4/11/2018 1 O RCHARD P ARK I NTERCOUNTY D RAIN L IVINGSTON AND G ENESEE C OUNTIES Meeting to Determine Necessity Preliminary Engineering Update April 11, 2018 2 Project History No established drain within drainage district currently


  1. 4/11/2018 1 O RCHARD P ARK I NTERCOUNTY D RAIN L IVINGSTON AND G ENESEE C OUNTIES Meeting to Determine Necessity Preliminary Engineering Update April 11, 2018 2 Project History � No established drain within drainage district currently � Petitioned to establish drainage district filed with Livingston County Drain Commissioner in September 2015 � Determined practical by Drain Board - May 2016 � Draft Preliminary Engineering Report - January 2017 � Engineer evaluated additional scenarios in 2017 � Level of Service and Cost-Benefit analysis � Updated route was established on the main drain � Petition to establish and construct drain received by LCDC on January 31, 2018 1

  2. 4/11/2018 3 Drainage District and Drain Route � Drainage District = 476 acres • 316 acres-Genesee County • 160 acres-Livingston County � The Main Drain route was updated to align with parcel boundaries on January 9, 2018 (6,100 feet) � East Branch provides outlet from existing retention basin (3,230 feet) 4 Orchard Park Retention Basin Flooding Frequency � In last 10 years, the basin flooded 4 times � Also, near flooding in 5/2015 and 5/2016 Photo taken May 2014 by Craig Saddler 2

  3. 4/11/2018 5 Updated Design Scenarios � In February 2017, additional scenarios were performed for the enclosed portion of the East Branch � Scenario 1 was included in the Draft Report � Scenarios 2 and 3 reduce the pipe sizes but the max HGL would increase � Scenario 4 reduces level of service and project costs Maximum Basin Outlet Design Max HGL Scenario No. Allowable HGL Diameter Drain Time (hrs) Storm (feet) (feet) (feet) 1 25-year 898.5 3 898.4 6 2 25-year 901 2 899 15 3 25-year 901 1.5 899.27 30 4 10-year 898.5 2 898.08 12 6 Easements � Estimated 25 easements required � Final drain route and project schedule to be impacted by easement acquisition 3

  4. 4/11/2018 7 Next Steps (if deemed necessary) � Finalize Preliminary Engineering Report � Obtain additional field survey � Complete Preliminary Plans � Draft easement documents and acquire easements � Finalize Construction Plans, obtain permits � Issue Bid Documents 4

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.