background and problems
play

Background and Problems Petitioned filed by Livingston County Drain - PDF document

4/11/2018 O RCHARD P ARK I NTER C OUNTY D RAIN Intercounty Drain Board and Public Meeting Wade Trim Inc. January 18, 2017 1 Purpose of Meeting Background and Problems Drainage District Drain Design Drain route Crossings


  1. 4/11/2018 O RCHARD P ARK I NTER C OUNTY D RAIN Intercounty Drain Board and Public Meeting Wade Trim Inc. January 18, 2017 1 Purpose of Meeting � Background and Problems � Drainage District � Drain Design � Drain route � Crossings � Storage areas 1

  2. 4/11/2018 Background and Problems � Petitioned filed by Livingston County Drain Commissioner in September 2015 � Determined practical by Drain Board May 2016 � No established drain within drainage district currently � Orchard Park Retention Pond has no outlet � Flooding in other areas within district Orchard Park Detention Basin Flooding Frequency � In last 10 years, the basin flooded 4 times: � 3/2006 � 4/2012 � 4/2013 � 5/2014 � Basement floods once every 2.5 years � It was close to flooding in 5/2015 and 5/2016 � Based on above information, basin is assumed to flood every 2-years (2-year storm) Photo taken May 2014 by Craig Saddler 2

  3. 4/11/2018 Survey and Design Process � Completed a field inspection of the potential position of the new drain � Evaluated the existing culvert crossings � Hydraulic analysis for proposed � Developed recommendations for improvements � Prepared opinion of construction costs Drainage District � What is the Drainage District? � Lands that contribute water runoff into the drain � Serves as special assessment district Orchard Park Retention Basin � Drainage District for Orchard Park Drain includes: � Tyrone Township, Livingston County � Fenton Township, Genesee County � Landowners 3

  4. 4/11/2018 Drain Design Process Data Collected � Aerial Photos � Landuse � Conflicts with drain alignment � Local topography (2 foot contours) � Recent field survey � Spot elevations � Culvert sizes � Existing drainage � Possible drain alignment � Soil data Drain Design Process Hydrologic and Hydraulic Analysis Hydrology � 25-year design storm for Main Drain (>300 acres) � 25-year design storm for Orchard Park detention basin outlet � 10-year design storm for East Branch (<300 acres) � Flow information based on MDEQ methodology “Computing Flood Discharges For Small Ungaged Watersheds” � MDEQ SCS peak discharge spreadsheet Hydraulics � Hydraulic profiles developed using USACE HEC-RAS 4

  5. 4/11/2018 Drain Alignment Development � Horizontal and vertical drain alignment developed within the GIS environment � Horizontal drain alignment intersected with surface model using GIS 3D Spatial Analyst Tool to develop drain overbank elevations � Initial vertical drain profile developed within excel using the drain overbank elevation as a starting point Proposed Drain Alignment Legend Proposed Culvert Orchard Park Drain Main Drain East Branch East Branch, Enclosed Existing 5

  6. 4/11/2018 Main Drain Detail (Profile) System Overview East Drain Detail (Plan) � Red Line is enclosed drain � Yellow Line is open channel with crossing at Linden Road 6

  7. 4/11/2018 East Drain Detail (Profile) Orchard Park Detention Basin 3 ft 3.5 ft Main Drain Potential North Storage • Assume storage invert = 928 feet • Storage depth of 930 feet impacts parcels • Excavation required to develop storage volume • Assumed not feasible 7

  8. 4/11/2018 South Storage Cumulative Stage (ft) Volume (cf) � 395 feet berm 0 0 2 55,769 � Provides 402,000 cf of storage 4 178,176 6 402,426 � Outlet diameter = 3 ft � Max depth = 5.6 ft (893.6 feet) � 28.7% peak reduction � Decrease culvert 1 from 5.5 ft to 5 ft Berm Berm Orchard Park Detention Basin Stage Storage Elevation Cumulative Volume (feet) (cubic feet) 892 0 893 12,681 894 40,401 896 137,173 898 287,568 900 493,896 8

  9. 4/11/2018 Orchard Park Floor Elevations Minimum basement elevation = 899.50 feet Maximum pond elevation = 898.50 feet Preliminary Culvert Sizes Culvert Size Culvert # Material Location (ft) 1 Concrete Box Bennett Lake Road 8’x3’ 3 Concrete 2 5.7’x3.6’ Linden Road (North) Elliptical 3 Concrete Box 5’x3’ Lobdell Road 2 4 RCP 3’ Linden Road (South) 4 1 9

  10. 4/11/2018 Drain Outlet Drain Outlet Outlet Pipe Open Channel Improvements � Work from one side of drain to excavate new drain � Clearing and Grubbing of trees and brush within new drain rights-of-way � Maintenance road to be established along one drain bank for future maintenance � Construct stable side slopes from 2H:1V to 3H:1V (Horizontal:Vertical) � Level spoil along drain banks � Remove within lawn areas 10

  11. 4/11/2018 Cost Estimate at Preliminary Design � Total Estimated Cost � $890,000 � 476 acres in drainage district Tentative Project Schedule � Submit plans � August… 11

  12. 4/11/2018 Questions and Comments 12

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend