cryogenics for large accelerators
play

Cryogenics for Large Accelerators Dr. Sergiy Putselyk Deutsches - PowerPoint PPT Presentation

Cryogenics for Large Accelerators Dr. Sergiy Putselyk Deutsches Elektronen-Synchrotron (DESY) MKS Division Notkestrasse 85 22607 Hamburg (Germany) Phone: +49 40 89983492 Fax: +49 40 89982858 E-Mail: Sergiy.Putselyk@desy.de 2 Outline:


  1. Cryogenics for Large Accelerators Dr. Sergiy Putselyk Deutsches Elektronen-Synchrotron (DESY) MKS Division Notkestrasse 85 22607 Hamburg (Germany) Phone: +49 40 89983492 Fax: +49 40 89982858 E-Mail: Sergiy.Putselyk@desy.de

  2. 2 Outline:  Present and Future 2K accelerators  Accelerator Module Test Facility (AMTF) Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  3. 3 Accelerators at 2K Accelerator Heat load Eq. Refriger. There is quite substantial number @ 2K Power @ 4.5K of accelerators working at 2K CEBAF 2*4.2kW 2*18 kW level! LHC 8*2.4kW 8*18 kW ≈ 2.4 kW ≈ 11 kW SNS The number of accelerators with ≈ 4 kW FRIB 18 kW sc cavities is growing! ≈ 2.4 kW ≈ 11 kW XFEL/DESY LCLS-II 2*4.6 kW 2*18 kW ≈ 3 kW ≈ 10 kW ESS The large cryogenic system & ILC 14-28(?) refrigerators are required! *2.4 kW ≈ 14 kW RHIC FAIR/GSI 6+18 kW (?) Note 1: for XFEL, it could be possible to cover 2K heat load with one 9kW@4.5K refrigerator (this will be cross-checked) Note 2: some refrigerators require also non- negligible 4.5K refrigeration load (e.g. FRIB, Cornell’s ERL) or 4.5K liquefaction l oad (e.g. SNS, FRIB, LCLS-II, ESS) Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  4. 4 Accelerators with s.c. cavities at 2K: cross- sectional view SNS, ESS LCLS-II CEBAF, C-100 CEBAF, old cryomodule Cornell ERL Beschleuniger-Palavers, GSI, 4 Feb. 2016 FLASH, XFEL, ILC Dr. S. Putselyk, DESY

  5. 5 Accelerators with s.c. magnets at 2 or 4K: cross-sectional view RHIC LHC SIS300 SIS100 Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  6. 6 Accelerators with s.c. cavities at 2 or 4K for heavy ions: cross-sectional view ISAC-II/ARIEL, FRIB, Michigan TRIUMF HIE-ISOLDE, CERN Rare Isotope Accelerator, Argonne Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  7. 7 XFEL-cryogenic system -overview Full design capacity requires operation of two 4.5K refrigerators in parallel. As a result of refrigerator commissioning, it seems to be feasible to operate XFEL with only one 4.5K refrigerator at slightly lower capacities. Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  8. 8 Simplified flow diagram of XFEL accelerator Up-graded HERA plant Simplified flow scheme 40K -> 80K shield circuit (in series) 5K -> 8K shield circuit (in series) 2K circuit (supply in parallel,return in series) warm gas collection pipe 40/80 K return, shield cooling 40/80 K return, shield cooling 40/80 K forward 40/80 K forward lead cooling 8 K return, shield cooling 8 K return, shield cooling 5 K forward 5 K forward JTHEX JTHEX 2.2 K forward 2.2 K forward 2 K return 2 K return module string 9-10 Injector 1 module string 2 module string 1 Injector 2 (not shown) Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  9. 9 Simplified flow diagram of cryomodule string Beschleuniger-Palavers, GSI, 4 Feb. 2016 Note: String connection box contains all cryogenic instrumentation Dr. S. Putselyk, DESY

  10. AMTF: purpose & objectives (TDR) 10 - Complete cold performance tests of all XFEL cryomodules before tunnel installation (RF measurements, vacuum check, cryo-losses) 103 cryomodules, rate: 1cryomodule/week - Cold RF tests of all XFEL superconducting cavities before cryomodule assembly 824 cavities, rate: 6 cavities/week - Cold tests of all superconducting magnet packages before cryomodule assembly 103 magnets, rate: 1magnet/week Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  11. AMTF Hall – Cavities and Cryomodules 11  Vertical Cryostat  Cavity preparation area  Radiation protection shielding  Unloading of the cryomodule  Cryomodule preparation area  XATB – module inside after transport radiation protection shielding Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  12. AMTF – cryogenics contributions 12 AMTF – cryogenics contributions Red = Wroclaw University Green= Budker Institute Blue = DESY MKS acting for of Technology+Kriosystem, of Nuclear Physics, XFEL company (no in-kind!) Poland (in-kind) Russia (in-kind) -> DeMaCo, Netherlands Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  13. Helium compressors (DESY in-kind) 13 Manufacturer: Oerlikon Leybold 2 sets of compressors for 2K operation at AMTF ( 2 x 20 g/s helium at 20 mbar) 1 set = 12 x parallel pump stations (WS 2001 RUVAC roots vacuum pump + SOGEVAC SV750B rotary vane vacuum pump) RUVAC – simple, modular, redundant SOGEVAC In average: about 8000 h operation (status June 2015) Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  14. AMTF Vertical Cryostats 14 SPEC DESY April 2009 Cavity Frame Design: Design & Construction DESY FLA WUT&Kriosystem 6 inserts for Delivery & installation: AMTF July 2012 – April 2013 A-A Ø ~Ø ~Ø Vacuum lid Vacuum flange Concrete floor Stainless steel ring 30mm thick ~ 3xM20 min. The lowest Concrete cylinder radiation shield 140mm thick Vacuum vessel Cold magnetic shield (MHF-sl) Cold magnetic Thermal shield shield (MKS1) Warm magnetic LHe vessel shields PVC pipe DN200 Space for heaters Ø max.Ø Ø ~ Support Soil Water drain pipe DN100 Concrete (PVC or stainless steel) Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  15. AMTF:3 cryomodule test stands & cryostat adapters 15 Spec DESY (February 2010) Design, Construction, Installation: BINP First test stand delivered & installed May 2013 (cold commissioning July 2013) Cold commissioning of 3rd test stand December 2013 2 cryostat adapters for the test of single dressed cavities at AMTF Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  16. XASB, XAVB, XAST 16 Wessington DESY is acting for XFEL company Cryogenics Ltd, UK Manufacturer: DeMaCO Sub-Cooler Box XASB Valve Box XAVB L Helium Dewar XAST Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  17. Cryogenic operation of AMTF 17  Supplied by HERA helium Cool down and Warm up refrigerator. XATC1, XATC2  33 g/s of LHe and cooling  Manual pump and purge capacities of about 3 kW at 40/80K, 0.5  kW at 4.5K. Cool-down to 4K, liquid helium transfer and warm-up in automatic  Modular structure - independent mode operation of test stands from each  Manual pump-down to 2K other.  Buffering of extra liquefaction in 10000 ltr liquid helium storage dewar XATB1, XATB2, XATB3 (XAST).  Manual pump and purge  Missing of air condensation on  Mainly automatically warm-up, cryogenic valves during exchange of  Cool-down partially in automatic modules or cavities. mode  Capacity limits – return gas peak, screw compressor capacity during cool down/warm-up, 2 dynamic procedures in parallel. Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  18. Summary of preliminary results (status Feb. 2016) 18 All superconducting magnets are tested! Leakage of some In total, >1200 Cavity modules tests were performed on vertical cryostats. Commissioning of Specified test rate of two other test accelerator modules benches is reached ! Total heat load (static+dynamic) in line with budget. Testing rate is Near all results above XFEL specification: slightly reduced due  accelerating gradient 23.6 MV/m to lower cryomodule  cavity quality factor Q 0 =10 10 at 23.6 MV/m delivery rate Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  19. Some preliminary conclusions 19  Deliveries & installation of XATCs,XASB,XAVB,XATL were “just -in- time“ for start-up of cavity production  Deliveries & installation of XATBs were “just -in- time“ for start-up of cryomodule production  No dedicated debugging of cryo-supply and other systems  XATCs design capacities demonstrated  Complexity of XATBs commissioning underestimated  General effort for installation & commissioning underestimated  1 cryomodule test/week is reached (further ramping-up rate is under investigation)  So far: in budget and almost “in time“ (not “on schedule “) Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

  20. 20 Thank you for your attention ! Beschleuniger-Palavers, GSI, 4 Feb. 2016 Dr. S. Putselyk, DESY

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend