SCHOOL BOARD INFORMATION ITEM 03/12/2020
EDUCATION CENTER REUSE
Final Design and Construction Contract Award
SCHOOL BOARD INFORMATION ITEM MARCH 12, 2020
EDUCATION CENTER REUSE Final Design and Construction Contract Award - - PowerPoint PPT Presentation
EDUCATION CENTER REUSE Final Design and Construction Contract Award SCHOOL BOARD INFORMATION ITEM MARCH 12, 2020 SCHOOL BOARD INFORMATION ITEM 03/12/2020 Project Parameters Project included in the FY2019-28 Capital Improvement Plan (CIP)
SCHOOL BOARD INFORMATION ITEM 03/12/2020
SCHOOL BOARD INFORMATION ITEM MARCH 12, 2020
Liberty initially, and later to adapt to possible future instructional and grade level changes
Supported Students
APS project website: https://www.apsva.us/education-center-reuse/
SCHOOL BOARD INFORMATION ITEM 03/12/2020 2
UPDATES SCHOOL BOARD INFORMATION ITEM 03/12/2020 3
SCHOOL BOARD INFORMATION ITEM 03/12/2020 4
Engineering Plan, Landscape Plan, and Fire Alarm
Sprinkler
Pre-Construction meeting
WASHINGTON-LIBERTY HIGH SCHOOL
SCHOOL BOARD INFORMATION ITEM 03/12/2020 5
WASHINGTON BLVD. 13TH ST. 14TH ST.
EXISTING TIME-RESTRICTED PARKING NEW BICYCLE PARKING, 30 BIKE CAPACITY ED CENTER LOT: 88 SPACES NEW BICYCLE PARKING IN GARAGE, 30 BIKE CAPACITY NEW RECTANGULAR RAPID FLASHING BEACONS (RRFB) AT 14TH EXISTING STAFFORD ST PICKUP/DROPOFF NEW DISPERSED PICKUP/DROPOFF @ 15TH ST NEW DISPERSED PICKUP/DROPOFF @ WASHINGTON BLVD EXISTING METERED PARKING ON N. QUINCY EXISTING FRONT DOOR LOT: 14 SPACES EXISTING I-66 GARAGE: 376 SPACES EXISTING BICYCLE PARKING EXISTING BUS DROPOFF ON GENERALS’ WAY NEW BUS DROPOFF EXISTING VISITOR/ POOL PARKING SCHOOL BOARD INFORMATION ITEM 03/12/2020 6
88 PARKING SPACES (18 MORE THAN ORIGINALLY PLANNED, TO OFFSET THE SPACES RESTRICTED ON 15TH STREET N QUINCY ST NEW ED CENTER MAIN ENTRANCE
PLAZA IMPROVEMENTS NEW TERRACE IMPROVEMENTS NEW “DO NOT ENTER” SIGNS NEW GROUND CONNECTION RAMP(SLOPE 1:12) AND FLUSH PAVING AT GENERALS’ WAY. GRADE DROPS 6.5’ BETWEEN ROAD CROSSING AND MAIN ENTRANCE NEW BICYCLE PARKING, 30 BIKE CAPACITY NEW BICYCLE PARKING IN GARAGE, 30 BIKE CAPACITY NEW RECT. RAPID FLASHING BEACONS (RRFB) AT 14TH EXISTING GENERATOR, DUMPSTERS AND NEW COOLING TOWER 14TH ST NEW WASH.BLVD. PU/DO NEW 15TH ST. PU/DO DASHED LINE = FIRE TRUCK ACCESS
Exhibit A
SCHOOL BOARD INFORMATION ITEM 03/12/2020 7
SCHOOL BOARD INFORMATION ITEM 03/12/2020 8
SCHOOL BOARD INFORMATION ITEM 03/12/2020 9
Classrooms / Collaboration Commons / Support Instructional Support Administration Building Support
Exhibit B
SCHOOL BOARD INFORMATION ITEM 03/12/2020 10
Exhibit C
SCHOOL BOARD INFORMATION ITEM 03/12/2020 11
Specifications on January 10, 2019.
Specifications with one exception:
Instruction (SGI).
food service operation within W-L was more efficient/effective than a distributed one.
instructional needs.
planned building capacity remains unchanged.
increase the serving capacity of the W-L kitchen.
At Final Design At Ed Specs Approval
FIRST FLOOR – VIEW INTO LOBBY SCHOOL BOARD INFORMATION ITEM 03/12/2020 12
COMMUNITY MEETING DRAFT 2/25/2020 13 FIRST FLOOR – VIEW OF DIGITAL LIBRARY TOWARDS COMMONS SCHOOL BOARD INFORMATION ITEM 03/12/2020 13 FIRST FLOOR – VIEW OF COMMONS TOWARDS PLANETARIUM SECOND FLOOR – VIEW OF COLLABORATION SPACE SECOND FLOOR – VIEW OF CLASSROOM
preliminary review of existing conditions and conceptual design study.
project including:
correct paving and drainage issues, and install right-of-way pedestrian improvements;
reconstructing one stairway;
Planetarium; and
and materials escalating at rates that exceed previous forecasts.
SCHOOL BOARD INFORMATION ITEM 03/12/2020 14
costs between multiple design options and evaluate possible scope reductions.
increase to the base cost.
related to:
safety issues
alternates related to:
(windows will be replaced within the existing
SCHOOL BOARD INFORMATION ITEM 03/12/2020 15
Project Funding (Millions) FY 2019-28 CIP1 Schematic Design2 Proposed Funding Major Construction Bonds $36.25 $36.05 $36.25 Other (Operating)3 $ 0.75 $ 0.75 $ 0.75 Other (MCMM)4 $ 0.20 $ 0.20 Capital Reserve $ 1.30 Total $37.0 $37.0 $38.5
Notes:
Construction / Major Maintenance.
Proposed Project Budget Construction Costs1 $29,194,176 Owner (Soft) Costs and Contingency2 $ 9,305,824 Total $38,500,000
Notes:
at-Risk (CMR). Includes the Early Work Contract value for interior demolition approved by the School Board on March 14, 2019.
services fees, utility/permitting fees, furniture, equipment, and project contingencies.
Exhibit D
SCHOOL BOARD INFORMATION ITEM 03/12/2020 16
September 2021
Education Center will be inaccessible throughout the construction period
updates posted to the project website: https://www.apsva.us/education- center-reuse/
SCHOOL BOARD INFORMATION ITEM 03/12/2020 17
Approve Exhibits A through D, including the following aspects of the project:
completed in time for start of school September 2021;
authorizes the Chair to sign related legal instruments, such as easements, vacations, and dedications, as may be required to comply with conditions of the Use Permit, provided such instruments were first reviewed and approved as to form by APS legal counsel;
existing purchase order to include the added contract value; and
SCHOOL BOARD INFORMATION ITEM 03/12/2020 18