Stakeholders Forum September 3, 2014 Maryland Energy Administration - - PowerPoint PPT Presentation

stakeholder s forum september 3 2014
SMART_READER_LITE
LIVE PREVIEW

Stakeholders Forum September 3, 2014 Maryland Energy Administration - - PowerPoint PPT Presentation

Stakeholders Forum September 3, 2014 Maryland Energy Administration September 3, 2014 Maryland Offshore Wind Energy Stakeholders Forum Agenda 12:30 1:00 Box Lunch and Introductions 1:00 1:30 Project Background and Objectives Project


slide-1
SLIDE 1

Stakeholder’s Forum September 3, 2014

slide-2
SLIDE 2

Maryland Energy Administration September 3, 2014

Maryland Offshore Wind Energy Stakeholders Forum

Agenda

12:30 – 1:00 Box Lunch and Introductions 1:00 – 1:30 Project Background and Objectives ‐ Project scope ‐ Introduction to the MD OSWE site ‐ OSWE staging port activities 1:30 – 2:30 Project Findings ‐ Turbine installation sequence in MD ‐ Turbine staging port requirements ‐ Foundation construction requirements ‐ Candidate port sites 2:30 – 4:00 Moderated Open Discussion ‐ Port options and opportunities ‐ Stakeholder input and recommendations ‐ Selected action items and additional findings ‐ Final Q&A 4:00 – 5:00 Networking and Refreshments

slide-3
SLIDE 3

Maryland Energy Administration September 3, 2014

PROJECT SCOPE

Objectives:

  • Identify Baltimore Harbor sites
  • Solicit expressions of interest

Tasks:

  • Definition of Needs and Port

Criteria

  • Inventory of Existing Terminal

Assets

  • Facility Plan Concepts
  • Terminal Operators Forum

Products:

  • Criteria and assumptions
  • A Base‐Case facility study
  • Survey of selected Maryland sites
  • Request for Expressions of

Interest

slide-4
SLIDE 4

Maryland Energy Administration September 3, 2014

Maryland Offshore Wind Energy Site

Ocean City Maryland Offshore Wind Energy Site 10 Miles

slide-5
SLIDE 5

Maryland Energy Administration September 3, 2014

Navigation Issues

Chesapeake and Delaware Canal Route

  • Vertical: 130 ft. at MHW
  • Horizontal: 450 ft.
  • Depth: 30 ft. at MLLW
  • Distance: 150 miles

Chesapeake Channel Route

  • Vertical: 182 ft. at MHW
  • Horizontal: 1,100 ft.
  • Depth: 50 ft. at MLLW
  • Distance: 290 miles
slide-6
SLIDE 6

Maryland Energy Administration September 3, 2014

Staging Port Activities

 Wind Turbine Generator Import

 Import turbine components  Buffer import against installation

 Wind Turbine Generator Installation

 Pre‐installation assembly and prep  Loading installation or delivery vessel

 Support Structure and Foundation Fabrication

 Import of foundation materials  Foundation fabrication  Loading foundation delivery vessels

slide-7
SLIDE 7

Maryland Energy Administration September 3, 2014

Wind Turbine Import Sequence

 Turbine components manufactured overseas

 Nacelle (generator, yaw drives, controller, and housing)  Rotor (hub, blades)  Tower (2 to 3 sections,)

 Import by heavy‐lift geared ship

 Ship cranes handle minimum 350 ton loads  Wharf to storage by SPMT

 SPMT transport to storage and prep area

 Store on specialized ‘mafi’ units, or  Heavy‐lift crane unloads to ground

slide-8
SLIDE 8

Maryland Energy Administration September 3, 2014

Import Vessels and Equipment

Heavy‐Lift Geared Ship

  • Length: 452 ft.
  • Beam: 75 ft.
  • Laden Draft: 31 ft.
  • DWT Capacity 15,000 tonnes
  • Cranes: 2X 400 tonnes

(combinable to 800 tonnes) Self Propelled Modular Transporter (SPMT)

  • Capacity: 25 tonnes/axle unit
  • Vertical adjustment: 2 ft.
  • Speed: 3 miles/hr (264 ft./min)
slide-9
SLIDE 9

Maryland Energy Administration September 3, 2014

Wind Turbine Storage and Prep

 Nacelles adjacent to heavy‐lift crane

 Require minimum of assembly/prep  Moved and stored on “Transport Frame”

 Rotors partially or fully assembled on‐site

 Requires large working area for assembly  Assembled rotor are transported wharf‐side for loading

  • n delivery vessel

 Towers stored horizontally or vertically

 Tower segments usually stored horizontally  Staged vertically for loading on delivery vessel

slide-10
SLIDE 10

Maryland Energy Administration September 3, 2014

Heavy‐Lift Crane

Liebherr SLDB 11350

  • Maximum rated load: 1,350 tonnes
  • Boom length: 334 feet (102 m)
  • Assumed maximum lift: 300 tonnes
  • Maximum reach at 300 tonnes: 170 feet
  • 400 tonne moveable counterweight
  • Approximate max concentrated load:

2o,000 psf

slide-11
SLIDE 11

Maryland Energy Administration September 3, 2014

Wind Turbine Loading and Delivery

 Jack‐up Delivery Barge

 Capacity for three complete units (nacelle, rotor, tower)  Four to six legs  Lift 20 feet clear in 120 feet of water  Jones Act compliant per Maryland OREC regulations

 Turbine components loaded by heavy‐lift crane

 Crane “walks” 300 tonne nacelle from storage to wharf  Crane lifts and swings assembled rotors to clear legs  Crane lifts tower segments upright and loads on barge

 Tug and barge delivery to OSWE construction site

 Use Chesapeake Channel outbound, may use Chesapeake and

Delaware Canal on return

 Possibly two to three barges in rotation

slide-12
SLIDE 12

Maryland Energy Administration September 3, 2014

Delivery Barge

80 Feet 200 Feet

slide-13
SLIDE 13

Maryland Energy Administration September 3, 2014

Foundation Units

70 Feet 30 Feet

Transition Piece Attachment Embedment

85 Feet± 155 Feet

Immersion

85 Feet

Monopile and Transition Piece Jacket

200 Feet

slide-14
SLIDE 14

Maryland Energy Administration September 3, 2014

Foundation Transportation and Installation

slide-15
SLIDE 15

Maryland Energy Administration September 3, 2014

Foundation Transportation and Installation

slide-16
SLIDE 16

Maryland Energy Administration September 3, 2014

Break Questions ‐ Discussions

slide-17
SLIDE 17

Maryland Energy Administration September 3, 2014

Maryland OSW “Design Turbine”

 Wind Turbine Generator: Siemens SWT 6.0

 6 Mega‐Watt, direct drive generator  300 Tonne nacelle weight

 Hub and Rotor Assembly: Siemens 154 meter

 245 Foot blade length  50 Tonne assembled weight

 Tower: Siemens manufactured

 232 Feet high (hub height: 312 feet)  Shipped in two sections of 116 feet  160 Tonnes estimated total weight

slide-18
SLIDE 18

Maryland Energy Administration September 3, 2014

Design Turbine Nacelle

50 Feet 21 Feet

slide-19
SLIDE 19

Maryland Energy Administration September 3, 2014

Design Rotor

370 Feet 438 Feet

slide-20
SLIDE 20

Maryland Energy Administration September 3, 2014

Design Tower

70 Feet 116 Feet 116 Feet 312 Feet

slide-21
SLIDE 21

Maryland Energy Administration September 3, 2014

Design Vessels

 Ocean‐Going Import Vessels

 Handy size – 400 ft. to 600 ft.  Draft 30 ft. to 35 ft.  Geared heavy lift

 Turbine Delivery Vessels

 Jack‐up barge – 200 ft. to 400 ft.  Draft 9 ft. to 18 ft.

 Foundation Delivery Vessels

 Does not require jack‐up capability  May deliver foundations from outside of region

 Turbine and Foundation Installation Vessels

 Jack‐up vessel 300 ft. to 500 ft.  Draft 20 ft. plus leg clearance  Remains on‐station at the MD OSWE Site

DRAFT

slide-22
SLIDE 22

Maryland Energy Administration September 3, 2014

Loaded Turbine Delivery Barge

 Three “Kits”

 Three 6 mega‐Watt nacelles  Three fully assembled rotors  Six tower segments  Ability to jack‐up with 1,500

tonnes on deck

slide-23
SLIDE 23

Maryland Energy Administration September 3, 2014

Wharf Configuration

65 ft. wide Crane Runway 100 ft. X 100 ft. Crane Pad 100 ft. X 800 ft. High Capacity Wharf 450 ft. Turbine Import Vessel Liebherr 11350 Heavy Lift Crane 200 ft. Jackup Delivery Barge 300 tonnes at 65 foot radius 300 tonnes at 170 feet

slide-24
SLIDE 24

Maryland Energy Administration September 3, 2014

Wind Turbine Staging Port Layout

800 Feet 2,000 Feet

 24 Kits in storage  One kit ready to load  37 Acres upland

slide-25
SLIDE 25

Maryland Energy Administration September 3, 2014

Foundation Port Layout

600 Feet 1,600 Feet 22 Acres±

slide-26
SLIDE 26

Maryland Energy Administration September 3, 2014

Port Requirements*: Turbines

Weight Min (tons) Weight Max (tons) Unit Load (psf) Unit Storage Area (sqft) Notes: Tower 80 165 2,000 1,000 Imported and stored horizontally, delivered vertically in sections Nacelle 180 375 4,000 2,000 Roughly 25 ft X 50 ft stored on support platform Blades 15 25 1,800 3,000 200 to 250 feet long stored horizontally Hub 20 35 1,800 400 6 meter diameter stored on blocks Rotor Assembly 40 110 1,800 na Assembled quay‐side and loaded on installation vessel

*DRAFT – Note: all numbers are approximate and subject to verification

slide-27
SLIDE 27

Maryland Energy Administration September 3, 2014

Port Requirements*: Foundations

Weight Min (tons) Weight Max (tons) Unit Load (psf) Unit Storage Area (sqft) Notes: Monopile 350 550 4,000 7,500 Unit load can be lower depending on storage mode Transition Piece 300 350 2,000 1,000 Assembled and stored vertically Jacket 500 1,200 3,000 11,000 Assembled and stored vertically, delivered horizontally or vertically

*DRAFT – Note: all numbers are approximate and subject to verification

slide-28
SLIDE 28

Maryland Energy Administration September 3, 2014

Candidate Ports

Rukert Terminal AmPorts/MAPC Sparrows Point Shipyard Sparrows Point Kinder Morgan Cianbro

DRAFT

slide-29
SLIDE 29

Maryland Energy Administration September 3, 2014

END Questions ‐ Discussions