Runway Pavement and Airfield Electrical Rehabilitation Project
Dwight D. Eisenhower National Airport Wichita Airport Authority September 3, 2019
Runway Pavement and Airfield Electrical Rehabilitation Project - - PowerPoint PPT Presentation
Runway Pavement and Airfield Electrical Rehabilitation Project Dwight D. Eisenhower National Airport Wichita Airport Authority September 3, 2019 Project Background 2 2016 airport wide Pavement Condition Inventory found runway pavements
Dwight D. Eisenhower National Airport Wichita Airport Authority September 3, 2019
pavements conditions had changed to trigger pavement rehabilitation
decreasing and maintenance is increasing
pavements that should be removed to enhance airfield safety
runway re-designations are required
2
3
4
was selected thru the City staff screening and selection process
project scope and develop a preliminary project cost
5
N a r y f
n d
review by staff and the FAA with significant input from stakeholders
an FAA supplemental grant for $6.66 million to replace the RWY 1L- 19R keel (center) section
16th with Pearson Construction the lowest bidder.
6
7
8
Document Date Processed
Scope of Work Cost Base Contract July 11, 2017 Study phase $155,400 Supplemental Agreement No. 1 April 19, 2018 Additional geo-technical surveys due to unforeseen conditions $14,579 Supplemental Agreement No. 2
Design and bid services $682,600 Supplemental Agreement No. 3 June 18, 2019 Additional design on the runway keel sections due to notification from the FAA of the availability of supplemental discretionary grant funds $59,500 Supplemental Agreement No. 4
(request) Construction phase and project closeout services $1,729,500 Total contract cost to date $2,641,579
9
10
Agreement Dates Purpose Amount July 11, 2017 Initial budget for Study phase $200,000 November 27, 2018 Design and bid phase expenses and related initial project costs $732,600 June 18, 2019 Remainder of design and initial pre-construction costs $100,000 September 3, 2019 (request) Construction and remaining project costs $21,500,000 Total budget to date $22,532,600
It is recommended the Wichita Airport Authority approve the capital project budget adjustment and supplemental agreement, ratify the grant applications, authorize acceptance of grant funds and designate the Director of Airports to sign all documents related to the grants.
11