D Avenue Improvement Project

E n g i n e e r i n g D e p t . N o v e m b e r 7 , 2 0 1 7

slide-2
SLIDE 2

Project Goals

  • Localized flooding
  • Stormwater treatment
  • Pedestrian

improvements

  • New road pavement
slide-3
SLIDE 3

Project Area

slide-4
SLIDE 4

Where we are at

  • 60% design plans
  • Comprehensive public
  • utreach to date
slide-5
SLIDE 5

What we’ve heard

slide-6
SLIDE 6

Meander = Slight Curves

slide-7
SLIDE 7

Cross Section Example

slide-8
SLIDE 8

Anticipated Schedule

  • 90% design

Late November 2017

  • Bid

Early January 2018

  • Contract award

February 2018

  • Construction

Spring 2018 – Fall 2018*

*landscaping/final paving could push to spring 2019

slide-9
SLIDE 9

Cost Estimate (60%) Anticipated construction cost = $4.2 million Total project cost = $5.3 million