Allin Drain: On-Site Meeting Section 78: Improvements & Updates - - PowerPoint PPT Presentation

allin drain on site meeting
SMART_READER_LITE
LIVE PREVIEW

Allin Drain: On-Site Meeting Section 78: Improvements & Updates - - PowerPoint PPT Presentation

Allin Drain: On-Site Meeting Section 78: Improvements & Updates to Report Monica Shade, P. Eng. Presentation Overview Introduction to the Drainage Act History of the Allin Drain Section 78 of the Drainage Act Next Steps


slide-1
SLIDE 1

Monica Shade, P. Eng.

Allin Drain: On-Site Meeting

Section 78: Improvements & Updates to Report

slide-2
SLIDE 2

Presentation Overview

  • Introduction to the Drainage Act
  • History of the Allin Drain
  • Section 78 of the Drainage Act
  • Next Steps
  • Questions
slide-3
SLIDE 3

Introduction to the Drainage Act

  • The Drainage Act is legislation unique to Ontario
  • Means for landowners to solve drainage problems
  • Two methods under the Drainage Act:

– Mutual Agreement Drains – Petition Drains

  • Allin Drain is an existing Petition Drain adopted under

bylaw.

slide-4
SLIDE 4

What is a Petition Drain?

  • Physically: a “Petition Drain” is a drainage system comprised
  • f ditches, pipes or other means to convey water to a

sufficient outlet.

slide-5
SLIDE 5

What is a Petition Drain?

  • Legally: a “Petition Drain” is a drainage system that has been

adopted by by-law. – Petitioned for by landowners for the right of drainage. – The municipality has the obligation to construct and maintain a “Petition Drain” to the design of an engineer.

  • Purpose: the removal of excess surface water from the

properties within the watershed area. – Reduction of flooding (lawns, basements etc.) – Increased longevity of public infrastructure – Increased production on agriculture lands – Outlet for tile drainage

slide-6
SLIDE 6

How is a Petition Drain Established?

Drainage Issue Petition to Council Engineer Appointed On-Site Meeting Report Prepared Council to Consider Report Appeals Period Construction By-Law Adopted Costs Assessed

slide-7
SLIDE 7

Petition Drain Summary

Community Project – Petitioned for by landowners within a watershed – Developed through public process – Appeal periods for objections. Legal Existence – Adopted by by-law – All landowners have the right of drainage – All landowners share costs of construction/maintenance Municipal Responsibilities – Obligated to maintain drain on behalf of landowners

slide-8
SLIDE 8

History of the Allin Drain

  • Originally partially constructed as an award drain;

– Known as D.W. Hutchison Award Drain;

  • Petitioned to be converted to a Petition Drain in 1978;

– New report prepared for the Allin Drain and Branch; – Latest governing report dated May 1979.

  • Consists of approximately 4.7 km of open ditch:

– Allin Drain: 4.3 km – Guild-Allin Branch: 400 m

  • Area drains:

– approximately 4,000 acres

slide-9
SLIDE 9

What are the concerns with the current Engineer’s Report?

  • Age of current Engineer’s Report;
  • Change in land use;
  • Land development – severances, etc.

What are the concerns with the current Drain Conditions?

  • Alignment;
  • Culverts;
  • Erosion;
  • Blockages;
  • Vegetation growth;
  • Sedimentation.

How can these issued be resolved?

  • Section 78 of the Drainage Act.
slide-10
SLIDE 10

Section 78 of the Drainage Act

This section allows for changes to a drain after a by-law has been adopted.

  • Changing the course of the drainage works.
  • Making a new outlet for the whole or any part of the drainage works.
  • Constructing a tile drain under the bed of the whole or any part of the

drainage works.

  • Constructing, reconstructing or extending embankments, walls, dykes,

dams, reservoirs, bridges, pumping stations or other protective works in connection with the drainage works.

  • Otherwise improving, extending to an outlet or altering the drainage

works.

  • Covering all or part of the drainage works.
  • Consolidating two or more drainage works. 2010, c. 16, Sched. 1, s. 2 (27).
slide-11
SLIDE 11

Section 78 Process (Improvements / Updates to Engineer’s Report)

Improvements

  • r Updates

Required Engineer Appointed Engineer’s Report Prepared Council to Consider Appeals Improvements Where Required By-Law Adopted Cost Assessed

slide-12
SLIDE 12

Engineer’s Report

  • Drawings (Plan/Profiles/Specifications)
  • Watershed Boundary
  • Cost Estimate
  • Assessments
  • Crossings
  • Future Maintenance
slide-13
SLIDE 13

Next Steps

  • 1. Respond to Questions / Drainage Concerns
  • 2. Topographic Survey & Environmental Field Review
  • 3. Confirm Watershed Boundary
  • 4. Investigate Drain Improvements
  • 5. Prepare Final Report
  • 6. Submission of Final Report to Council for circulation to

landowners.

Topographic Survey & Environmental Review

  • Survey crew staff and a biologist will be out collecting information in

the near future.

  • Staff will only enter properties where the Allin Drain resides.
slide-14
SLIDE 14

Questions

Contact Information Drainage@mcintoshperry.com