Edsall Road and South Pickett Street: Pedestrian I mprovements Public Information Meeting March 15th, 2016, 7: 30 p.m. Note: The following information was presented to the public on March 15th, 2016 at the Tucker Elementary library. Please


slide-1
SLIDE 1

Edsall Road and South Pickett Street: Pedestrian I mprovements

Public Information Meeting

March 15th, 2016, 7: 30 p.m.

Note: The following information was presented to the public on March 15th, 2016 at the Tucker Elementary library. Please note that the maintenance of traffic layouts presented are preliminary and are subject to change. In particular the barrels, barriers, and mid-block crossings may be adjusted as the City coordinates with the Contractor. Citizens are encouraged to follow all pedestrian signage to allow safe passage around the active construction site. Contact information for the project has been provided on PDF page 15 of 16. Please contact Brian Meli (Brian.Meli@alexandriava.gov; 703-746-4110) with any questions.

slide-2
SLIDE 2

Agenda

2

Edsall Rd

  • S. Reynolds St
  • 1. Project Location
  • 2. Project Purpose
  • 3. Existing Condition
  • 4. Proposed Condition
  • 5. What To Expect During

Construction

  • 6. Project Contacts
slide-3
SLIDE 3
  • 1. Project Location

Intersection of Edsall Road & South Picket Street

3

Edsall Rd

  • S. Reynolds St
slide-4
SLIDE 4
  • 2. Project Purpose

4

Edsall Rd

  • S. Reynolds St

Improve pedestrian access and safety through the Edsall/ Pickett intersection.

slide-5
SLIDE 5
  • 3. Existing Condition

5

Edsall Rd

  • S. Reynolds St
  • No pedestrian signals
  • Inadequate ramps and pavement marking
slide-6
SLIDE 6
  • 3. Existing Condition

6

Edsall Rd

  • S. Reynolds St
  • Poor sight distance
slide-7
SLIDE 7
  • 4. Proposed Condition

7

Edsall Rd

  • S. Reynolds St
slide-8
SLIDE 8
  • 4. Proposed Condition

8

Edsall Rd

  • S. Reynolds St

IMG_0319.MOV

slide-9
SLIDE 9
  • 4. Proposed Condition

9

Edsall Rd

  • S. Reynolds St
slide-10
SLIDE 10
  • 5. What to Expect During

Construction

  • Regular Work Hours

7: 00 AM to 6: 00 PM (Mon-Fri)

  • Estimated Construction Schedule:

Start March 2016; Finish by Fall 2016

  • Some noise & disturbance

10

slide-11
SLIDE 11
  • 5. What to Expect During

Construction

11

  • Vehicular traffic control

Merge down to 1 lane each way (min.)

Note: Please note that the maintenance of traffic layouts presented are preliminary and are subject to change. In particular the barrels, barriers, and mid-block crossings may be adjusted as the City coordinates with the Contractor. Citizens are encouraged to follow all pedestrian signage to allow safe passage around the active construction site.

slide-12
SLIDE 12
  • 5. What to Expect During

Construction

12

  • Pedestrian Detour

At first, shift pedestrians away from

northeast corner.

Note: Please note that the maintenance of traffic layouts presented are preliminary and are subject to change. In particular the barrels, barriers, and mid-block crossings may be adjusted as the City coordinates with the Contractor. Citizens are encouraged to follow all pedestrian signage to allow safe passage around the active construction site.

slide-13
SLIDE 13
  • 5. What to Expect During

Construction

13

  • Pedestrian Detour

Then, shift pedestrians away from southwest

corner.

Note: Please note that the maintenance of traffic layouts presented are preliminary and are subject to change. In particular the barrels, barriers, and mid-block crossings may be adjusted as the City coordinates with the Contractor. Citizens are encouraged to follow all pedestrian signage to allow safe passage around the active construction site.

slide-14
SLIDE 14
  • 5. What to Expect During

Construction

14

  • Temporary parking restrictions
  • Contractor equipment / laydown area

Note: Please note that the maintenance of traffic layouts presented are preliminary and are subject to change. In particular the barrels, barriers, and mid-block crossings may be adjusted as the City coordinates with the Contractor. Citizens are encouraged to follow all pedestrian signage to allow safe passage around the active construction site.

slide-15
SLIDE 15
  • 6. Project Contacts

Project Manager (City of Alexandria): Brian Meli, P .E., Civil Engineer III City of Alexandria Department of Project Implementation Brian.Meli@alexandriava.gov 703.746.4110 http: / / alexandriava.gov/ dpi/ Project Inspectors (City of Alexandria) Rob McGuire, Project Inspector City of Alexandria Department of Project Implementation Robert.Mcguire@alexandriava.gov 703-746-4092 www.alexandriava.gov/ dpi/ Project Manager (Sagres Construction): Franklin Walker, P .E. Sagres Construction Franklin@sagresconstruction.com 703-357-2704 (cell)