1
Design Oversight Committee
March 17, 2017
Design Oversight Committee March 17, 2017 1 Agenda 1. Welcome and - - PowerPoint PPT Presentation
Design Oversight Committee March 17, 2017 1 Agenda 1. Welcome and Introductions - Tully 2. Meeting Purpose - Sam 3. Report Summary - Peter Dam Removal Concepts Water Supply Mitigation Options 4. Project Funding and Project
1
March 17, 2017
2 of 34
3 of 34
4 of 34
5 of 34
6 of 34
7 of 34
Project Categories Construction Cost (2015) Low (-30%) High (+50%) Mobilization $3,500,000 Site Preparation $11,800,000 Sediment Components $0 Slurry System Components $0 Dam Removal Components $9,200,000 Site Restoration $2,500,000 Subtotal $27,000,000 Contingency (30%) $8,100,000 Subtotal $35,100,000 Construction Contingency (15%) $5,300,000 Total $40,400,000 $28,300,000 $60,600,000
schedule
8 of 34
9 of 34
10 of 34
schedule
Project Categories Construction Cost (2015) Low (-30%) High (+50%) Mobilization $1,600,000 Site Preparation $900,000 Sediment Components $0 Slurry System Components $0 Dam Removal Components $8,000,000 Site Restoration 1,900,000 Subtotal $12,400,000 Contingency (30%) $3,700,000 Subtotal $16,100,000 Construction Contingency (15%) $2,400,000 Total $18,500,000 $13,000,000 $27,800,000 Note – The ROM construction cost of each additional orifice would be $1,000,000. 11 of 34
schedule
Project Categories Construction Cost (2015) Low (-30%) High (+50%) Mobilization $1,800,000 Site Preparation $1,900,000 Sediment Components $0 Slurry System Components $0 Dam Removal Components $8,000,000 Site Restoration 1,900,000 Subtotal $13,600,000 Contingency (30%) $4,100,000 Subtotal $17,700,000 Construction Contingency (15%) $2,700,000 Total $20,400,000 $14,300,000 $30,600,000 Note – The ROM construction cost of each additional orifice with gate would be $2,100,000. 12 of 34
13 of 34
14 of 34
15 of 34
Project Categories Construction Cost (2015) Low (-30%) High (+50%) Mobilization $4,400,000 Site Preparation $3,600,000 Sediment Components $15,000,000 Slurry System Components $0 Dam Removal Components $8,000,000 Site Restoration $2,200,000 Subtotal $33,200,000 Contingency (30%) $10,000,000 Subtotal $43,200,000 Construction Contingency (15%) $6,500,000 Total $49,700,000 $34,800,000 $74,500,000 16 of 34
17 of 34
Evaluation Category Evaluation Criteria Description A. Biological Resources Steelhead Passage Time to reach steelhead passage through dam/reservoir area Steelhead Health Scale of severity of impacts for suspended sediment to steelhead Ecological Health Acres of vegetation communities impacted by actions at dam/reservoir Ecological Health Acres of future vegetation communities within reservoir area of impact B. Technical & Implementation ROM Construction Cost Rough Order of Magnitude Construction Cost Risk Management Flexibility to manage risk and react to unanticipated conditions C. Sediment Transport & Water Quality Water Supply Wet cycle percent reduction in Lake Casitas water storage levels Water Supply Dry cycle percent reduction in Lake Casitas water storage levels
18 of 34
Dam Removal Concept Implementation Duration (years) DRC-1 3 to 6 DRC-2A/B 2 to 5 / 3 to 9 DRC-3 2 to 5
19 of 34
Dam Removal Concept Phase I Severity Score DRC-1 13 DRC-2A 13 DRC-2B 13, but second flush possible with gate DRC-3 minimal
Fish Response to Suspended Sediments for Adult Salmonids (using the empirically generated model of Newcombe and Jensen, 1996)
20 of 34
Vegetation Community Impacts (acres) DRC-1 DRC-2 DRC-3 Mixed Chaparral 0.6 0.4 1.3 Freshwater Marsh 1.9 1.6 2.5 Oak Woodland 1.0 0.0 3.5 Riparian Scrub 7.2 5.7 15.5 Riparian Woodland 14.2 12.0 37.0 Coastal Sage Scrub 0.5 0.2 2.1 Total 25.5 19.6 69.0 21 of 34
Vegetation community DRC-1 (acres) DRC-2 (acres) DRC-3 (acres) Herbaceous Riparian 7.4 7.4 7.9 Riparian Scrub 17.5 17.5 15.8 Riparian Woodland 26.3 26.3 14.4 Oak Woodland 21.5 21.5 28.9 Coastal Sage Scrub 59.2 59.2 53.6 Mixed Chaparral 22.1 22.1 39.3 Total 154.0 154.0 159.9 22 of 34
DCR Range of Magnitude Construction Cost (ROMCC) (-30%) Estimate (+50%) DRC-1 $28,300,000 $40,400,000 $60,600,000 3 DRC-2A $13,000,000 $18,500,000 $27,800,000 1 DRC-2B $14,300,000 $20,400,000 $30,600,000 2 DRC-3 $34,800,000 $49,700,000 $74,500,000 4
23 of 34
24 of 34
25 of 34
26 of 34
27 of 34
Type of Mitigation
Description
Cost Environ. Feasibility Adapt. Develop Further Diversion Replace.
Diversion from Matilija to Canal
Diversion from NF Matilija to Canal
Diversion from Matilija to NF Matilija to Canal
Replacement Supplies
Infiltration Galleries
Water Transfer from SWP
Water Transfer from MWD to Casitas via Carpinteria
CMWD Transfers to MOWD
Groundwater Transfers
Desalination
New Wells at Santa Paula Basin
New Well Heads at Foster Park
San Antonio Creek Diversion Expansion
Re-Use & Conservation
Recycled Water – Ojai Valley Waste Water Treatment Plant
Recycled Water – Ventura Water Reclamation
Recycled Water – Scalping Plants
Urban and Agricultural Conservation
Crop Idling Transfers
Treatment
Robles Diversion Dam Improvements
Robles-Casitas Canal Treatment
Casitas Reservoir Oxygenation Enhancement
Back-flushing of Meiners Oaks Wells 1 and 2
CMWD Water Treatment Plant System Modifications
CMWD Water Treatment Plant Roughing Filters
28 of 34
Type of Mitigation Description Volume1. (AFY) Volume2. (% per year) Cost ($) Replacement Supplies CMWD Transfers to MOWD N/A N/A $20K New Wells at Santa Paula Basin 1,400 11% $250K New Well Head at Foster Park 750 5.9% $1.5M Re-Use & Conserve Urban and Agricultural Conservation 250 2.0% $191K Crop Idling Transfers 800 6.3% $5.95M Treatment Casitas Reservoir Oxygenation Enhancement N/A N/A $5K Back-flushing of Meiners Oaks Wells 1 and 2 83 0.7% $20K CMWD Water Treatment Plant System Modifications Varies3. Varies3. $250K + $10K/y ear 1. Potential additional or saved volume of water. 2. Potential percentage of loss water volume mitigated. 3. Amount of volume mitigated depends on level of additional treatment implemented. 4. Water volume losses are estimated at 12,700 AF per storm event when diversion operations are suspended.
29 of 34
30 of 34
31 of 34
32 of 34
33 of 34
34 of 34