Critical bottleneck for the survival of VSPPs in Thailand by - - PowerPoint PPT Presentation

critical bottleneck for the survival of vspps in thailand
SMART_READER_LITE
LIVE PREVIEW

Critical bottleneck for the survival of VSPPs in Thailand by - - PowerPoint PPT Presentation

Technical constraints on Biomass gasification: Critical bottleneck for the survival of VSPPs in Thailand by Wirachai Soontornrangson, PhD. Thailand Institute of Scientific and Technological Research (TISTR) for Regional Workshop on Overcoming


slide-1
SLIDE 1

Technical constraints on Biomass gasification: Critical bottleneck for the survival of VSPPs in Thailand

Regional Workshop on Overcoming Critical Bottlenecks to Accelerate Renewable Energy Deployment in ASEAN+6 Countries

Rama Gardens Hotel, Bangkok, Thailand 14 June 2016

by

Wirachai Soontornrangson, PhD. Thailand Institute of Scientific and Technological Research (TISTR)

for

slide-2
SLIDE 2

Presentation outline

  • Backgrounds
  • Abbreviations
  • Technical Review
  • Status of VSPPs using biomass gasification

technology in Thailand

  • Technical constraints on biomass gasification

for power generation purpose

  • Conclusions

2

slide-3
SLIDE 3

Backgrounds

  • Intensive campaign for encouraging and supporting small private

power producers (<1 - <10 MW) in Thailand has been launched since the early 1990s

  • Biomass gasification combined with gas engine generator was

introduced and recommended as the most suitable technology for power plant with <1 - <10 MW installed capacity, i.e. VSPP

  • Biomass gasification power plants in Thailand more likely to close

down after 3 years due to problems caused by gasification process*

  • Biomass gasification power plant with <1 MW installed capacity would

not be viable economically**

*ASIAN Institute of Technology, (2003) **Energy for Environment Foundation, (2012)

3

slide-4
SLIDE 4

Abbreviations

VSPP = Very Small Power Producer = Renewable energy power plant with <1 - <10 MW installed capacity EGAT = Electricity Generation Authority of Thailand = National power producer/provider MEA = Metropolitan Electricity Authority = Power provider for Bangkok and vicinity PEA = Provincial Electricity Authority = Power provider for areas beyond Bangkok and vicinity

4

slide-5
SLIDE 5

Technical Review

Process mechanism

Gasification process

  • Operating Temperature 500 – 1,200 o C
  • Inlet air 1/3 of that required for complete combustion (Partial oxidation)
  • Combinations of Exothermic and Endothermic reactions

Factors affecting process performance

  • Reactor’s physical figure
  • Operating temperature, i.e. higher is better
  • Size (1.5 – 2 inch) and moisture content (< 20%) of feedstock

Products

  • Gas: Synthetic gas (CO, H2, CH4), CO2, NO2 and H2O
  • Vapor: heavy hydrocarbons (Condensable), light hydrocarbons

(Incondensable)

  • Solid: char, ash

5

slide-6
SLIDE 6

Source: http://aboriginalankur.com/author/admin/

Typical Biomass gasification VSPP in Thailand

6

slide-7
SLIDE 7

Gasifiers used by VSPPs

Fixed bed gasifier

Updraft gasifier Downdraft gasifier

Source: Thomas B. Reed and Agua Das, 1988

7

slide-8
SLIDE 8

Status of VSPPs using biomass gasification technology in Thailand

COD* committed 14 plants Under construction 16 plants

8

Total license granted VSPPs 30 plants

(1991 - 2003) * Commercial operation date

slide-9
SLIDE 9

Status of VSPPs using biomass gasification technology in Thailand

(Continued)

9

Total COD* committed VSPPs 14 plants

(1991 - 2000) * Commercial operation date

Regularly supply electricity to MEA/PEA 5 plants Temporarily suspended 6 plants Closing down 3 plants

slide-10
SLIDE 10

10

What prevents biomass gasification VSPPs in Thailand from being viable economically?

slide-11
SLIDE 11

11

TISTR’s Study team Sponsored by TRF-EGAT** “Status of Biomass Gasification for either Heat or Power generation via Industry Community and SMEs* scale in Thailand”

* Small and Medium Enterprises ** Thailand Research Fund – Electricity Generation Authority of Thailand

slide-12
SLIDE 12

Field surveys on 10 VSPPs (Sep 2014 – Jun 2015)

12

slide-13
SLIDE 13

Technical constraints on biomass gasification for power generation purpose

  • 1. Low efficiency
  • 2. Limited continuous operation duration
  • 3. Sensitive to feedstock’s size and moisture content
  • 4. Produced large amounts of by-products/wastes

13

slide-14
SLIDE 14

14

Constraint 1: Low efficiency

Causes:

  • Design of gasifier
  • User’s application

Impacts:

  • Low operating temperature
  • Low quantity and quality, i.e. high tar contamination,

gas produced

  • Inefficient feedstock consumption
slide-15
SLIDE 15

15

Constraint 2: Limited continuous operation duration

Average operation duration 2,800 - 3,500 hours/year

Causes:

Frequent unscheduled shutdowns due to accumulation of tar in plumbing, accessories and/or engine’s parts

Impacts:

  • Losing Income due to less electricity produced
  • Increasing operating cost, i.e. for unscheduled maintenances

and/or premature spare parts replacements

slide-16
SLIDE 16

16

Constraint 3: Sensitive to feedstock’s size and moisture content

Causes :

  • Large numbers of big voids in pile/column of feedstock, i.e. oversized feedstock
  • Compact pile/column of feedstock with small number of tiny voids,

i.e. undersized feedstock

  • Damped pile/column of feedstock, i.e. > 20% MC

Impacts :

  • Non-uniform zonal temperature
  • Obstructing inlet/outlet gases flow, increasing waste char
  • Extended start-up time and lower operating temperature
slide-17
SLIDE 17

Wastewater (4-6 m3/MW/day)

17

(4 tons/MW/Day) Bottom ash/char Tar (400-700 liters/MW/Day)

Constraint 4: Produced large amounts of by-products/wastes

slide-18
SLIDE 18

18

Constraint 4: Produced large amounts of by-products/wastes

Causes : Impacts :

Typical characteristic of fixed bed gasifiers

  • Increasing investment, i.e. sufficient appropriate waste treatment

system

  • Increasing external cost, i.e. Financial compensation to human

health and ecosystem deterioration and Corporate Social Responsibility (CSR) activities

  • Risk of losing income, i.e. being shut down by public/community
  • pposition due to environmental issues
slide-19
SLIDE 19

Conclusions

19

Technical constraints on biomass gasification considered as a critical bottleneck for the survival of VSPPs due to following issues:

Increasing (unplanned) investment Increasing operating costs Increasing external costs Losing incomes

64% of COD committed VSPPs were left idle because of either closing down due to accumulated deficit or suspended because it was too costly to operate

slide-20
SLIDE 20

20

Acknowledgement

Thanks : The Thailand Research Fund (TRF) Electricity Generation Authority of Thailand (EGAT) Metropolitan Electricity Authority (MEA) Provincial Electricity Authority (PEA) All VSPPs those participated this study

slide-21
SLIDE 21

Thailand Institute of Scientific and Technological Research (TISTR) 35 Mu 3 Khlong Ha, Khlong Luang, Pathum Thani 12120 http://www.tistr.or.th

Thank you