Stakeholder’s Forum September 3, 2014
Stakeholders Forum September 3, 2014 Maryland Energy Administration - - PowerPoint PPT Presentation
Stakeholders Forum September 3, 2014 Maryland Energy Administration - - PowerPoint PPT Presentation
Stakeholders Forum September 3, 2014 Maryland Energy Administration September 3, 2014 Maryland Offshore Wind Energy Stakeholders Forum Agenda 12:30 1:00 Box Lunch and Introductions 1:00 1:30 Project Background and Objectives Project
Maryland Energy Administration September 3, 2014
Maryland Offshore Wind Energy Stakeholders Forum
Agenda
12:30 – 1:00 Box Lunch and Introductions 1:00 – 1:30 Project Background and Objectives ‐ Project scope ‐ Introduction to the MD OSWE site ‐ OSWE staging port activities 1:30 – 2:30 Project Findings ‐ Turbine installation sequence in MD ‐ Turbine staging port requirements ‐ Foundation construction requirements ‐ Candidate port sites 2:30 – 4:00 Moderated Open Discussion ‐ Port options and opportunities ‐ Stakeholder input and recommendations ‐ Selected action items and additional findings ‐ Final Q&A 4:00 – 5:00 Networking and Refreshments
Maryland Energy Administration September 3, 2014
PROJECT SCOPE
Objectives:
- Identify Baltimore Harbor sites
- Solicit expressions of interest
Tasks:
- Definition of Needs and Port
Criteria
- Inventory of Existing Terminal
Assets
- Facility Plan Concepts
- Terminal Operators Forum
Products:
- Criteria and assumptions
- A Base‐Case facility study
- Survey of selected Maryland sites
- Request for Expressions of
Interest
Maryland Energy Administration September 3, 2014
Maryland Offshore Wind Energy Site
Ocean City Maryland Offshore Wind Energy Site 10 Miles
Maryland Energy Administration September 3, 2014
Navigation Issues
Chesapeake and Delaware Canal Route
- Vertical: 130 ft. at MHW
- Horizontal: 450 ft.
- Depth: 30 ft. at MLLW
- Distance: 150 miles
Chesapeake Channel Route
- Vertical: 182 ft. at MHW
- Horizontal: 1,100 ft.
- Depth: 50 ft. at MLLW
- Distance: 290 miles
Maryland Energy Administration September 3, 2014
Staging Port Activities
Wind Turbine Generator Import
Import turbine components Buffer import against installation
Wind Turbine Generator Installation
Pre‐installation assembly and prep Loading installation or delivery vessel
Support Structure and Foundation Fabrication
Import of foundation materials Foundation fabrication Loading foundation delivery vessels
Maryland Energy Administration September 3, 2014
Wind Turbine Import Sequence
Turbine components manufactured overseas
Nacelle (generator, yaw drives, controller, and housing) Rotor (hub, blades) Tower (2 to 3 sections,)
Import by heavy‐lift geared ship
Ship cranes handle minimum 350 ton loads Wharf to storage by SPMT
SPMT transport to storage and prep area
Store on specialized ‘mafi’ units, or Heavy‐lift crane unloads to ground
Maryland Energy Administration September 3, 2014
Import Vessels and Equipment
Heavy‐Lift Geared Ship
- Length: 452 ft.
- Beam: 75 ft.
- Laden Draft: 31 ft.
- DWT Capacity 15,000 tonnes
- Cranes: 2X 400 tonnes
(combinable to 800 tonnes) Self Propelled Modular Transporter (SPMT)
- Capacity: 25 tonnes/axle unit
- Vertical adjustment: 2 ft.
- Speed: 3 miles/hr (264 ft./min)
Maryland Energy Administration September 3, 2014
Wind Turbine Storage and Prep
Nacelles adjacent to heavy‐lift crane
Require minimum of assembly/prep Moved and stored on “Transport Frame”
Rotors partially or fully assembled on‐site
Requires large working area for assembly Assembled rotor are transported wharf‐side for loading
- n delivery vessel
Towers stored horizontally or vertically
Tower segments usually stored horizontally Staged vertically for loading on delivery vessel
Maryland Energy Administration September 3, 2014
Heavy‐Lift Crane
Liebherr SLDB 11350
- Maximum rated load: 1,350 tonnes
- Boom length: 334 feet (102 m)
- Assumed maximum lift: 300 tonnes
- Maximum reach at 300 tonnes: 170 feet
- 400 tonne moveable counterweight
- Approximate max concentrated load:
2o,000 psf
Maryland Energy Administration September 3, 2014
Wind Turbine Loading and Delivery
Jack‐up Delivery Barge
Capacity for three complete units (nacelle, rotor, tower) Four to six legs Lift 20 feet clear in 120 feet of water Jones Act compliant per Maryland OREC regulations
Turbine components loaded by heavy‐lift crane
Crane “walks” 300 tonne nacelle from storage to wharf Crane lifts and swings assembled rotors to clear legs Crane lifts tower segments upright and loads on barge
Tug and barge delivery to OSWE construction site
Use Chesapeake Channel outbound, may use Chesapeake and
Delaware Canal on return
Possibly two to three barges in rotation
Maryland Energy Administration September 3, 2014
Delivery Barge
80 Feet 200 Feet
Maryland Energy Administration September 3, 2014
Foundation Units
70 Feet 30 Feet
Transition Piece Attachment Embedment
85 Feet± 155 Feet
Immersion
85 Feet
Monopile and Transition Piece Jacket
200 Feet
Maryland Energy Administration September 3, 2014
Foundation Transportation and Installation
Maryland Energy Administration September 3, 2014
Foundation Transportation and Installation
Maryland Energy Administration September 3, 2014
Break Questions ‐ Discussions
Maryland Energy Administration September 3, 2014
Maryland OSW “Design Turbine”
Wind Turbine Generator: Siemens SWT 6.0
6 Mega‐Watt, direct drive generator 300 Tonne nacelle weight
Hub and Rotor Assembly: Siemens 154 meter
245 Foot blade length 50 Tonne assembled weight
Tower: Siemens manufactured
232 Feet high (hub height: 312 feet) Shipped in two sections of 116 feet 160 Tonnes estimated total weight
Maryland Energy Administration September 3, 2014
Design Turbine Nacelle
50 Feet 21 Feet
Maryland Energy Administration September 3, 2014
Design Rotor
370 Feet 438 Feet
Maryland Energy Administration September 3, 2014
Design Tower
70 Feet 116 Feet 116 Feet 312 Feet
Maryland Energy Administration September 3, 2014
Design Vessels
Ocean‐Going Import Vessels
Handy size – 400 ft. to 600 ft. Draft 30 ft. to 35 ft. Geared heavy lift
Turbine Delivery Vessels
Jack‐up barge – 200 ft. to 400 ft. Draft 9 ft. to 18 ft.
Foundation Delivery Vessels
Does not require jack‐up capability May deliver foundations from outside of region
Turbine and Foundation Installation Vessels
Jack‐up vessel 300 ft. to 500 ft. Draft 20 ft. plus leg clearance Remains on‐station at the MD OSWE Site
DRAFT
Maryland Energy Administration September 3, 2014
Loaded Turbine Delivery Barge
Three “Kits”
Three 6 mega‐Watt nacelles Three fully assembled rotors Six tower segments Ability to jack‐up with 1,500
tonnes on deck
Maryland Energy Administration September 3, 2014
Wharf Configuration
65 ft. wide Crane Runway 100 ft. X 100 ft. Crane Pad 100 ft. X 800 ft. High Capacity Wharf 450 ft. Turbine Import Vessel Liebherr 11350 Heavy Lift Crane 200 ft. Jackup Delivery Barge 300 tonnes at 65 foot radius 300 tonnes at 170 feet
Maryland Energy Administration September 3, 2014
Wind Turbine Staging Port Layout
800 Feet 2,000 Feet
24 Kits in storage One kit ready to load 37 Acres upland
Maryland Energy Administration September 3, 2014
Foundation Port Layout
600 Feet 1,600 Feet 22 Acres±
Maryland Energy Administration September 3, 2014
Port Requirements*: Turbines
Weight Min (tons) Weight Max (tons) Unit Load (psf) Unit Storage Area (sqft) Notes: Tower 80 165 2,000 1,000 Imported and stored horizontally, delivered vertically in sections Nacelle 180 375 4,000 2,000 Roughly 25 ft X 50 ft stored on support platform Blades 15 25 1,800 3,000 200 to 250 feet long stored horizontally Hub 20 35 1,800 400 6 meter diameter stored on blocks Rotor Assembly 40 110 1,800 na Assembled quay‐side and loaded on installation vessel
*DRAFT – Note: all numbers are approximate and subject to verification
Maryland Energy Administration September 3, 2014
Port Requirements*: Foundations
Weight Min (tons) Weight Max (tons) Unit Load (psf) Unit Storage Area (sqft) Notes: Monopile 350 550 4,000 7,500 Unit load can be lower depending on storage mode Transition Piece 300 350 2,000 1,000 Assembled and stored vertically Jacket 500 1,200 3,000 11,000 Assembled and stored vertically, delivered horizontally or vertically
*DRAFT – Note: all numbers are approximate and subject to verification
Maryland Energy Administration September 3, 2014
Candidate Ports
Rukert Terminal AmPorts/MAPC Sparrows Point Shipyard Sparrows Point Kinder Morgan Cianbro
DRAFT
Maryland Energy Administration September 3, 2014