REDUCTION OF SANITARY SEWER INFIL TRATION AND INFLOW IN A PUBLIC - - PowerPoint PPT Presentation

reduction of sanitary sewer
SMART_READER_LITE
LIVE PREVIEW

REDUCTION OF SANITARY SEWER INFIL TRATION AND INFLOW IN A PUBLIC - - PowerPoint PPT Presentation

REDUCTION OF SANITARY SEWER INFIL TRATION AND INFLOW IN A PUBLIC SEWER SYSTEM A CASE STUDY OF THE VILLAGE OF OAK LAWN'S REHABILITATION PROGRAM June 26, 2014 2:15 pm to 3:00 pm Jared Wendorf, PE, CDM Smith Repaired Fracture and Holes C S


slide-1
SLIDE 1

REDUCTION OF SANITARY SEWER INFIL TRATION AND INFLOW IN A PUBLIC SEWER SYSTEM A CASE STUDY OF THE VILLAGE OF OAK LAWN'S REHABILITATION PROGRAM

June 26, 2014 2:15 pm to 3:00 pm Jared Wendorf, PE, CDM Smith

slide-2
SLIDE 2
slide-3
SLIDE 3

Repaired Fracture and Holes

slide-4
SLIDE 4

Acknowledgements

  • Larry Deetjen

Oak Lawn Village Manager

  • Jack Gallagher

Oak Lawn Village Engineer

  • Steve Barrett

Oak Lawn Public Works Director

  • Bill Meyer

Oak Lawn Sewers Crew Chief

  • Mandeera Wagle

CDM Smith Project Manager

  • Doug Youngblood CDM Smith Technical Lead

C S W E A -2 0 1 4 C o lle ctio n S y ste m s C o n fe re n ce

slide-5
SLIDE 5

Project Timeline

CSWEA-2014 Collection Systems Conference

2011 2012 2013 2014 2010 2015

Project Kickoff Begin Hydraulic Modeling Clean + Inspect Develop 2013 Rehab Approach Complete 2014 Rehab. Clean + Inspect Develop 2015 Rehab Approach Complete Master Plan Complete 2013 Rehab. Clean + Inspect Develop 2014 Rehab Approach Complete 2015 Rehab. Clean + Inspect Develop 2016 Rehab Approach

slide-6
SLIDE 6

Introduction to the Village of Oak Lawn Sewer S ystem

  • Oak Lawn incorporated in 1909
  • Approx 55,000 Residents
  • 8.5 Sq M iles
  • Sanitary Sewers installed M id-

Century

  • Separate Sewer Systems
  • Pipes are mostly clay

CSWEA-2014 Collection Systems Conference

slide-7
SLIDE 7

Hydraulic M odeling and Flow M onitoring

  • Objective –

Create a Sanitary Sewer M aster Plan—A Roadmap

– Comprehensive model of the entire system – Rainfall and flow data measured and integrated – Three Hydrograph Method

CSWEA-2014 Collection Systems Conference

slide-8
SLIDE 8
slide-9
SLIDE 9

Hydraulic M odeling and Flow M onitoring

  • Identify potential problem areas
  • Prioritize use of limited funds

CSWEA-2014 Collection Systems Conference

slide-10
SLIDE 10

Cleaning and T elevised Inspections

  • Development of 2012 Program
  • Use M aster Plan to identify two areas at most risk

– Clean and Inspect approximately 16,600 lf of pipe in projected

future problem areas

– Inspect approx 100 manholes – Time of Project –

8 working days

– Average 2,075 ft / day

  • Next Steps

– Analyze inspections and develop rehabilitation plan

CSWEA-2014 Collection Systems Conference

slide-11
SLIDE 11

Cleaning of Sanitary Sewers and T elevised Inspections—Prioritization of Rehab

  • High Priority

– Risk of collapse / sinkholes – M ajor structural damage – M ajor infiltration potential

  • M edium Priority

– Some infiltration potential – Structural damage likely to degrade to major

damage

  • Low Priority

– M ineral deposits – Fine roots – Hairline cracks, small sags

CSWEA-2014 Collection Systems Conference

slide-12
SLIDE 12

Pipe fractures In 10962

slide-13
SLIDE 13

Pipe fractures In 10961

slide-14
SLIDE 14

Offset joints and Intruding taps at 7288

slide-15
SLIDE 15

Fractures at 7374

slide-16
SLIDE 16

Hammer Tap – Infiltration Around Edges

slide-17
SLIDE 17

Intruding break-in tap at 7249

slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23
slide-24
SLIDE 24
slide-25
SLIDE 25
slide-26
SLIDE 26

Develop Plan for 2013 Rehabilitation

  • Select rehabilitation methods to repair approx 10,000 ft of

pipe

– Options for pipe repair:

  • pipe replacement
  • slip lining
  • CIPP
  • Spot repairs
  • Short liners
  • Break in tap repairs (LCR)
  • Lateral Grouting

CSWEA-2014 Collection Systems Conference

slide-27
SLIDE 27

Develop Plan for 2013 Rehabilitation

  • Select rehabilitation methods to rehab approx 50 manholes

– Options for manhole repair:

  • Raising M anhole Lids
  • Chimney Seals
  • Chemical Grouting
  • Cementitious Resurfacing
  • Concrete Surfacing at M anhole/ Liner Interface
  • Pipe Seals

CSWEA-2014 Collection Systems Conference

slide-28
SLIDE 28

Refrigerated Truck Water Source or Steam Source

slide-29
SLIDE 29

CIPP rehabilitation

slide-30
SLIDE 30

CIPP rehabilitation

slide-31
SLIDE 31

CIPP rehabilitation

slide-32
SLIDE 32
slide-33
SLIDE 33
slide-34
SLIDE 34

Execute 2013 Rehabilitation

  • Repair approx 10,000 ft of pipe and Rehab approx 50

manholes based on 2012 inspections results

  • Clean and Inspect 10,000 additional ft of pipe and inspect

approx 100 additional manholes (two additional sewersheds)

  • Provide unit cost rates that the Owner can use to authorize

rehab of newly inspected pipes and manholes

  • Repair newly inspected pipes and manholes

CSWEA-2014 Collection Systems Conference

slide-35
SLIDE 35

2013 Rehabilitation Summary

CSWEA-2014 Collection Systems Conference

Area Manholes Rehabilitated CIPP Lining in 2013 Additional Rehab Area #1

29 of 32 (91%) 5,389 of 6,022 lf (89%) two spot repairs

Area #2

37 of 60 (62%) 4,488 of 10,255 lf (44%) 1 short liner, 1 LCR

Area #3

42 of 71 (59%) 5,182 of 12,303 lf (42%) 1 short liner, 1 LCR

Area #4

18 of 40 (45%) 2,985 of 6,258 lf (48%)

slide-36
SLIDE 36
slide-37
SLIDE 37

Fractures and Hole in Pipe

slide-38
SLIDE 38

Repaired Fracture and Holes

slide-39
SLIDE 39
slide-40
SLIDE 40

Fractures – Imminent Risk of Collapse

slide-41
SLIDE 41

Repaired Fractures

slide-42
SLIDE 42
slide-43
SLIDE 43

Hole in Pipe Active Infiltration

slide-44
SLIDE 44

Location of Repaired Hole in Pipe Location of Infiltration Defect

slide-45
SLIDE 45
slide-46
SLIDE 46

Fractures – Pipe Approaching Collapse

slide-47
SLIDE 47

Repaired Fractures

slide-48
SLIDE 48

Cast in Place Pipe Structural Integrity

CSWEA-2014 Collection Systems Conference

slide-49
SLIDE 49

Analysis of 2013 Rehabilitation

  • Identify common sources of problems

CSWEA-2014 Collection Systems Conference

slide-50
SLIDE 50
slide-51
SLIDE 51
slide-52
SLIDE 52
slide-53
SLIDE 53
slide-54
SLIDE 54
slide-55
SLIDE 55
slide-56
SLIDE 56
slide-57
SLIDE 57
slide-58
SLIDE 58
slide-59
SLIDE 59
slide-60
SLIDE 60
slide-61
SLIDE 61
slide-62
SLIDE 62
slide-63
SLIDE 63

2014 Rehabilitation Work

slide-64
SLIDE 64

Creating a Sustainable Funding Source

  • 2012-2013 work was funded by Build America Bonds
  • The Village recognized the need for a sustainable funding

source

  • Benchmarking against similar communities showed that a

reasonable sewer rate increase was warranted

  • The funds from this increase are accounted for separately

in a fund allowing 1-2% of the system to be rehabilitated annually.

  • Spend approx $1M per year

CSWEA-2014 Collection Systems Conference

slide-65
SLIDE 65

Summary

  • The Village of Oak Lawn has successfully initiated a

comprehensive annual sanitary sewer rehabilitation program that is effective and sustainable.

  • The efficiency of the program increases with each year by

building upon specifications and improvements of prior years.

  • T
  • date, Oak Lawn has rehabilitated more than 20,000 linear

feet of pipe and 150 manholes, and is currently preparing for the next phase of rehab starting in Summer 2014.

slide-66
SLIDE 66

Lessons Learned

  • Emphasize the importance of the contractor walking the site
  • Hold a mandatory Pre-bid.
  • Communicate early and often with homeowners
  • Use LCR in combination with short liners
  • Have a protocol set up for resident issues
slide-67
SLIDE 67

Contact Information

Jared Wendorf, PE CDM Smith Chicago wendorfjw@cdmsmith.com