SLIDE 15 Project Schedule
Watauga Elementary School Additions // Birdville ISD // Schematic Design Presentation // August 27, 2015
DESIGN DEVELOPMENT PHASE JULY 24 – AUGUST 27, 2015 Present Design Development to Board of Trustees.…………………………………AUGUST 27, 2015 CONSTRUCTION DOCUMENTS PHASE AUGUST 28 – OCTOBER 26, 2015 100% Issue for Proposals .……………………………………………………………...OCTOBER 26, 2015 BIDDING PHASE OCTOBER 26 – DECEMBER 10, 2015 Receive Proposals ………………………………………………………………………NOVEMBER 24, 2015 Present Proposals to Board of Trustees ………………………………………….......DECEMBER 10, 2015 CONSTRUCTION PHASE JANUARY 4, 2016 – AUGUST 1, 2016 Substantial Completion Date ..………………………………………………..……...…AUGUST 1, 2016