Derwent Hydroelectric Plant: A Decentralised Energy Case Study Helen Carter Senior Climate Change Projects Officer Agenda Introduction Key drivers The hydro project Key lessons learnt Utilising the asset Questions


slide-1
SLIDE 1

Derwent Hydroelectric Plant: A Decentralised Energy Case Study

Helen Carter Senior Climate Change Projects Officer

slide-2
SLIDE 2

Agenda

  • Introduction
  • Key drivers
  • The hydro project
  • Key lessons learnt
  • Utilising the asset
  • Questions
slide-3
SLIDE 3

Introduction

  • Derby City Council
  • Climate Change Team
  • The Project
slide-4
SLIDE 4
  • 1. History
  • 2. Council House Redevelopment
  • 3. Derby’s Climate Change Strategy

Key Drivers

slide-5
SLIDE 5

Hydroelectric power on the river Derwent – a brief history

History

  • The Silk Mill
  • Derwent Valley Mills

– Belper, Darley Abbey, Masson Mills Recent history

  • 1960: 20 turbines operating at 8 sites
  • 2007: 7 turbines operating at 4 sites

(Borrowash, Milford, Belper and Masson Mills)

  • Belper hydro generator produces

350kw of power

Back

slide-6
SLIDE 6

Council House Redevelopment

  • Ambitious project to completely refurbish and

redesign the Council House.

  • Building has been designed to secure an 'excellent'

rating under BREEAM and an 'A' rated Energy Performance Certificate.

  • Initiatives include solar panels, adiabatic cooling,

rainwater harvesting & hydroelectric power.

Back

slide-7
SLIDE 7

Derby’s Climate Change Strategy

  • 6 key themes covering;

– An active community – Being prepared for a changing environment – A secure local renewable energy supply – Thriving sustainable economy – Smarter travel options – Energy efficient homes

slide-8
SLIDE 8

Longbridge Weir – hydroelectric project

slide-9
SLIDE 9

Project timeline

Initial proposal 2007/08 Planning permission

  • btained

2011 Construction start August 2011 Construction end December 2012 Final testing & completion 2013

slide-10
SLIDE 10

Construction

slide-11
SLIDE 11

Design features

  • A siphon chamber
  • Single turbine construction which can be removed
  • Trap and raking system to remove debris
  • Tail race to direct water back to the river
  • Fish pass
  • Intake channel, screen cleaner, fish by-wash weir,

flood overspill weir

slide-12
SLIDE 12

Vertical shaft Kaplan propeller

  • Turbine: vertical- shaft Kaplan-

propeller (2m in diameter)

  • Output power:230kW
  • Peak turbine flow: 13 m3/s
  • Minimum turbine flow: 2 m3/s
  • Potential to generate 1.3 million

kWh/year

slide-13
SLIDE 13

Finance

  • Approximately £1.7 million capital programme with a

25 year expected pay back time.

  • Funded by the Council through a Prudential loan.
  • Income generation of approx. £138,000 per year

through FITS with an additional £60,000 per year from sale of electricity to grid.

slide-14
SLIDE 14

Environmental considerations

  • Ecological surveys
  • Tree surveys
  • Fish pass
  • CO2 reduction

Next

slide-15
SLIDE 15

CO2 emission reduction

Pay back cost of project is 25 years which equates to;

  • 125 tonnes of CO2 generated.
  • A CO2 saving of 28375 tonnes (compared to the

equivalent energy supplied by coal power).

  • 32,500,000 kWh generated.

Back

slide-16
SLIDE 16

4.8 563 1140 200 400 600 800 1000 1200 total tonnes of CO2 produced by Derwent hydro per year total tonnes of CO2 produced from equivalent gas fired power per year total tonnes of CO2 produced from equivalent coal fired power per year

slide-17
SLIDE 17

Reducing and Managing Risk

  • Public and political support
  • Finance
  • Planning
  • Construction
  • Maintenance
  • Environment
slide-18
SLIDE 18

Flood defence

  • Built on a worse case scenario of flood level 2.5m

above weir crest.

  • Over 800m3 of material from the floodplain upstream
  • f the weir was removed.
  • The scheme will provide a 10m length of new flood

spillway, set 0.3m above weir crest level.

slide-19
SLIDE 19

Key lessons learnt

  • Recognise and factor in potential delays in

construction; – for poor or extreme weather – Complications with external parties and partners

  • Avoid high cost of creating a river diversion where

possible

  • Environmental/ecological complications
slide-20
SLIDE 20

Utilising the asset

  • Educational tool
  • Case studies
  • Interpretation boards & real

time monitors

  • Visits – President of RTPI

(Royal Town and Planning Institute), other LA’s

slide-21
SLIDE 21

Questions?

slide-22
SLIDE 22

Useful contacts

Helen Carter Senior Climate Change Projects Officer Derby City Council Helen.carter@derby.gov.uk or 01332 680810 Gethyn Davies Project Manager Derby City Council Gethyn.davies@derby.gov.uk or 01332 643345