COSGRAY ROAD E XT E NSI ON City o f Hillia rd Ohio De pa rtme nt o f T ra nspo rta tio n F RA-COSGRAY ROAD, PI D 90989 Aug ust 12, 2014 EXISTING CONDITIONS Lack of north south connectivity Long queues at intersections today


  1. COSGRAY ROAD E XT E NSI ON City o f Hillia rd Ohio De pa rtme nt o f T ra nspo rta tio n F RA-COSGRAY ROAD, PI D 90989 Aug ust 12, 2014

  2. EXISTING CONDITIONS • Lack of north ‐ south connectivity • Long queues at intersections today Contributes to rear ‐ end collisions • • Congestion predicted to worsen • Lack of bicycle/pedestrian facilities

  3. PROJECT PURPOSE • Improve north ‐ south connectivity • Reduce congestion • Improve safety • Enhance alternative travel modes

  4. ZONING • Includes Jerman Tract • Retail, office, and recreational land uses • Zoning approved in 2010 by City and Big Darby Accord

  5. ZONING 2008/2010: • Includes Jerman Tract Willoway Wholesale/MJC Holdings LLC • Retail, office, and (Campus at Alton Darby) recreational land uses • Zoning approved in 2010 by City and Big Darby Accord 2013: Planned Development Company of Ohio (Heritage Preserve)

  6. • Project focuses on transportation network • Considers stormwater & future development • Project will not focus on zoning &/or land uses

  7. RECOMMENDED ALTERNATIVE “Green” median with • bioswales Multi ‐ use paths on both sides • and on ‐ street bike accommodations Enhanced pedestrian crossing • for regional bike trail Roundabout with access to • public soccer fields & Jerman site Roundabout at Alton & Darby • Creek Road intersection 35 ‐ mph speed limit •

  8. COSGRAY ROAD EXTENSION TYPICAL ROADWAY ELEVATION VIEW

  9. • Roundabout at Soccer Field/Main Site Drive Intersection • Allows for safe bike/ped crossing of Cosgray Extension • Maximizes median/bioswale length • Slower speeds (20 ‐ 25 mph design speed)

  10. • Roundabout at Alton & Darby Creek intersection • Slower speeds (20 ‐ 25 mph design speed) • Traditional (4 ‐ leg) intersection on curve not desirable

  11. PEDESTRIANS & BICYCLES Multi ‐ use path • Future regional trail • connection On ‐ street bicycle facilities • Split median pedestrian • crossings Future extensions to Municipal • Park & Prairie Oaks Metro Park

  12. TYPICAL SPLIT MEDIAN CROSSING ELEVATION VIEW

  13. Cosgray Road Extension Will Exceed Stormwater Requirements 79 Runoff Storage Volume (acre ‐ feet) COSGRAY ROAD EXTENSION PROJECT 34 28 City of Hilliard Big Darby Creek Zero Runoff in 2 ‐ Year Watershed Rain Storm

  14. NEXT STEPS • 2014/2015: Finish environmental studies & preliminary design • 2015/2016: Final Design • 2016: Right ‐ of ‐ Way Acquisition • 2017: Construction *All dates are subject to funding availability.

  15. PUBLIC COMMENTS • Comments must be received by August 26, 2014 • Comments can be provided: • Comment form (dropped off at meeting or mailed) • Email: lschamp@hilliardohio.gov • Project website: www.hilliardohio.gov/

  16. QUESTIONS

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.