SLIDE 1
Digesters at La Crosse Provide some incredibly interesting - - PowerPoint PPT Presentation
Digesters at La Crosse Provide some incredibly interesting - - PowerPoint PPT Presentation
Replace or Rehab Anaerobic Digesters at La Crosse Provide some incredibly interesting information describing the La Crosse wastewater treatment plant. Provide historical information related to the Citys experience with other rehab
SLIDE 2
SLIDE 3
Impress anyone with an especially innovative use of PowerPoint (or any other) technology, and/or Impress anyone with the presentation capabilities of the presenters!
SLIDE 4
West coast of Wisconsin; approx. City population of 52,000. WWTP……
20 MGD facility Regional wastewater plant - currently receives flow from five areas
- utside corporate limits; approx. population served 85,000 – 90,000.
Anaerobic Digestion System
Four “vintage” digesters: Newest 1953….Oldest 1936 (original)
SLIDE 5
SLIDE 6
SLIDE 7
2002 – Three Primary Clarifiers
All steel Concrete tank restoration (epoxy injection) Handrail Project costs:
- Rehabilitation - $ 220,300
- Design, Engineering & Project Management - $100,000
2004 – Four Final and Two Rectangular Primary Clarifiers
All steel Concrete tank restoration (epoxy injection) Handrail Project costs:
- Rehabilitation - $ 829,000
- Design, Engineering & Project Management - $100,000
SLIDE 8
2011 – Two Gravity Thickeners
All steel One drive mechanism Concrete tank restoration (epoxy injection) Handrail Project costs:
- Rehabilitation - $ 220,100
- Design, Engineering & Project Management - $100,000
SLIDE 9
One 74’ diameter spiral-guided cover
Original cover installed in 1953; inspected in last five years as part of digester cleaning Remove cover from tank Structural and steel replacement as required Complete sandblast and re-paint Re-installation of cover into tank & start-up Project costs:
- Rehabilitation - $ 435,000
- Design, Engineering & Project Management - $100,000
Estimated cost to replace - $1.3 million
SLIDE 10
SLIDE 11
SLIDE 12
SLIDE 13
SLIDE 14
SLIDE 15
SLIDE 16
SLIDE 17
SLIDE 18
SLIDE 19
SLIDE 20
SLIDE 21
SLIDE 22
SLIDE 23
SLIDE 24
SLIDE 25
SLIDE 26
SLIDE 27
SLIDE 28
SLIDE 29
SLIDE 30
SLIDE 31
Project costs:
- Rehabilitation - $ 435,000
- Design, Engineering & Project Management - $100,000
Estimated cost to replace - $1.25 million
SLIDE 32
Inspection is critical first step. Capacity issues? Philosophy, i.e., replace just because it’s old…..?? Design has to assume some surprises along the way. On-site inspection during project!!!!! Resulting Value – La Crosse experience has been that rehabilitation can be a very cost-effective alternative to replacement.
SLIDE 33
Wastewater supervisors and staff City Engineering Department Process Equipment Repair Services
SLIDE 34