SLIDE 1
East Division Elementary School GC/CM
March 7th, 2018 Board Update
SLIDE 2 Agenda for this evening
Madison Elementary School – Design Update – Gerry Pless
- Design Progress
- Cost Estimating and Value Engineering
- Permitting
- Land Use/Master Plan
East Division Elementary School – Construction Update – Kevin Fromm, Joe Ness, Craig Greene
- Look at updated progress photos
- Review Schedule and what's ahead
- Review potential Risks the Team is working through
SLIDE 3 MADISON ELEMENTARY STATUS UPDATE
Design Progress
Progressing
Submitted
Package
regarding Interior Design
packages in June/July
SLIDE 4 MADISON ELEMENTARY STATUS UPDATE
Cost Estimating and Value Engineering
Complete
Control Completed
Construction Budget Target
SLIDE 5 MADISON ELEMENTARY STATUS UPDATE
Cost Estimating and Value Engineering
- Alternates
- 4 Classroom Addition
- Pick-up Canopy
- Outdoor Amphitheater
- Unforeseen Issues
(addressed in estimate)
Replacement
SLIDE 6 MADISON ELEMENTARY STATUS UPDATE
Permitting
permits to the City of Mount Vernon
service permit to Skagit PUD
SLIDE 7 MADISON ELEMENTARY STATUS UPDATE
Land Use / Master Plan Progress
City Staff report.
- City reviewing response.
- Likely Hearings Examiner
and City Council in Late March.
SLIDE 8
Site Progress and Stabilization
1-17-18 Presentation to Board 3-7-18 Presentation to Board
SLIDE 9
Off-Site Utility and Pond work
3-7-18 1-17-18
SLIDE 10
Area D Classroom Wing/Main Entrance Progress Looking North
1-17-18 Presentation to Board 3-7-18 Presentation to Board
SLIDE 11
Area B Classroom Wing Progress
1-17-18 Presentation to Board 3-7-18 Presentation to Board
SLIDE 12
Outdoor Learning Area
1-17-18 Presentation to Board 3-7-18 Presentation to Board
SLIDE 13
Library Progress Interior Looking to the South
1-17-18 Presentation to Board 3-7-18 Presentation to Board
SLIDE 14
Area B Classroom Wing Interior Progress
1-17-18 Presentation to Board 3-7-18 Presentation to Board
SLIDE 15
Area C Classroom Wing Interior Progress 1st and 2nd Floor
3-7-18 1-17-18
SLIDE 16 Upcoming Schedule Milestones
Mar 2018 APR 2018 MAY 2018 JUNE 2018
Complete
- Wing A, B & C Finishes
- ngoing, start Wing D
Finishes
sidewalk
Building
Finishes Ongoing
Complete
underway on the exterior
- f the site
- Begin MEP Startup and
Commissioning
A, C & D ongoing
Complete
in
Complete
- All Finishes Complete
- Owner/Architect Punch
- Project Demobilization
- Finalize Elevator
- Final Inspections
SLIDE 17 Ongoing Risk Mitigation
- One recordable safety incident
- Structure 100% Complete
- Building 100% Dried in
- Submittals 99% complete
- MACC Contingency use still less than $300,000