DPW and Parks & Recreation Facility Site 1 10 Great Meadow - - PowerPoint PPT Presentation

dpw and parks amp recreation facility
SMART_READER_LITE
LIVE PREVIEW

DPW and Parks & Recreation Facility Site 1 10 Great Meadow - - PowerPoint PPT Presentation

Town of Burlington DPW and Parks & Recreation Facility Site 1 10 Great Meadow Road Site 2 1-3 Great Meadow Road Great Meadow Road Sites Proposed Site 1 (10 Great Meadow Rd) Existing DPW Site 2 (1-3 Great Meadow Rd) Great Meadow


slide-1
SLIDE 1

DPW and Parks & Recreation Facility

Site 1 – 10 Great Meadow Road Site 2 – 1-3 Great Meadow Road

Town of Burlington

slide-2
SLIDE 2

Existing DPW Site 2 (1-3 Great Meadow Rd) Proposed Site 1 (10 Great Meadow Rd)

Great Meadow Road Sites

slide-3
SLIDE 3

Existing DPW Site 2 (1-3 Great Meadow Rd) Proposed Site 1 (10 Great Meadow Rd)

Great Meadow Road Sites

slide-4
SLIDE 4

DPW and Parks & Recreation Facility

Site 1 10 Great Meadow Road

slide-5
SLIDE 5

+/- 12,000 SF +/- 3,500 SF

Existing Site

10 Great Meadow Road

slide-6
SLIDE 6

Existing Buildings

10 Great Meadow Road

slide-7
SLIDE 7

Existing Buildings

10 Great Meadow Road

slide-8
SLIDE 8

Untreated Sheet Flow Stormwater Runoff From Site

Existing Stormwater

10 Great Meadow Road

slide-9
SLIDE 9

Proposed Development Plan

Site 1 10 Great Meadow Road

slide-10
SLIDE 10

Demolish Existing Structures Demolish Existing Structures Remove Existing Pavement & Compacted Gravel Areas

Site Prep Plan

10 Great Meadow Road

slide-11
SLIDE 11

Proposed Site Plan

10 Great Meadow Road PROPOSED DPW / PARKS & RECREATION FACILITY

slide-12
SLIDE 12

Building Floor Plan

10 Great Meadow Road

slide-13
SLIDE 13

10 Great Meadow Road

DEEP SUMP HOODED CB’s OIL / GRIT SEPARATORS UNDERGROUND INFILTRATION CHAMBERS

Overflow

New Stormwater System

slide-14
SLIDE 14

10 Great Meadow Road

STORMWATER BASIN PARKING LOT DEEP SUMP HOODED CB’s

New Stormwater System

slide-15
SLIDE 15

10 Great Meadow Road

Knockdown Pad

KNOCKDOWN PAD

Overflow

slide-16
SLIDE 16

DPW and Parks & Recreation Facility

Site 2 1-3 Great Meadow Road

slide-17
SLIDE 17

Existing Site

1-3 Great Meadow Road

slide-18
SLIDE 18

Existing Site

1-3 Great Meadow Road

slide-19
SLIDE 19

Existing Site

1-3 Great Meadow Road

slide-20
SLIDE 20

Existing Stormwater

Untreated Sheet Flow Stormwater Runoff From Site

1-3 Great Meadow Road

slide-21
SLIDE 21

Proposed Development Plan

Site 2 1-3 Great Meadow Road

slide-22
SLIDE 22

Demolish Existing Structures Remove Existing Pavement & Compacted Gravel Areas

Site Prep Plan

1-3 Great Meadow Road

slide-23
SLIDE 23

Proposed Site Plan

1-3 Great Meadow Road

PROPOSED DPW FACILITY

slide-24
SLIDE 24

Building Floor Plan

1-3 Great Meadow Road

CANOPY

slide-25
SLIDE 25

1-3 Great Meadow Road

New Stormwater System

DEEP SUMP HOODED CB’s OIL / GRIT SEPARATORS Underground infiltration chambers STORMWATER BASIN

slide-26
SLIDE 26

Zoning

slide-27
SLIDE 27

SITE 1 (IG) SITE 2 (RO)

slide-28
SLIDE 28

SITE 1 (IG) SITE 2 (RO)

slide-29
SLIDE 29

SITE 1 SITE 2

slide-30
SLIDE 30

Zoning – 5.2.0 Density Regulation Schedule

Conforms to Zoning Bylaws Special Permit Required

Site 1 - 10 Great Meadow Road Site 2 – 1-3 Great Meadow Road

0.19

9 ft

slide-31
SLIDE 31

Permitting / Approvals Required

slide-32
SLIDE 32

Site 1 - 10 Great Meadow Road - Potential Permits Required

  • Notice of Intent from Conservation Commission
  • Planning Board Special Permit for Aquifer District
  • Pre-existing non-conforming use (Section 4.2.0 Principal Use Regulation Schedule)
  • VSQG, Wash bay, Vehicle Maintenance, Diesel Generator, Maintenance Fluids (8.3.5 Uses & Activities)
  • Planning Board - Special Permit for Frontage
  • Pre-existing / non-conforming (Section 5.2.0 Density Regulation Schedule)
  • Planning Board – Special Permit for FAR
  • Maximum .15, Proposed .19 (Section 5.2.0 allows up to .25 with reduced trip generation during peak hours)
  • Planning Board – Special Permit Yard Adjoining RO District
  • Pre-Existing Non-Conforming (Section 5.2.0 Requires 37’, Existing 12’)
  • Planning Board – Approval of number of parking spaces
  • Based on type and nature of use proposed (Section 7.2.5.a)

Site 1 - 10 Great Meadow Road

slide-33
SLIDE 33

Site 2 – 1-3 Great Meadow Road - Potential Permits Required

  • Notice of Intent from Conservation Commission
  • Planning Board - Special Permit for Principal Use Regulation Schedule
  • Pre-existing non-conforming use (Section 4.2.0 Principal Use Regulation Schedule) for

Municipal Maintenance and Garage Facilities in RO District

  • Planning Board Special Permit for Aquifer District
  • Pre-existing non-conforming use (Section 4.2.0 Principal Use Regulation Schedule)
  • Planning Board – Special Permit for pre-existing / non-conforming front yard setbacks
  • Building Setback (Section 5.2.0 Density Regulation Schedule) – Required 25’, Existing 9’, Proposed 9’
  • Planning Board - Off site parking within 200’ of lot (Section 7.2.0)
  • Planning Board – Approval of number of parking spaces
  • Based on type and nature of use proposed (Section 7.2.5.a)

Site 2 - 1-3 Great Meadow Road

slide-34
SLIDE 34

Pre-Existing Non-Conforming

Aquifer District

Proposed Project will not increase danger of pollution. It will better protect surface and groundwater through:

  • New stormwater system with TSS removal and oil/grit separators
  • Increased covered storage for vehicles/equipment with floor drains discharging to sewer – not stormwater
  • Dedicated fluid storage room with above ground storage with spill containment system and monitoring system
  • Enclosed Washbay – discharge to sewer system – not stormwater
slide-35
SLIDE 35

Pre-Existing Non-Conforming

Non-Conforming Uses and Structures

Proposed Project will not be more detrimental. It will improve the premises, neighborhood, and environment through:

  • Replacement of old / deteriorated structures with new structures
  • Storage of vehicles, equipment, and materials will be primarily under cover vs. outdoors
  • Setbacks will be either maintained or improved
  • New stormwater system with TSS removal and oil/grit separators
  • Dedicated fluid storage room with above ground storage with spill containment system and monitoring system
  • Enclosed Washbay – discharge to sewer system – not stormwater
slide-36
SLIDE 36

THANK YOU

Town of Burlington DPW and Parks & Recreation Facility