El Limon-Guajes Mine Photographic Report First Ounces December 2015 - - PowerPoint PPT Presentation
El Limon-Guajes Mine Photographic Report First Ounces December 2015 - - PowerPoint PPT Presentation
TSX: TXG January 14, 2016 El Limon-Guajes Mine Photographic Report First Ounces December 2015 2 First Shipment January 2016 3 View of Guajes Pit And RopeCon 4 Crushing And Ore Stockpiles RopeCon, coming down from the El Limon crusher
First Ounces December 2015
2
First Shipment January 2016
3
View of Guajes Pit And RopeCon
4
Crushing And Ore Stockpiles
5
1 of 9 coarse
- re stockpiles
Guajes Crusher RopeCon, coming down from the El Limon crusher Stacker conveyor from the Guajes crusher Discharge point for the RopeCon, onto the same fine ore stockpile as the Guajes Stacker conveyor Fine ore stockpile (SAG Mill feed) Reclaim tunnel that pulls fine
- re from the
stockpile and puts it onto the SAG Mill feed conveyor
Guajes Crusher And Stacker Conveyor
6
Reclaim Tunnel – Fine Ore Stockpile Is Above The Tunnel, Ore Comes Down Through Feeders To The SAG Mill Feed Conveyor
7
SAG Mill Feed Conveyor From The Reclaim Tunnel
8
SAG Mill And Screens To Remove ‘Pebbles’
9
After The Screens, Material Is Pumped To The Cyclones At the Top Right, Cyclone Oversize To The Ball Mill
10
Cyclone Undersize Is Pumped To The Pre-Leach Thickener
11
From The Pre-Leach Thickener To The Leach Tanks And Then To CIP Process In The Back
12
What The Inside Of A Leach Tank Looked Like
13
From CIP, Pregnant Solution Goes To Carbon Handling
14
Trying to get new picture
From Carbon Handling To The Refinery For Dore’
15
From CIP, Tailings Go To Cyanide Destruction
16
From Cyanide Destruction Over To The Filter Building
17
Inside the Filter Plant
18
Filtered Tailings Are Conveyed To The Disposal Area
19
Tailings Disposal Area (TDS) – The End Of The Process
20
Secondary Processes: Reagent Distribution
21
Process Water Control Structures Needed To Be Built And Sealed
22
Mobile Equipment Maintenance Facilities Needed To Be Built And Equipped (Not Critical Path)
23
Staff Housing, An Administration Building, An Access Road, And A New Village Have Been Constructed And Are Now In Use
24
View From El Limon – Rope-Con In Front, Stockpile In The Middle And Filter Plant On The Far Right
25
Advancing On ‘Full Production’ Construction. This Is the El Limon Crusher Building
26
Mining And Road Construction Have Started For The El Limon Pit
27
For further information: Gabriela Sanchez, VP Investor Relations email: gabriela.sanchez@torexgold.com Mobile: (416) 357-6673 www.torexgold.com