Contra Costa Community College District Project and Construction - PowerPoint PPT Presentation

Contra Costa Community College District Project and Construction Management RFQ Non-Mandatory Pre-Proposal Conference 7/26/19 1 Agenda Capital Improvement Bond Program Overview o Introductions o Sustainability Goals o Major Active Projects


  1. Contra Costa Community College District Project and Construction Management RFQ Non-Mandatory Pre-Proposal Conference 7/26/19 1

  2. Agenda  Capital Improvement Bond Program Overview o Introductions o Sustainability Goals o Major Active Projects  Request for Qualifications Overview  Q & A 2

  3. Welcome and Introductions Contra Costa CCD, Facilities Planning Department Leadership: Ines Zildzic, Vice Chancellor, Facilities Planning & Construction Kathleen Halaszynski, Director, Construction Program Controls P.J. Roach, Facilities Project Manager Ben Azarnoush, District Design Director Tracy Marcial, Energy & Sustainability Manager Ben Cayabyab, Contracts Manager Fiscal and Document Control Support Staff Our partners: DVC, CCC, LMC Administration, M&O Directors, IT Managers, Users and Academic Deans 3

  4. Contra Costa CCD At a Glance $856.5M Capital Improvement Program Three Campuses and two Centers  Contra Costa College –San Pablo 3 Local Bond Measures:  Diablo Valley College – Pleasant Hill  Measure A 2002 $120M – closed out  San Ramon Campus  Measure A+ 2006, $286.5M – in  Los Medanos College – Pittsburg progress, 90% spent  Measure E 2014, $450M – in progress  Brentwood Center  District Office – Martinez *$300M + Remaining *Multiple Funding Sources  50,323 Students / 4,559 Employees *Concurrent schedules, multiple sites 4

  5. Program Overview Over 30 active projects districtwide $4.5M in Proposition 39 funds = large number of executed projects and ongoing Districtwide sustainability initiatives Projects in various stages of planning, design and construction Multiple funding sources Concurrent schedules; all college sites with active construction 2020-2025 Districtwide Strategic Plan completed 2020 Accreditation - Facilities Master Plans, District and Colleges focused standards and guidelines, future bond preparation efforts. 5

  6. Sustainability Goals All New Buildings & Major Renovations LEED Silver Target State Mandates Driving our Goals ◦ By 2030 - 50% of all existing buildings must be retrofit to ZNE ◦ Buildings under construction now will be existing buildings in 2030 ◦ ZNE Ready is MORE than roof ready for solar PV ◦ Driving the energy use intensity down during design is FUNDAMENTAL ◦ By 2045, achieve statewide carbon neutrality – GHG Reductions ◦ Moving toward electrification of our buildings (all electric heating, domestic hot water, etc) ◦ By 2020 –75% waste diversion from landfill ◦ Water use allowed in new buildings continues to ratchet down 6

  7. A.0 GOLF CLUB RD UNDERGROUND SITE U TILITIES CENTRAL PLANT S COPE All utilities part of PE/K, Art INCLUDES SERVICES TO PE/K BUILDINGS & POOL, ART COMPLEX Complex and CP PROJECTS. COURTS HV ELECTRICAL BUDGE T: $7M for site utilities; CP POTABLE WATER will be part of the Art Complex SANITARY SEWER LOT 8 project construction LOT 9 LOT 7 GAS 3. STORM DRAIN IRRIGATION (RECLAIMED WATER) TELEPHONE NEW ACADEMIC C OMPLEX COMMUNICATIONS EST. CONST. 10 /2022 - 1 2 /2024 BUDGET: $4M OCCUPANCY: 01/2025 TOTAL PROJECT BUDGET: $ 5 8M W 2. D-4014 7. A A A A NEW ART COMPLEX FUTURE SITE DEVELO[PMENT EST CONST. 3 / 20 20 - 1 2/ 2021 EST. DEMO START FALL 2025 TOTAL B F L ECN AO AO OCCUPANCY: 01/2022 DEMO (E) PROJECT BUDGET: TBD H PAC OLD MAINT. BLDG. LOT 5 DEMO (E) FO, LA, & COUNSELING BLDGS. HSF TOTAL PROJECT BUDGET: $ 47 M PE PE ECS AR 1. D-4012 4. LOT LOT T LA LA 10 10 0 FO FO SSC SU NEW PE/KINESIOLOGY COMPLEX LEARNING CENTER ML ML EST. CONST. Demo Oct. 2019 RENOVATION POOL POOL Main project: 3 /20 20 - 4 /202 0 EST. CONST. 07/ 2024 - 3/2026 WL WL OCCUPANCY Spring /Summer 2022 OCCUPANCY: 08/2026 TOTAL BC AB PROJECT BUDGET : TBD LAKE TOTAL PROJECT BUDGET: $ 4 9 M C C LC LC GYM GYM PEO PEO LOCALIZED ADA ISSUES MULTIPLE ADA P ATH OF TRAVEL MA SOCCER ISSUES ALONG THIS EDGE AS M GRADE TRANSITIONS FROM GYM LEVEL TO LAKE LEVEL. SC SC L OTHER PROJECTS: 5. * CLASSROOM DESIGN LHS PS STANDARDS ET ET BASEBALL * BUILDING SYSTEMS: SCIENCE HILL DEMO MECHANICAL ALL BLDGS. 6. UPGRADE & DEMO START FALL 2026 VF ET ET PROJ BUDGET NOT SET CONTROLS RETROFIT LOT 1 * ELECTRICAL ET BUILDING RENOVATION SWITCHGEAR EST.CONST :11/ 2024 -09/2025 REPLACEMENT OCCUPANCY:12/2025 LOT 4 TOTAL PROJECT BUDGET: $1 1 M * OTHER INFRASTRUCTURE LOT 3 LOT 2 UPGRADE PROJECTS * CAMPUS ADA DVC PLEASANT HILL CAMPUS, MEASURE E MAJOR BUILDING PROJECTS IMPROVEMENTS NG DR ALL DATES SUBJECT TO CHANGE. ALL PROJECT WORK LIMIT LINES ARE I VIK APPROXIMATE. C 09/30/17: Facilities Planning N

  8. Diablo Valley College – Pleasant Hill Campus Physical Education/Kinesiology Complex Status: Project in DSA; Early construction work for site utilities for Art and PE/K site utilities – in construction; swing space in progress. Demolition construction October 2019 – February 2020 Construction Start : March, 2020 with Art Complex Planned Completion : Spring 2022 Total SFT: 30,000, multiple buildings Total Budget : $49M Design team: HMC Delivery method: DBB 8

  9. DVC PE/K and Art Complex - Coordination 9

  10. Diablo Valley College – Pleasant Hill Campus Art Complex Status: In DSA; Early construction work for site utilities for Art and PE/K site utilities – in construction; demo warehouse done. Construction Start : March, 2020 with PE/K Planned Completion : Spring 2022 Total SFT: 37,000 Total Budget : $47M Design team: HMC Delivery method: DBB 10

  11. Diablo Valley College – Pleasant Hill Campus Academic Center Status: Predesign Evaluation of project program requirements, location and SFT Total SFT: 68,000 Total Budget : $70M Design Team: TBD Delivery: TBD 21

  12. C-4016 Incr. 3 Future Land Bank Bldg. Removal C-4001 Campus Safety Parking Center Lot 12 C-4008 C-608 - PE/K AA Building Renovation C-4016 New Science Building C-4025 Future Campus Site Work C-4008 Future B&G

  13. Contra Costa College – New Science Building Status: DSA Approved! Early increments for demolition and site work are close to completion Construction Start : Fall 2019 Planned Completion : Fall 2021 Total SFT: 50,000 Total Budget : $67M Design Team: SmithGroup Delivery Method: DBB 12

  14. Thank you! Questions? 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.