Energy Networks Association Open Networks Project Advisory Group
5th September 2019
Energy Networks Association Open Networks Project Advisory Group - - PowerPoint PPT Presentation
Energy Networks Association Open Networks Project Advisory Group 5 th September 2019 General Housekeeping Amenities Both male and female toilets can be found in the corridor. Emergency Exit Fire escape door is located in the
5th September 2019
Amenities
Emergency Exit
Wifi
Tea & Coffee
Attendance
Feedback
Correspondence
2
The Advisory Group is essential to our project to:
resolve where appropriate. We will provide input to:
We will seek to send information in advance of meetings to ensure that views can be sought by trade associations in advance. Our objective is to encourage open feedback from you all across all of our work. Thank you for the continued input.
3
4
Item Leader Welcome & Introduction NT General Project Updates JB Workstream 2 Product 1: System Wide Resource Register JW Workstream 3 Product 7: Conflicts of Interest and Unintended Consequences RB Breakout session: Workstream 1A Product 6, Facilitation of new markets Workstream Representatives Breakout session: Workstream 4 Product 2, Day ahead real time operations Workstream Representatives Breakout session: Workstream 4 Product 4, Investment planning Workstream Representatives Wrap-up NT
5
Work has now commenced on all Workstream products outlined in our 2019 plan. We have taken your feedback to help us identify priorities and shape the scope and direction of travel for this year.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Overall Project Future Workplan & Prioritisation Workstream 3 Product 1 Impact Assessment Workstream 1A Various products Workstream 2 Queue Management; Interactivity Workstream 4 Dependent on scoping work
6
Consultants, 5 Consumer Protection Party, 3 Cross Industry Representative, 3 Distributed Energy Resource, 2 DNO/DSO, 1 Electricity TO, 1 Generator/DER, 4 iDN O, 1 Large Energy Company, 6 Local Energy System, 5 Settlement Agent, 1 Supply Chain, 3
7
8
The development work of Workstream 1a: Flexibility Services has been opened up to wider stakeholder participation, to help develop products beyond the existing Advisory Group input. Workstream 1a is currently developing the following products, and the project team would encourage further stakeholder participation in its development work:
The Open Networks Workstream Working Groups have responsibility for the definition, review and approval (or recommendation of submission to the Steering Group for approval) of all Workstream outputs. Reporting to the Workstream Working Group, we have convened a number of Subject Matter Experts (SMEs) into product development teams to develop products and submit content for review and guidance from the Working Group. This enables us to develop content in between the Working Group meetings (typically every 3 weeks) and to maintain pace in delivery in the project. Typically, this will require between half and one day’s work a week to provide the necessary input into product development. The Terms of Reference for participating in Workstream 1A development work can be found here. To find out more about participating in Workstream 1a, please email us at opennetworks@energynetworks.org.
9
We intend to ask stakeholders for their views on our open letter response: Whilst we are not formally consulting on this letter response, we would welcome any input from stakeholders
will set as our priorities and development work for 2020 and beyond. We are beginning to plan our work for 2020 and draft our annual Project Initiation Document, therefore there is an opportunity to provide stakeholder input to our panning in whilst it is still in development. We would encourage any stakeholders to provide feedback to us at the following email address: opennetworks@energynetworks.org We plan to give 4 weeks to respond (any longer and we won’t be able to take feedback into account) This gives stakeholders the opportunity to shape our priorities up-front. We have also planned to consult on our full Workplan and PID in Q1 2020, but we are conscious of the draw on industry resources and the need to for us to focus our consultations on key areas. Questions for you today: Would you welcome the opportunity to provide feedback on our Open Letter response? Would you still like to be given the opportunity to provide feedback on our PID in Q1 by formal consultation?
John West (ENA)
11
12
(Options include central database, portal and
ENWL NPg SPEN SSEN UKPN WPD LTDS Heat Maps Contract Registers New Information DNO’s update registers on a regular basis Project Developers Network Companies Govt & Agencies Service Providers Other Parties
Ofgem work to update form of LTDS’s may revise data EDTF work provides additional context for SWRR
RecorDER project may provide future implementation
With flexibility service platforms (e.g. Piclo) there may be value in a register
capability, pre-qualification etc.
Users access registers for complete, accurate info which is consistent across DNOs
DCUSA proposal DCP350 to establish DER registers was reviewed at the 17th July DCUSA panel
and seek further advice on confidentiality aspects.
TEC Registers etc TOs, ESO
13
Connection
Opportunities to trade rights? Better forecasts
requirements Where is it best to site local infrastructure? Opportunities to provide flexibility Policy review &
Savings through flexibility services?
14
Implementation Steps
Aug 19 Sep 19 Oct 19 Nov 19 Jan 20 Dec 19 Feb 20 Mar 20 Apr 20 May 20 Jun 20 Jul 20
Publish Initial Registers Refine Registers Legal Advice on Confidentiality Aspects Support DCUSA Modification DCP 350 Establish Internal Processes to Deliver Network Reinforcement Information Update & Maintain Registers Include Network Reinforcements
Further work will be undertaken including:
Further work could also include:
General Data
connection point, plant type etc
Already Connected
Commercial Services
duration
Accepted to Connect
Network Reinforcement
completion date
Data Structure
15
The SWRR aligns with the EDTF recommendations and the direction of travel on data access. For example, the SWRR could be one of the Energy System datasets that is accessed via the EDTF’s proposed Data Catalogue (Recommendation 3).
Data Catalogue
Network Codes Settlement Data Energy System Database Energy System Database SWRR
SWRR data has been triaged against EDTF data types (Open, Public, Shared & Closed). Customer names, sites and locational data that might allow specific customers to be identified are likely to be “Closed” data unless licence or code changes are made. Data on commercial services provided by customers is likely to be “Shared” data
General Data
Field Tag Data Category Mitigation
Customer Name Closed Anonymise Customer Site Closed Anonymise Grid Supply Point (GSP) Might be Closed or Open Aggregate Bulk Supply Point Might be Closed or Open Aggregate Primary Might be Closed or Open Aggregate Licence Area Open Plant Type Open Type of Connection Open Connection Status Open
Randolph Brazier (ENA)
17
18
19
Version shared today Future version (september)
20
Steve Atkins - SSEN
Facilitation of New Markets 22
Facilitation of new markets In addition to directly procured DSO services, we need to consider how we can facilitate
peer trading platforms, capacity management, trading flexibility to take on or avoid constraints). Development work should include considering:
actions to facilitate these
Facilitation of New Markets 23
Facilitation of New Markets 24
Facilitation of New Markets 25
1. What don’t we know about? i. Review of recent consultations – Future Worlds, Impact Analysis, Flexibility Market ii. Review of BEIS Flex/Innovate UK applications 2. What’s covered? i. Review of ON Products ii. WS3 Product 5 Outputs iii. Review of TEF Projects/DNO Trials 3. Data Requirements i. pre-trade - for facilitation ii. post-trade - for resilience 4. Trial scenarios
Facilitation of New Markets 26
Telephone Interviews – 13/8/19 to 30/9/19
Desktop Survey – 13/8/19 to 30/9/19
Cross-check against our categories of new markets – September 2019 New stakeholders - 13/8/19 to 30/10/19
Stakeholder event – October 2019
Utilise Flexibility in GB webpage – 1/10/19 to 30/11/19 Produce Report – December 2019
Facilitation of New Markets 27
Project Name What they applied for Scale Funded/Unfunded Is it new? What service are they trying to develop? Is it a refinement of an existing market? What essential data do you require for the market to function? What data would be good to have in addition? What are the regulatory barriers?
Facilitation of New Markets 28
services for system operators – define peer to peer
add value for stakeholders pre-trade to facilitate the range of activities
requirements for market participants
Facilitation of New Markets 29
Engage with:
Facilitation of New Markets 30
Facilitation of New Markets 31
Mark Herring – National Grid
33
WS4 Overview
Data Processes & Principles Customer Segmentation Early Development Further Process Development Finalise & Approve Outcomes
34
WS4 Timeline
35
WS4 Product 2 – Real time / day ahead
Problem statement(s) / hypotheses
Activity Sub-deliverable A: Identify activities that impact / support cross-vector operation and
Site nominations (sites inform control centres as to planned hours of operation) Major outages (look at circumstances where we should share information) System Operation forecasts (data transactions) Test value i.e. potential benefits vs additional workload Review existing terminology and aim to create common dictionary to terms of agree common language Sub-deliverable B: Target processes for implementation across network operator, which are likely to result in consequential business change (this is likely to be different across different network operators depending on what processes they have in place now) Suggested / identified Code Changes, System Changes, Process Changes Recommendations for further work Identification of barriers [regulatory etc.] Output Sub-deliverable A: Report findings and options/ recommendations for improvement Case study for appropriate customer type(s) (Date: September 2019) Sub-deliverable B: Implementation plan (Date: November 2019) Interactions Close linkages with other products in workstream 4 Link to the Energy Data Taskforce group Legal restrictions around data sharing and transparency WS1b – real time data exchange
36
Product 2 – Examples of case studies
electricity networks:
generation
most immediate issue with most to gain in the short term
inform the approach for CHP and H2 injection at a later date following similar principles
37
Product 2 – Opportunities
Gas Network Electricity Network
Short term opportunities focus on Flexible Generation:
Longer term opportunities (outside current scope):
How can real-time / day ahead coordination of data & operations:
local production )
improved efficiency, lower costs, less CO2 from compressors
38
Product 2 – Proposal for discussion
Capacities connected Markets signed up to Capacity agreements / svcs (gas) Capacity agreements / svcs (elec) Real time network constraints Electricity demands (local and national) Real time generation services required Weather patterns Availability of renewable / intermittent Requirement for flexible generation Electricity supply prices ESO dispatch instruction
39
Product 2 – Proposal for discussion
Capacities connected Markets signed up to Capacity agreements / svcs (gas) Capacity agreements / svcs (elec) Real time network constraints Electricity demands (local and national) Real time generation services required Weather patterns Availability of renewable / intermittent Requirement for flexible generation Electricity supply prices ESO dispatch instruction
For this discussion:
data eg. shared procurement of 3rd party forecasts vs a single network forecast vs shared forecasts between networks vs shared inputs to forecast models?
value / risk comparisons?
be useful, and for what purpose?
within our 5 year horizon?
Stuart Easterbrook - Cadent
41
WS4 Overview
Data Processes & Principles Customer Segmentation Early Development Further Process Development Finalise & Approve Outcomes
42
WS4 Timeline
43
Product Team Approach
The aim of the product is to identify and realise benefits to customers and stakeholders by applying a whole system approach within the investment planning processes.
Identify
Prioritise based on hypotheses Test Hypotheses Confirm deliverables Confirm delivery plan
Opportunity Area Hypotheses
Information Flow A single entity undertaking the information gathering activity from local bodies will reduce costs for all parties, remove the potential for inconsistencies, create a consistent trusted data set, and provide a basis for networks to feedback related issues on their networks. There is data that a network could provide that would help customers and stakeholders from another network e.g. gas network capacity info for gas power generation. Delivering Solutions Applying a whole energy system approach can generate a better and more valuable range of
WS4 Product 4 – Investment planning
Do you agree with the hypotheses?
44
WS4 Product 4 – Investment planning
Information In and Out Delivering Solutions (3 years +) Deliverable:
A single entity will procure, update, and share the requirements for medium and long term incremental network capacity from regional bodies.
Deliverable:
Accessed from a central hub, the networks produce “heat maps” showing their networks and areas of spare/scarce entry and exit capacity
Deliverable:
A whole system optioneering service, providing Local Authorities with options to meet their future requirements, to enable the establishment of regional energy infrastructure
application from the Local Authority/Regional body. Anticipated outcomes:
Product Deliverables
Do you think these deliverables can add significant value to customers and stakeholders? What are the risks that might need to be mitigated? Potential approaches to delivery of these proposals, and the value / risks of each?
Nigel Turvey (WPD, Open Networks Project Chair)
46
There are some challenges ahead if we want to meet our carbon targets while providing a safe and secure energy grid at an affordable price. However, by enabling flexible networks we can address these; open up new markets for customers for low carbon and innovative technologies; and deliver efficient network costs for consumers. We are working together and dedicated to making this work with input from stakeholders in an open and transparent way. Please remember to complete the feedback poll on your desks. We welcome feedback from all our stakeholders. If you have any comments that you would like to share, please feel free to submit them to opennetworks@energynetworks.org.