TSX: TXG January 14, 2016 El Limon-Guajes Mine Photographic Report First Ounces December 2015 2 First Shipment January 2016 3 View of Guajes Pit And RopeCon 4 Crushing And Ore Stockpiles RopeCon, coming down from the El Limon crusher


slide-1
SLIDE 1

TSX: TXG

El Limon-Guajes Mine Photographic Report

January 14, 2016

slide-2
SLIDE 2

First Ounces December 2015

2

slide-3
SLIDE 3

First Shipment January 2016

3

slide-4
SLIDE 4

View of Guajes Pit And RopeCon

4

slide-5
SLIDE 5

Crushing And Ore Stockpiles

5

1 of 9 coarse

  • re stockpiles

Guajes Crusher RopeCon, coming down from the El Limon crusher Stacker conveyor from the Guajes crusher Discharge point for the RopeCon, onto the same fine ore stockpile as the Guajes Stacker conveyor Fine ore stockpile (SAG Mill feed) Reclaim tunnel that pulls fine

  • re from the

stockpile and puts it onto the SAG Mill feed conveyor

slide-6
SLIDE 6

Guajes Crusher And Stacker Conveyor

6

slide-7
SLIDE 7

Reclaim Tunnel – Fine Ore Stockpile Is Above The Tunnel, Ore Comes Down Through Feeders To The SAG Mill Feed Conveyor

7

slide-8
SLIDE 8

SAG Mill Feed Conveyor From The Reclaim Tunnel

8

slide-9
SLIDE 9

SAG Mill And Screens To Remove ‘Pebbles’

9

slide-10
SLIDE 10

After The Screens, Material Is Pumped To The Cyclones At the Top Right, Cyclone Oversize To The Ball Mill

10

slide-11
SLIDE 11

Cyclone Undersize Is Pumped To The Pre-Leach Thickener

11

slide-12
SLIDE 12

From The Pre-Leach Thickener To The Leach Tanks And Then To CIP Process In The Back

12

slide-13
SLIDE 13

What The Inside Of A Leach Tank Looked Like

13

slide-14
SLIDE 14

From CIP, Pregnant Solution Goes To Carbon Handling

14

Trying to get new picture

slide-15
SLIDE 15

From Carbon Handling To The Refinery For Dore’

15

slide-16
SLIDE 16

From CIP, Tailings Go To Cyanide Destruction

16

slide-17
SLIDE 17

From Cyanide Destruction Over To The Filter Building

17

slide-18
SLIDE 18

Inside the Filter Plant

18

slide-19
SLIDE 19

Filtered Tailings Are Conveyed To The Disposal Area

19

slide-20
SLIDE 20

Tailings Disposal Area (TDS) – The End Of The Process

20

slide-21
SLIDE 21

Secondary Processes: Reagent Distribution

21

slide-22
SLIDE 22

Process Water Control Structures Needed To Be Built And Sealed

22

slide-23
SLIDE 23

Mobile Equipment Maintenance Facilities Needed To Be Built And Equipped (Not Critical Path)

23

slide-24
SLIDE 24

Staff Housing, An Administration Building, An Access Road, And A New Village Have Been Constructed And Are Now In Use

24

slide-25
SLIDE 25

View From El Limon – Rope-Con In Front, Stockpile In The Middle And Filter Plant On The Far Right

25

slide-26
SLIDE 26

Advancing On ‘Full Production’ Construction. This Is the El Limon Crusher Building

26

slide-27
SLIDE 27

Mining And Road Construction Have Started For The El Limon Pit