4/11/2018 1
ORCHARD PARK INTERCOUNTY DRAIN
Intercounty Drain Board and Public Meeting Wade Trim Inc. January 18, 2017
1
Purpose of Meeting
Background and Problems Drainage District Drain Design
Drain route Crossings Storage areas
Background and Problems Petitioned filed by Livingston County Drain - - PDF document
4/11/2018 O RCHARD P ARK I NTER C OUNTY D RAIN Intercounty Drain Board and Public Meeting Wade Trim Inc. January 18, 2017 1 Purpose of Meeting Background and Problems Drainage District Drain Design Drain route Crossings
1
Background and Problems Drainage District Drain Design
Drain route Crossings Storage areas
Petitioned filed by Livingston County Drain
Commissioner in September 2015
Determined practical by Drain Board May 2016 No established drain within drainage district
currently
Orchard Park Retention Pond has no outlet Flooding in other areas within district
In last 10 years, the basin flooded 4 times:
3/2006 4/2012 4/2013 5/2014
Basement floods once every 2.5 years It was close to flooding in 5/2015 and 5/2016 Based on above information, basin is assumed
to flood every 2-years (2-year storm)
Photo taken May 2014 by Craig Saddler
Completed a field inspection of the potential position of the new drain Evaluated the existing culvert crossings Hydraulic analysis for proposed Developed recommendations for improvements Prepared opinion of construction costs
What is the Drainage District?
Lands that contribute water runoff into the drain Serves as special assessment district
Drainage District for Orchard Park Drain includes:
Tyrone Township, Livingston County Fenton Township, Genesee County Landowners
Orchard Park Retention Basin
Aerial Photos
Landuse Conflicts with drain alignment
Local topography (2 foot contours) Recent field survey
Spot elevations Culvert sizes Existing drainage Possible drain alignment
Soil data
Hydrology
25-year design storm for Main Drain (>300 acres) 25-year design storm for Orchard Park detention basin outlet 10-year design storm for East Branch (<300 acres) Flow information based on MDEQ methodology “Computing Flood
Discharges For Small Ungaged Watersheds”
MDEQ SCS peak discharge spreadsheet
Hydraulics
Hydraulic profiles developed using USACE HEC-RAS
Horizontal and vertical drain alignment developed within the GIS
environment
Horizontal drain alignment intersected with surface model using GIS 3D
Spatial Analyst Tool to develop drain overbank elevations
Initial vertical drain profile developed within excel using the drain
Legend
Orchard Park Drain
Proposed Culvert East Branch East Branch, Enclosed Existing Main Drain
Red Line is enclosed drain Yellow Line is open channel with
crossing at Linden Road
3 ft 3.5 ft Orchard Park Detention Basin
395 feet berm Provides 402,000 cf of storage Outlet diameter = 3 ft Max depth = 5.6 ft (893.6
feet)
28.7% peak reduction Decrease culvert 1 from 5.5 ft
to 5 ft
Berm Berm
Stage (ft) Cumulative Volume (cf) 2 55,769 4 178,176 6 402,426
Elevation (feet) Cumulative Volume (cubic feet) 892 893 12,681 894 40,401 896 137,173 898 287,568 900 493,896
Minimum basement elevation = 899.50 feet Maximum pond elevation = 898.50 feet
Culvert # Location Material Culvert Size (ft) 1 Bennett Lake Road Concrete Box 8’x3’ 2 Linden Road (North) Concrete Elliptical 5.7’x3.6’ 3 Lobdell Road Concrete Box 5’x3’ 4 Linden Road (South) RCP 3’ 1 2 3 4
Outlet Pipe Drain Outlet
Work from one side of drain to excavate new drain Clearing and Grubbing of trees and brush within new drain rights-of-way
Maintenance road to be established along one drain bank for future maintenance
Construct stable side slopes from 2H:1V to 3H:1V (Horizontal:Vertical) Level spoil along drain banks
Remove within lawn areas
Total Estimated Cost
$890,000 476 acres in drainage district
Submit plans
August…