(Cyanobacteria) Management Options for Halfmoon Lake, Alberta Al - - PowerPoint PPT Presentation

cyanobacteria management options
SMART_READER_LITE
LIVE PREVIEW

(Cyanobacteria) Management Options for Halfmoon Lake, Alberta Al - - PowerPoint PPT Presentation

An Evaluation of Bluegreen Algae (Cyanobacteria) Management Options for Halfmoon Lake, Alberta Al Sosiak, Sosiak Environmental Services Calgary, Alberta Overview of Talk Introduction Limnology 101: some lake management concepts


slide-1
SLIDE 1

Al Sosiak, Sosiak Environmental Services Calgary, Alberta

An Evaluation of Bluegreen Algae (Cyanobacteria) Management Options for Halfmoon Lake, Alberta

slide-2
SLIDE 2

Overview of Talk

 Introduction  Limnology 101: some lake management

concepts

 Suitability of Halfmoon Lake for in-lake

treatment

 Approach and results of evaluation: what

is feasible and what is impractical

 Preliminary costs, regulatory needs, and

what needs further study

 Implementation and conclusions

slide-3
SLIDE 3

Study Objectives

 Contracted to do the following:  Determine options to control

cyanobacterial blooms in Halfmoon Lake

 Summarize approximate cost of each

feasible option

 Identify the likelihood of impacts on non-

target aquatic species

 Determine regulatory requirements

slide-4
SLIDE 4

Some Limnology Concepts

Limnology=freshwater ecology

 Halfmoon has blooms of cyanobacteria

(sometimes called blue-green algae)

 Photosynthetic bacteria, not algae, no nuclear

membrane; like warm stable weather, hi [P]

 Found in nearly every terrestrial, freshwater,

marine habitat

Dolichospermum planktonica (formerly Anabaena)

Two dominant forms in Halfmoon, 1982, 1988

Aphanizomenon flos-aquae

slide-5
SLIDE 5

Human Impacts of Cyanobacteria

 Can produce unsightly blooms (above is

Microcystis in Pine Lake around 1990)

 Contact dermatitis (skin rash) from some forms

  • different from swimmer’s itch

 Another form (Nostoc) produces neurotoxic

amino acid BMAA – implicated in ALS

slide-6
SLIDE 6

Cyanobacteria can produce strong toxins

slide-7
SLIDE 7

Legacy Phosphorus

 All lakes are phosphorus (P) traps

 Lakes with history of sewage input, agricultural

impacts, etc, have large pool of P trapped in sediments (legacy P)

 Continues to circulate and cause blooms  Phosphorus most often limits phytoplankton in

temperate lakes

 Amount of phytoplankton - floating algae and

cyanobacteria - measured as chlorophyll a

 Halfmoon is mostly P-limited - P must be at very

low levels to limit cyanobacteria

slide-8
SLIDE 8

Legacy Phosphorus

 Legacy P can continue to impact lakes long

after external P greatly reduced

 Requires efforts to control or treat internal

P release – called inlake treatment

 Classic example is Lake Biwa, Japan

slide-9
SLIDE 9

Stratification and Oxygen Depletion

 Lakes tend to form stable layers over

summer - bottom waters become anoxic from decomposition in sediments

 Anoxia drives most sediment P release

Most years Halfmoon L. stratified from June to early September

slide-10
SLIDE 10

Any questions during talk?

 Please ask! This is a complex field with

lots of technical terms

slide-11
SLIDE 11

Halfmoon Lake is a Good Candidate for Inlake Treatment

 Few AB lakes are as well-suited  Small lake area (41 ha); chemical

treatments are possible

 Small watershed (2.43 km2), external

nutrient loadings small and already well managed

 Well buffered (can use chemicals affected

by pH

 Active motivated community

slide-12
SLIDE 12

Study Approach

 Based entirely on previous sampling and

studies

 Only able to obtain provincial monitoring

data (most U of Alberta data not available)

 First sorted all the available methods of

inlake treatment (e.g. see public document Wagner 2004)

 Serious evaluation of 25 methods; 5 other

methods totally impractical, as no practical case studies, or too disruptive

slide-13
SLIDE 13

Methods Not Recommended

 Of the 25 methods, three tried before on

Halfmoon and judged not successful

 Copper sulphate apparently used before 1982  Has toxic effects on non-target organisms,

accumulates sediments, resistance develops in some cyanobacteria

 Algicides do nothing to deplete legacy P  Aeration of bottom waters tried repeatedly for

fisheries enhancement, attempts failed (high sediment DO demand)

slide-14
SLIDE 14

Methods Not Recommended (Lime)

 Four experimental treatments of Halfmoon

with lime or powdered limestone by U of Alberta scientists in 1988, 1989, 1991, and 1993

 These scientists felt that multiple whole lake

treatments needed to obtain purported effects

 Provincial water quality data suggest effects

were short-term at best

slide-15
SLIDE 15

Methods Not Recommended (Lime)

 Total dissolved phosphorus (TDP) increased

after at least second application

 Prepas et al. (2001) stated that TP also

increased after the third and fourth applications

slide-16
SLIDE 16

Methods Not Recommended (Lime)

 Provincial data show that chlorophyll a

increased after the first two lime applications

 Prepas et al. (2001) also reported chlorophyll

increased after third and fourth applications

slide-17
SLIDE 17

Methods Not Recommended (Lime)

Cooke et al. (2005) say:

“more experimentation (with lime) is needed on questions of dose, application techniques, best seasons for treatment, chemical mechanisms, and treatment longevity”

slide-18
SLIDE 18

Methods Not Recommended

 Artificial mixing and bacterial additives have

been aggressively promoted throughout North America

 Have found no published evidence these

methods would meet the objectives at Halfmoon, but various accounts of failed applications

Artificial mixing: SolarBee deployment in Jordan L., NC Bacterial Additive

slide-19
SLIDE 19

Methods Not Recommended

 Some methods have provided benefits

elsewhere, but inappropriate for Halfmoon:

  • Iron salts: should only be used in well-aerated

lakes (sediments release P under anoxia)

  • Hypolimnetic withdrawal (used at Pine Lake):

too shallow and weak stratification, not enough inflow

  • Enhanced flushing: – no nearby source of low

nutrient water that is not already allocated

  • Evaluation of other methods in report
slide-20
SLIDE 20

Feasible Treatment Methods

 Four methods have worked elsewhere and

should work here

 Three involve P inactivation compounds

containing aluminum (Al) or lanthanum (La), and other is hydraulic dredging

 Main goal of the P inactivation

compounds is to inactivate P in surficial sediments, and prevent release to

  • verlying water

 Also strip P from the water column

slide-21
SLIDE 21

Feasible Treatment Methods – Option 1. Whole Lake Alum Application

 Longest use of any P inactivation agent (200

years in water treatment, over 250 applications world-wide)

 Same active ingredient as Maalox  Used for many years in water treatment in AB -

river discharge of effluent

 One recent application to a lake in northern AB

  • in 1990’s in combination with lime

 ~10 yr possible duration of effectiveness for

Halfmoon - longer in deeper stratified lakes (<42 yr; less in well-mixed lakes)

slide-22
SLIDE 22

Feasible Treatment Methods – Option 1. Whole Lake Alum Application

 Alum can form dissolved and toxic aluminate

above pH of 9

 pH should stay in range 6-8 (Cooke et al 2005)  Can avoid toxic form by slow addition of

compound deep in euphotic zone, use of buffering compounds

slide-23
SLIDE 23

Feasible Treatment Methods – Option 1. Whole Lake Alum Application

 Requires further sampling and analysis to

determine dosage (Dr. Harry Gibbons)

 Typically applied from a barge moving over the

target area

slide-24
SLIDE 24

Feasible Treatment Methods –

Option 2. Whole Lake Phoslock Application

 Phoslock is lanthanum-amended bentonite,

developed in Australia

 Extensive use in UK and Europe - in 2016 in

Henderson L, AB

 Pros: less pH sensitive, avoids public concerns

about aluminum

 Cons: Binds less rapidly than alum, can get

increased turbidity if dosage wrong, shorter period of use under narrower range of conditions

 Like alum, should be effective for ~10 yr.

slide-25
SLIDE 25

Feasible Treatment Methods –

Option 2. Whole Lake Phoslock Application

 Requires further sampling and analysis to

determine speed of binding at IDN lab in Germany

 Like alum typically applied from a barge moving

  • ver the target area (below Henderson L., AB,

application by Aquality)

slide-26
SLIDE 26

Feasible Treatment Methods –

Option 3. Microfloc Alum Injection

 Very low alum levels injected into lake bottom

waters

 Intercepts P released from sediments  Much lower costs, but ongoing process to suppress

blooms - costs add up over time

 Costs at Newman Lake, WA over many years

thought to be similar to cost of whole lake treatment, but spread out (B. Moore, Washington State U)

 Successful well-documented use at Newman L,WA  At least seven projects in the US

slide-27
SLIDE 27

Feasible Treatment Methods –

Option 3. Microfloc Alum Injection

 Below is peak post restoration phytoplankton

biovolumes in Newman Lake, in mm3m3

slide-28
SLIDE 28

Feasible Treatment Methods –

Option 3. Microfloc Alum Injection

Newman L system consists of:

 Storage tank on

shore in a spill containment berm

 Peristaltic pump

with valves

 Two distribution

lines

 Alum injectors on

an aeration system

slide-29
SLIDE 29

Feasible Treatment Methods –

Option 3. Microfloc Alum Injection

 Pros: costs spread out over many years; easier

for fundraising, injects deep in lake well away from hi pH induced by photosynthesis.

 Cons: requires permanent site for equipment,

lines in lake, ongoing maintenance and

  • peration (volunteer or paid time)

 Requires dosage determination and complete

system design for Halfmoon

 Costs should be much less than system for

12.6x larger Newman Lake

slide-30
SLIDE 30

Feasible Treatment Methods –

Option 4. Hydraulic Dredging

 Mobile cutterhead removes sediments in

target area, slurry piped to settling basin or treatment plant on shore

 Commonly used to remove sediment infilling,

rarely for control of blooms, but appropriate here because external P loading well controlled

slide-31
SLIDE 31

Feasible Treatment Methods –

Option 4. Hydraulic Dredging

 Used at Arbour Lake, Calgary; Lake

Trummen, Sweden

 Permanently removes the legacy P and

complete ecosystem rehabilitation

 Could create a valuable sport fishery by

deepening lake and removing decomposing material that strips oxygen from water

 Major disruption, aquatic organisms in

dredged material are affected

 Most expensive method and ~75% more if

centrifuges used to treat effluent.

slide-32
SLIDE 32

Option 4 – Hydraulic Dredging

 Requires deep core sediment sampling to

determine dredging depth to remove P and

  • xygen demand

 Also need a good TP budget to confirm previous

U of Alberta finding that external P is small

TP budget for Pine L, 1992

slide-33
SLIDE 33

Costs

 Approximate costs from applicators,

dredging firm, and suppliers

 For method assessment and fundraising

Feasible Methods Whole Lake Alum Single Treatment Whole Lake Phoslock Single Treatment Microfloc Alum Injection Hydraulic Dredging Approximate Cost Range $US325,000 to $525,000 depending on dosage (US applicator) $390,705 to $401,205 Cdn with Cdn applicator $US35,000 design and build; $US30,000 annual costs 12x larger Newman L. $700,000- $1,225,000 Cdn, settling basin northwest end of lake, 75% more for centrifuge treatment of effluent

slide-34
SLIDE 34

Regulatory Side

 All feasible methods require licenses and

permits from various levels of government (see report for details)

 Whole lake alum or Phoslock treatment will

require an AEPEA approval (see sample approval in Appendix III issued for Henderson Lake)

 Under Section 2.1 approval holders have to

promptly report any contraventions, do monitoring, submit annual reports for a specified number of years, for specified variables (bioassays, chemistry, etc)

slide-35
SLIDE 35

Regulatory Side

 Whole lake treatment alum or Phoslock

simplest, dredging most demanding in terms of regulatory requirements, and microfloc alum injection between the two

 Water management is a provincial

responsibility - federal involvement triggered if project affects migratory birds, endangered species, sport or commercial fish

 Only sticklebacks in Halfmoon Lake, no

sport fishery

slide-36
SLIDE 36

Phosphorus Loading from the Watershed

 Control of external P sources alone unlikely

to control cyanobacterial blooms (5 kg vs 147 kg from sediments in 1982)

 Some uncertainty about exact external P load

– should manage nutrients in shoreline areas:

 Phosphorus free lawn fertilizers and widely

available in Canada

Green lawn=green lake

slide-37
SLIDE 37

Phosphorus Loading from the Watershed

 Vegetated buffer strips (right below) and

grassy runoff channels remove suspended sediments and nutrients that would

  • therwise enter a lake

 For more on topic, see Wagner (2004)

Photos courtesy of Ken Wagner

slide-38
SLIDE 38

Phosphorus Loading from the Watershed

 Impervious surfaces such as pavement

near lakes allow runoff containing suspended sediments, nutrients, and other contaminants to enter a lake.

Low impact development tries to keep stormwater on sites

slide-39
SLIDE 39

Other Phosphorus Sources

 Large flocks of birds congregate some

years on Halfmoon Lake

 Residents remove woody debris from lake  P contribution of both sources should be

assessed using a detailed TP budget

slide-40
SLIDE 40

Implementation Model used at Pine Lake

 All stakeholders represented on an Advisory

Committee, then a registered society: Pine Lake Restoration Society

 Strong political involvement (MLA established

advisory committee) and county participation

 Strong local leadership (Bill Wearmouth)  Extensive provincial scientific support 1991-

1998, then post-project evaluation

 You will need scientific support – consultants

are expensive, but sometimes necessary

 Might want to get help from universities (grad

students), government, retired scientists?

slide-41
SLIDE 41

Implementation Objectives

 Stakeholders in this community need to

decide on objectives, what P levels are realistic, do you want a sport fishery?

 Best approach is to do this in consultation

with scientific/management staff

 Need to achieve very low dissolved P

levels to control cyanobacteria, a little bit is not good enough

 Sas et al. (1989) provide criterion of 10

µg/L soluble reactive phosphorus - well above this at Halfmoon

slide-42
SLIDE 42

Implementation Objectives

 Paleolimnology could help by

telling what lake was like before European settlement

 Uses lake sediment cores to

determine history of lake

 Timelines in sediments using

radioisotopes 210Pb, 14C, volcanic eruptions, other markers.

 Study changes in phytoplankton

and terrestrial community (pollen) using thin slices of sediment

slide-43
SLIDE 43

Implementation Objectives

 Determines what was natural

productivity - lakes resist attempts to make them better than they were historically

 Some lakes were naturally productive  Also shows impacts that human

activities in basin have had in past

 Various AB lakes (e.g. Pine Lake)

deteriorated in 70s with the increased use of agricultural fertilizers

slide-44
SLIDE 44

Implementation - Fundraising

 Funds available for well-thought out lake

and watershed projects with clear benefits, good science, and community involvement

 Different funding sources are available:

RBC Blue Water, Wild Rose Foundation (lottery money), Environment and Parks Grant (AEP)(requires “champion”)

 AB Conservation Association

  • license sale revenue

Pine Lake Restoration Society received $200,000 from Wild Rose Foundation for inlake treatment

slide-45
SLIDE 45

Implementation - Fundraising

 Community fund-raising for cost-shared

projects

Leisure Bike Tour at Pine Lake Raised $21,663 for the Restoration Program in 2000

slide-46
SLIDE 46

Concluding Remarks

 Any of these four inlake treatment

methods should work here

 Inlake treatment tends to be complex,

costly, and takes time to get it right

 Alum has the longest track record,

methods are well understood, but must control pH, Halfmoon is well-buffered and suitable for either alum or Phoslock

slide-47
SLIDE 47

Concluding Remarks

 Phoslock is less sensitive to pH, but

newer method and only one treatment in Alberta

 Preliminary costs to apply these two

chemicals to the whole lake are similar

 Microfloc alum injection uses far less

chemical but requires infrastructure, maintenance, and operation

 Hydraulic dredging could completely and

permanently renovate Halfmoon Lake and provide a potentially valuable fishery.

slide-48
SLIDE 48

Acknowledgements

I thank all technical and professional staff of Alberta

Environment and Parks (AEP) and Lakewatch (ALMS) who assisted in the sampling of Halfmoon Lake.

Dörte Köster (Hutchinson Environmental Sciences),

Harry Gibbons (Lake Advocates), John Holz (HAB Aquatic Solutions), Nigel Traill and Karin Finsterle (both Phoslock Water Solutions), Jay White (Aquality Environmental Consulting), and Matthew Peyton (CEDA) provided preliminary cost estimates for lake management services at Halfmoon Lake

Barry Moore (Washington State U.) provided

unpublished costs for the Newman Lake microfloc alum injection project.

slide-49
SLIDE 49

Al.Sosiak@telus.net

Lastly thanks to HMLRA! Questions?

Newman Lake, WA, location of microfloc alum injection system