Extended Detention Practices Table 4a Justin Reinhart, PE Division - - PowerPoint PPT Presentation

extended detention practices
SMART_READER_LITE
LIVE PREVIEW

Extended Detention Practices Table 4a Justin Reinhart, PE Division - - PowerPoint PPT Presentation

Extended Detention Practices Table 4a Justin Reinhart, PE Division of Surface Water Northeast Ohio Stormwater Training Council Cleveland, Ohio Richfield, Ohio July 12, 2018 July 25, 2018 Table 4a Extended Detention Post-Construction


slide-1
SLIDE 1

Extended Detention Practices Table 4a

Justin Reinhart, PE Division of Surface Water

Northeast Ohio Stormwater Training Council Cleveland, Ohio Richfield, Ohio July 12, 2018 July 25, 2018

slide-2
SLIDE 2
  • What did the Construction General Permit change ?
  • What may change in the RWLD manual ?
  • Common issues / challenges

Table 4a Extended Detention Post-Construction Practices with Minimum Drain Times Extended Detention Practices Minimum Drain Time of WQv Wet Extended Detention Basin1,2 24 hours Constructed Extended Detention Wetland1,2 24 hours Dry Extended Detention Basin1,3 48 hours Permeable Pavement – Extended Detention1 24 hours Underground Storage – Extended Detention1,4 24 hours Sand & Other Media Filtration – Extended Detention1,5 24 hours

slide-3
SLIDE 3

Dry Extended Detention Basin

What did the permit change ?

– Allows for acceptable pretreatment in place of a forebay and micropool. – Must include a protected outlet.

What will be changing in the RWLD Manual ?

– Standards for acceptable pretreatment practices and protected

  • utlet. (Appendix 10)
slide-4
SLIDE 4

Dry Extended Detention Basin

Acceptable alternatives must be equivalent to a forebay & micropool:

– Remove 50% of annual TSS load. – Require minimal maintenance and oversight for long-term functioning of the extended detention volume. – Prevent scour/erosion at pipe outfalls.

slide-5
SLIDE 5

Pretreatment Alternatives

Grass Swale

  • Vel. ≤1 ft/s @ d ≤ 4 in.

W = 4 ft. to 8 ft. L ≥ 50 ft. S ≤ 4% (< 1% may be an issue)

IMAGE SOURCE: VA DEQ Stormwater Design Specification No. 10

slide-6
SLIDE 6

Pretreatment Alternatives

slide-7
SLIDE 7

Pretreatment Alternatives

Grass Filter Strip Full width of pavement L ≥ 10 ft. Dense turf

slide-8
SLIDE 8

Pretreatment Alternatives

slide-9
SLIDE 9

Pretreatment Alternatives

Still need erosion/scour protection at basin inlet. Manufactured Treatment Device

slide-10
SLIDE 10

Pretreatment Alternatives

Deep Sump Trap or Catch Basin Possible for small drainage areas:

parking lot catch basin (6 ft dia.) 4 ft x 28.3 ft2 = 113 ft3 @ 10%, WQv = 1,132 ft3 ~ 1,600 ft2 max. impervious d.a.

IMAGE SOURCE: USEPA

slide-11
SLIDE 11

Dry Forebay… Possibly

  • Not much research
  • Need to develop standards
  • May need test sites
slide-12
SLIDE 12

Dry Forebay… Possibly

Permeable Dike 10% - 20% WQv

Concept based on: UDFCD, Urban Storm Drainage Criteria Manual Vol. 3 (2015)

72-hr Drawdown ?

slide-13
SLIDE 13

Dry Forebay… Possibly

IMAGE SOURCE: NJ Stormwater BMP Manual, Chapter 9.5 Infiltration Basins

slide-14
SLIDE 14

Dry Forebay… Possibly

Concrete Impermeable Dike Weep Hole / Pipe

Concept based on: New Jersey Stormwater Manual, Chapter 9.5

72-hr Drawdown ?

slide-15
SLIDE 15

Protected Outlet

slide-16
SLIDE 16

Protected Outlet

slide-17
SLIDE 17

Protected Outlet

slide-18
SLIDE 18

Protected Outlet

Micropool Micropool Micropool

slide-19
SLIDE 19

Protected Outlet

slide-20
SLIDE 20

Protected Outlet

slide-21
SLIDE 21

Protected Outlet

slide-22
SLIDE 22

Protected Outlet

IMAGE SOURCE: www.ads-pipe.com/products/pipes/advanedge-panel/advanedge-site-drain-pipe

slide-23
SLIDE 23

Protected Outlet

“The filter under drain system at Carver County dry detention pond exhibited poor hydraulic performance and failed to keep the pond dry between the storm events.” “Continual maintenance is required to maintain the filter system in an operational condition.”

  • Minnesota DOT. 2006. Water Quality Performance of Dry Detention

Ponds with Under-Drains. Mn/RC-2006-43.

slide-24
SLIDE 24

Protected Outlet

Agricultural “blind inlet” to field tile 24-hr drawdown

slide-25
SLIDE 25

Protected Outlet

“designed to catch sediment and therefore, eventually fail and require maintenance”

slide-26
SLIDE 26

Dry Extended Detention Basin

Pool Volume = WQv + 20% sediment Pool Volume = WQv + 10% forebay + 10% micropool

slide-27
SLIDE 27

Wet Extended Detention Basin

What did the permit change ?

– Permanent pool volume and extended detention volume are now both equal to the WQv (was ¾ WQv).

What will be changing in the RWLD Manual ?

– Not much.

slide-28
SLIDE 28

+20% Sediment Storage +20% Sediment Storage ≥ WQv ≥ WQv

slide-29
SLIDE 29

Extended Drawdown

  • Wet & underground: 24-hour minimum
  • Dry: 48-hour minimum
  • Shall not discharge more than the first half of the WQv

in less than one-third of the drain time.

slide-30
SLIDE 30

Extended Drawdown

slide-31
SLIDE 31

Extended Drawdown

slide-32
SLIDE 32

Extended Drawdown

slide-33
SLIDE 33

Extended Drawdown

slide-34
SLIDE 34

Extended Drawdown

slide-35
SLIDE 35

Extended Drawdown

slide-36
SLIDE 36

Extended Drawdown

slide-37
SLIDE 37

Extended Drawdown – 2” Min.

  • As designed, the acre basin with a 1⅝ in. diameter orifice.
  • What if the local authority has a minimum 2 in. orifice

diameter requirement ?

slide-38
SLIDE 38

Extended Drawdown – 2” min.

slide-39
SLIDE 39

Extended Drawdown – 2” min.

slide-40
SLIDE 40

Underground Stormwater Management Systems

slide-41
SLIDE 41

Underground Stormwater management Systems

What did the permit change ?

– Added infiltrating and extended detention USMS as standard practices pre-approved for general use. – Requires pretreatment at verified efficacy.

What will be changing in the RW&LD Manual ?

– Provisional standard has been posted. – Welcome input.

slide-42
SLIDE 42

USMS – Ext. Det. Pretreatment

  • Verified 50% TSS removal.
  • Can use NJDEP list.
  • Max treatment flow rate/hydraulic loading @ WQf.
  • Size according to each inlet.
  • Can be used in parallel, but does not increase TSS

removal.

slide-43
SLIDE 43

Infiltrating System

Pre-T 80% TSS @ WQF Verified

  • Infl. Rate

Flood Control Outlet

Open System

WQv @ d ≤ IWS No Sediment Storage Flood Control Volume

slide-44
SLIDE 44

Extended Detention System

Pre-T WQ, FC & Overflow Outlets

All Solid Wall

Wet Sump (20% Sediment) WQv Flood Control Volume 50% TSS @ WQF

slide-45
SLIDE 45

Extended Detention System

Pre-T Wet Sump (20% Sediment)

Lined

Contained WQv WQ Outlet Flood Control Volume . Flood Control & Overflow Outlets 50% TSS @ WQF

slide-46
SLIDE 46

Extended Detention System

Pre-T Infiltration

Partially Infiltrating

Flood Control Volume Wet Sump (20% Sediment) Outlets WQv above IWS 50% TSS @ WQF

slide-47
SLIDE 47

Multiple Entry Points

slide-48
SLIDE 48

Multiple Entry Points

slide-49
SLIDE 49

Multiple Entry Points

slide-50
SLIDE 50

WQ Outlet Configuration

slide-51
SLIDE 51

Maintenance Feasibility

  • Access manholes at inlet,
  • utlet and within storage as

necessary for cleaning.

  • Observation wells.
slide-52
SLIDE 52

Maintenance Feasibility

  • Costs ?
  • Depth ?
  • Surface Accessibility ?
  • How Often ?
  • How ?

SOURCE: “Maintaining Stormwater Systems”, Northern Virginia Regional Commission, 2007

slide-53
SLIDE 53

Post-Construction O & M Plan

site map w/ stormwater infrastructure

slide-54
SLIDE 54

Storm Water Technical Assistance justin.reinhart@epa.ohio.gov 614-705-1149