Leteng Mine Life of Mine 2015 Update Presentation 22 May 2015 - - PowerPoint PPT Presentation

let eng mine life of mine 2015
SMART_READER_LITE
LIVE PREVIEW

Leteng Mine Life of Mine 2015 Update Presentation 22 May 2015 - - PowerPoint PPT Presentation

Leteng Mine Life of Mine 2015 Update Presentation 22 May 2015 Summary 2 The most recent update of the Leteng Life of Mine plan (published 17 March 2015) has resulted in: A significantly improved NPV over the life of the mine A


slide-1
SLIDE 1

Letšeng Mine – Life of Mine 2015

Update Presentation 22 May 2015

slide-2
SLIDE 2

Summary

2

The most recent update of the Letšeng Life of Mine plan (published 17 March 2015) has resulted in:

A significantly improved NPV over the life of the mine

A 15% increase in higher value satellite ore being treated annually from 2015 to 2019

A 39% increase in higher value satellite ore being treated from 2020 onwards

The life of the open pits being extended until 2038

A smoother waste mining profile with a reduced peak of 36mtpa

An overall reduction in stripping ratios

These results have been achieved following the operational improvements introduced through:

improved blasting practice

geotechnical controls

mining efficiencies.

slide-3
SLIDE 3

Background

Long term mine plans for Letšeng are updated annually on most current market and operational information

The 2015 update is of greater significance as it incorporates a significant steepening of the pit slopes made possible by improved blasting practices and pit-wall protection

The increase in treatment rate resulting from the No 2 Plant Phase 1 Upgrade project is incorporated

The main objectives of the mine plan revision are as follows:

To enhance value

To optimise / defer waste stripping

To optimise/maximise the percentage of the higher grade, higher value satellite ore treated

3

slide-4
SLIDE 4

Pit Wall Protection

The following initiatives have contributed to pit wall protection resulting in the steepening of the pit walls:

Employment of a Blasting Engineer

Engagement of Blasting Consultant

Establishment of a Geotechnical Department

Improved wall and floor control – better pre-splits

Electronic blasting

Real time slope monitoring

Commissioning of a Scaler

4

slide-5
SLIDE 5

Objectives

To enhance value

Optimise/defer waste

Optimise/maximise Satellite contribution

Incorporate steeper slopes in pit design (70º v 65º)

Basis

2014 Reserve grades and prices

6mtpa of ore treated through Plants 1 & 2

Contractor operation (AV) to continue - end of 2016

Incorporates additional 0.25mtpa ore treated from 2016 from Plant 2 Upgrade Project

Does not currently include further expansion opportunities

Operating Costs*

Direct cash cost per tonne treated (exc waste) M150.00

Waste cost per waste tonne mined M29.00

5

Planning Parameters/Results

Output Maximising value

Satellite Ore tonnage ramp up

2015 to 2019 increased from 1.44 to 1.65 mtpa

2020 to end increased from 1.44 to 2.00 mtpa

Significantly increased NPV

*Costs are as per 2015 guidance and in 2015 terms

Stripping ratios (LoM): Main Pit

  • > 1.6

Satellite

  • > 6.7

Combined

  • > 2.9

Smoother profile of waste

Peak waste of 36 mtpa

slide-6
SLIDE 6

Waste Mining Profile

6

5 10 15 20 25 30 35 40 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037

Waste Tonnes Mined - million tonnes

Updated LoM Plan Waste Mining Tonnage Profile

Main Pit Waste Satellite Pit Waste

slide-7
SLIDE 7

Tonnes Treated / Carats Recovered Profile

7

1 2 3 4 5 6 7 8 20 40 60 80 100 120 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037

Ore Tonnes Treated - million tonnes Carats Recovered - thousand carats

Updated LoM Plan Treated Tonnes and Carats Recovered Profile

Main Pipe Tonnes Treated Satellite Pipe Tonnes Treated Carats Recovered

slide-8
SLIDE 8

Letšeng reserves and resources

8

As at 1 January 2014 Carats (millions) Grade (cpht) US$/ct In-situ value (US$ billions) Letšeng Indicated Resource 3.23 1.73 2 086 6.7 Letšeng Reserve 2.26 1.71 2 045 4.6

2014 Extension of Indicated depth at Letšeng to 350m below mining face

Letšeng Life of Mine open pit is wholly contained within the Reserve category

The reserve, based on the 2015 pit design, will be updated by mid 2015.