlet Every 6 months w w w. t r a n s p o r t a t i o n . o h i o . g o v 49

  50. Maintenance Access w w w. t r a n s p o r t a t i o n . o h i o . g o v 50

  51. FEMA Floodplain No BMPs in FEMA Floodplain Floodplains have open space for a reason No fill in FEMA Floodplain Unless compensatory cut/fill analysis Confirm limits of det. basin berms outside floodplain w w w. t r a n s p o r t a t i o n . o h i o . g o v 51

  52. ODNR Dam Permit Only for big detention basins No permit needed if: <10’ Berm and <50 ac-ft storage; or < 15 ac-ft storage; or < 6’ Berm w w w. t r a n s p o r t a t i o n . o h i o . g o v 52

  53. Re-Run the Numbers! Many iterations After values are set, re-run the analyses and check w w w. t r a n s p o r t a t i o n . o h i o . g o v 53

  54. BMP Calcs Spreadsheet w w w. t r a n s p o r t a t i o n . o h i o . g o v 54

  55. Sample Plan Note W106 w w w. t r a n s p o r t a t i o n . o h i o . g o v 55

  56. Questions ? Jon Prier, P.E. jonathan.prier@dot.ohio.gov 614-644-1876 w w w. t r a n s p o r t a t i o n . o h i o . g o v 56

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend