The Drainage Act Tow nship of East Zorra - Tavistock February 4, - - PowerPoint PPT Presentation

the drainage act
SMART_READER_LITE
LIVE PREVIEW

The Drainage Act Tow nship of East Zorra - Tavistock February 4, - - PowerPoint PPT Presentation

The Drainage Act Tow nship of East Zorra - Tavistock February 4, 2015 Why Have a Drainage Act? Ontario has a surplus of annual precipitation this advantage can be a disadvantage Without the Drainage Act, drainage issues are


slide-1
SLIDE 1

The Drainage Act Tow nship of East Zorra - Tavistock February 4, 2015

slide-2
SLIDE 2

Why Have a Drainage Act?

  • Ontario has a surplus of annual precipitation

– this advantage can be a disadvantage

  • Without the Drainage Act, drainage issues are

resolved through the courts, whose views are: – Surface water has no right of drainage – A lower landowner can protect their property by building berms or dykes – Owners can be held liable for damages for modifying natural watercourses

slide-3
SLIDE 3

Why Have a Drainage Act?

  • An alternative to resolve Common Law

disputes

  • Procedure for constructing “drainage works” to

resolve drainage problems

  • “Drainage Works” are more commonly known

as “Municipal Drains”.

slide-4
SLIDE 4

What Is A “Drainage Works”? Drainage Act defines “drainage works” as: “…a drain constructed by any means, including the

improving of a natural watercourse, and includes works necessary to regulate the water table or water level within or on any lands or to regulate the level of the waters of a drain, reservoir, lake or pond, and includes a dam, embankment, wall, protective works or any combination thereof…”

slide-5
SLIDE 5

The Petition Process

  • All new drains must be initiated by Petition:
  • Petition is a legal document
  • Petitioners become financially responsible as

soon as the petition is signed and submitted

slide-6
SLIDE 6

Petition Submission To Council Council considers petition – Council may reject a petition – Council may request an environmental appraisal or benefit/cost statement Council circulates petition to CA’s & MNR for comment (also include Fisheries & Oceans)

  • Agencies may request an environmental

appraisal

slide-7
SLIDE 7

Appointment

  • f Engineer
  • Council appoints independent engineer (s.8)

– Engineer must be fair and impartial (S.11)

  • Appointment by by-law or resolution (S.8)

– Appointed engineer has right of entry

  • nto private property (S.12)
  • Working with the engineer, the clerk sends

notice of an “on-site meeting”

slide-8
SLIDE 8

On-Site Meeting Engineer’s Responsibilities:

  • Determine validity of petition
  • Determine landowner/agency needs &

concerns

slide-9
SLIDE 9

Preliminary Report

  • Council may instruct engineer to prepare a

preliminary report

  • Optional, unless benefit/cost statement or an

environmental appraisal has been requested

  • Allows different options & costs to be explored

Meeting To Consider Preliminary Report:

  • Council Decision (based on info in report)
  • Appeal available to the Tribunal
  • Who pays if council decides not to proceed?
  • Petitioners’ Decision
  • Petitioners pay if decision not to proceed
slide-10
SLIDE 10

Final Report

  • Final Report must include:

– plans, profiles, specifications – total cost estimate – assessment schedule – allowances – other matters

  • Must consider individual property owner needs
  • Along with report, a key component of the

engineer’s responsibilities is to obtain necessary permits/approvals

slide-11
SLIDE 11

Field Survey

Survey would:

Identify drainage features

Record soil details

Record tile outlets

Record other features e.g. fences, pipelines

Opportunity to discuss project with owners

slide-12
SLIDE 12

Drain Plan

Plan shows:

Watershed boundary

Location of drain

Property boundaries including lot/conc.

Other features (e.g. roads, railways)

slide-13
SLIDE 13

Drain Profile

slide-14
SLIDE 14

Assessment Schedule

slide-15
SLIDE 15

Drainage Assessments Review

  • Benefit Assessment
  • Outlet & Injurying Liability Assessment
  • Special Benefit Assessment
  • Special Assessment (Sec. 26)

“…the public utility or road authority shall be assessed for and shall pay all the increase of cost of such drainage works caused by the existence of the works of the public utility or road authority.”

slide-16
SLIDE 16

The Final Report

  • Report submitted to council
  • Council considers report
  • Council conducts a “Meeting to Consider

Report” with landowners, agencies and

  • ther interested parties

At Meeting To Consider Report: If Petitioners decided not to proceed: Costs levied & project stops If Petitioners decide to continue: First & Second Reading of By-law

slide-17
SLIDE 17

Council’s Role At Meeting To Consider Report

Council Can:

  • Chose to accept report – gives two readings to

by-law (S.44 & 45)

  • Refer report back to engineer for changes

(S.57)

  • Do nothing - Petitioners have right of appeal to

Tribunal (S.45) Council Cannot:

  • Modify the report of the engineer
slide-18
SLIDE 18

Appeals: Court of Revision (CoR)

  • Hears appeals on assessments only
  • Appointed by Municipality

– Must be eligible to be elected to council – If council appoints members of council to serve on CoR, separate the two responsibilities

slide-19
SLIDE 19

Appeals: Agriculture, Food & Rural Affairs Appeal Tribunal – Appeals from Court of Revision – Technical appeals Appeals: Drainage Referee – Legal or procedural appeals

slide-20
SLIDE 20

Final Authorization

  • After all appeals have been dealt with and a

by-law adopting the engineer’s report is passed … – Construction of the project is authorized, even across properties opposed to the drain – Costs can be assessed to the lands – Drain now has legal existence and becomes part of the municipality’s infrastructure

slide-21
SLIDE 21

Physical Forms of Municipal Drain

slide-22
SLIDE 22

What Is A Municipal Drain?

  • Community Project: Developed through a

public process.

  • Legal Existence: Adopted by by-law
  • Municipal Infrastructure: Local municipality is

responsible for management of the drainage system and could be liable if they do not fulfill their responsibilities.

slide-23
SLIDE 23

Management

  • f Municipal

Drains

slide-24
SLIDE 24

Drainage Superintendent Responsibilities: Manages municipal drains on behalf of council

  • From S. 93(3) of the Drainage Act:

a) inspect every drainage works b) initiate and supervise the maintenance and repair of municipal drains c) assist in the construction or improvement of municipal drains d) report to council on the superintendent’s activities

slide-25
SLIDE 25

Maintenance & Repair SECTION 74:

Any drainage works constructed under a by-law passed under this Act … …shall be maintained and repaired by each local municipality through which it passes… …at the expense of all the upstream lands and roads … in the proportion determined by the then current by-law pertaining thereto…

  • Sec. 79: Potential liability if notice given by an affected property owner.

“Maintenance” means the preservation of a drainage works. “Repair” means the restoration of a drainage works to its original condition.

slide-26
SLIDE 26

Improvements: SECTION 78:

  • To make improvements/changes to the

“communally accepted” standards for a drain, must have new communal acceptance

  • New engineer’s report using the same general

process as for a new drain, but no petition required

  • Note: Landowners may request

improvements, but this is not a petition; it is still council’s decision to proceed

“Improvement” means any modification of or addition to a drainage works intended to increase the effectiveness of the system.

slide-27
SLIDE 27

Enforcement On drainage systems constructed under the Drainage Act, the municipality has ability to take action against:

  • Any owner or occupant for obstructing a drain

– S.80

  • Any person for damaging a drain – S.82
slide-28
SLIDE 28

Grants OMAFRA provides grants: 1.Towards the share of the cost of drain construction that is assessed to agricultural property owners: 1/3 south; 2/3 north 2.Towards the share of the cost of drain repair

  • r maintenance assessed to agricultural

property owners: 1/3 south; 2/3 north 3.To municipalities towards the cost of employing a drainage superintendent (50%)