US 14 Improvements City of La Crosse, South Avenue Green Bay Street to Ward Avenue La Crosse County WisDOT Project ID 1641-02-02 Public Involvement Meeting #4 January 30, 2020 La Crosse Central High School Purpose o se of Meet Meeting


slide-1
SLIDE 1

City of La Crosse, South Avenue Green Bay Street to Ward Avenue La Crosse County WisDOT Project ID 1641-02-02

Public Involvement Meeting #4

US 14 Improvements

January 30, 2020 La Crosse Central High School

slide-2
SLIDE 2

Purpose o se of Meet Meeting

 Review the purpose of the US 14/South Avenue

project and past project efforts

 Review the recommended roadway improvement

alternative

 Discuss real estate impacts and acquisition  Gather information and input to be considered

during the final design process

Purpose of Meeting

slide-3
SLIDE 3

Proj

  • ject

ct O Ove vervie view

Project Overview

Green Bay St West Ave Ward Ave

N

slide-4
SLIDE 4

Projec ject O Objec bjectives es

 Improve safety along the

corridor

  • Remove left turns from

through traffic lanes

  • Improve intersection
  • perations

 Address pavement needs  Address accommodations

for bicycles, pedestrians, and transit

Project Purpose

slide-5
SLIDE 5

Projec ject P Process ess

 Public Involvement Meeting #1 – November 2014  Community Advisory Group  Coordination with City of La Crosse  Public Involvement Meeting #2 – March 2017  Selection of recommended alternative  Public Involvement Meeting #3 – July 2017

Past Project Efforts

slide-6
SLIDE 6

Projec ject P Process ess

Based on the following:

  • Level of safety/operational improvements
  • Impacts along the corridor
  • Public comments
  • PIM (written and verbal comments)
  • Community Advisory Group
  • WisDOT website
  • Input from separate City study

Selection of Recommended Alternative

slide-7
SLIDE 7

Possi ssible e Imp Improveme ements

Recommended Alternative

Minimum width with roundabouts/no bikes

slide-8
SLIDE 8

Projec ject P Process ess

WisDOT representatives

  • Jill Noel
  • Angie Kneip
  • Dave Selissen
  • Ashley Seibel
  • Plus 4 relocation agents

Real Estate Acquisition

slide-9
SLIDE 9

Projec ject P Process ess

Real Estate acquisitions

  • 104 total properties
  • Fee (permanent acquistions)
  • TLE (temporary limited easements)
  • Relocations
  • Appraisal staking completed fall 2019

Potential property impacts

  • Trees, landscaping, and signs

Real estate acquisition

  • 2020 - 2021

Real Estate Acquisition

slide-10
SLIDE 10

Projec ject P Process ess

Access evaluation

  • Removing some accesses
  • Property owners have been notified
  • WisDOT access representatives request property
  • wners meet with them individually after the

presentation if questions

Real Estate Acquisition

slide-11
SLIDE 11

Projec ject P Process ess

Spring 2020, Real Estate Blitz at WisDOT B-19, B-20; 3550 Mormon Coulee Road

The Blitz will be from 10am to 7pm for parcels being acquired via the nominal waiver process

All nominal offers to be sent to landowners in spring 2020

Real Estate Negotiations to take place from spring 2020 to July 2021

All real estate acquired by August 2021

Real Estate Acquisition and Schedule

slide-12
SLIDE 12

Projec ject P Process ess

Proceed with final design

  • Construction staging/traffic control
  • Transit coordination

Continue real estate acquisition process

Schedule

  • Final plans complete August 2021
  • Additional public involvement meeting
  • Construction begins spring 2022

Next Steps/Project Schedule

slide-13
SLIDE 13

Co Contac act In Informat mation

Ryan Murphy, PE OES Project Manager 2600 N. Mayfair Road, Suite 200 Milwaukee, WI 53226 (414) 607-6765 rmurphy@oesllc.com Project Website:

http://wisconsindot.gov/Pages/projects/by-region/sw/14lacrosse/default.aspx

Mailer in handout

Contact Information

slide-14
SLIDE 14

14

Your input is important!

Questions