DPW Road Projects Updates
Tuesday, October 15, 2019 GSPE
DPW Road Projects Updates Tuesday, October 15, 2019 GSPE Line-up - - PowerPoint PPT Presentation
DPW Road Projects Updates Tuesday, October 15, 2019 GSPE Line-up Village Streets Overview of DPW (FHWA & DoD Funded) Projects GTIP 2020-2023 Briefing Village Streets Update $2.9 M from THF NTP issued to Hawaiian Rock
Tuesday, October 15, 2019 GSPE
2019
NORTHERN REGION
Dededo 6,365 FT
Dededo 955 FT
Yigo 700 FT
Yigo 232 FT CENTRAL REGION
Agana Heights 900 FT
Agana Heights 500FT
Asan-Maina 1,054 FT
Barrigada 4,103 FT
Barrigada 540 FT
Chalan Pago 2,367 FT
Chalan Pago 2,567 FT
Mangilao 1,200 FT
Mangilao 1,094 FT
Mongmong-Toto-Maite 1,582 FT
Mongmong-Toto-Maite 486 FT
Sinajana 1,215 FT
Sinajana 444 FT SOTHERN REGION
Agat 1,320 FT
Inarajan 2,106 FT
Talofofo 1,413 FT
Yona 3,425 FT
Government of Guam DPW Ongoing Construction Projects
Government of Guam DPW Ongoing Construction Projects
Government of Guam DPW Ongoing Construction Projects
Projects Complete
$ 8M Feb 2020
$44M March 2020
Government of Guam DPW Ongoing Construction Projects
Projects Estimate IFB Date
Aug 2019
4th Q 2019
4th Q 2019
1st Q 2020
$1 M 2020-2023
$4 M 2020-2023
$2.5 M 2020-2023
$1 M 2020-2023
Government of Guam DPW Upcoming Construction Procurements
Projects Under Design Design Complete
2nd Q 20
2nd Q 20
1st Q 20
2nd Q 20
Completed
Completed
Completed
Completed
Completed
Completed
projects FY 2020 Design Procurement
Route 14 Route 14B
Route 14 and Route 14B Project Schedule and Cost
Route 14 Route 14B Estimated Cost $10M $14M Design Completion May 2018 October 2015 Begin Public Outreach May 2018 July 2015 Advertise for Bids June 2018 Summer 2018 Start Construction Dec 2018 Spring 2019 Completion 15 Months 15 Months
Route 14 Existing Project Features
Reconstruct Sidewalks Resurface Traffic Circle Pedestrian Access ADA Accessibility Resurface Route 14
safety and access control
to Bishop Flores Circle
Pedestrian Access Steep Grading Existing Utilities Bus Stops Rolling Terrain Flooding
Road
from Route 1 to Carmen Memorial Rd.
Design Innovations being Advanced by DPW Cont.
Mechanical Stabilized Earth (MSE) Retaining Wall
Project –Geosynthetic Reinforced Soil (GRS) Integrated Bridge System
Design Innovations being Advanced by DPW
Project – Cement Treated Base
Grouted Rock Nail Wall for rock cut
Route 14 Visualization
Route 14 Visualization
Route 14B Visualization (Ernst and Young to Royal Gardens)
Route 14B Visualization (Route 1 to Ernst and Young)
Route 14B Visualization (Royal Gardens to Flower Shop)
Route 14B Visualization (Flower shop to Pale San Vitores)