concept study
play

Concept Study Plans and Programs Committee Item 10 December 9, - PowerPoint PPT Presentation

E10-1 Item 10 Enclosure Plans and Programs Committee December 9, 2014 San Francisco Planning Department T-Third Phase 3 Concept Study Plans and Programs Committee Item 10 December 9, 2014 E10-2 San Francisco Planning Department Origins


  1. E10-1 Item 10 Enclosure Plans and Programs Committee December 9, 2014 San Francisco Planning Department T-Third – Phase 3 Concept Study Plans and Programs Committee Item 10 December 9, 2014

  2. E10-2 San Francisco Planning Department Origins of the Study • Interest in the extension due to T-Third Phase 2 (Central Subway) – especially after tunnel boring machines reach North Beach; preserving right-of-way • Interest from the Board of Supervisors (Sup. Chiu), public • Funds approved for limited consultant assistance by SFCTA Board – March 2014 • Three agency team: SFMTA, SFCTA and SF Planning Department • Concept Study started in March 2014 and a draft report completed in October 2014 2

  3. San Francisco E10-3 Planning Department Concept Alignments 3

  4. E10-4 San Francisco Planning Department Concept Alignments Number 1-1 1-2 2A-1 2A-2 2A-3 2A-4 2A-5 2A-6 2B-1 2B-2 2B-3 2B-4 3-1 3-2 Street (s) Columbus Columbus Powell Powell Powell Powell Powell Powell Powell-Beach Powell-Beach Powell-Beach Powell-Beach One-Way Loop One-Way Loop One-Way Loop Columbus Powell Powell-Beach NOT FEASIBLE NOT FEASIBLE Subway / Surface Subway / Subway Subway / Subway Subway / Subway Subway / Subway Subway / Subway Subway / Subway / Subway / Subway Surface Surface Surface Surface Surface Surface / Surface Surface / Subway Subway Station (s) North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach Conrad Square Conrad Square Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Conrad Square Conrad Square Conrad Square Conrad Square Conrad Square Conrad Square Data Highlights 4 Corridors 14 Concept Alignments 2 or 3 stations Subway and Subway-Surface combination 4

  5. San Francisco E10-5 Planning Department Constructability D C Ground Cross Sections B A Powell Beach Columbus 5

  6. E10-6 San Francisco Planning Department Constructability Issues Data Highlight No Fatal Flaws Areas at risk with sea-level rise Areas of possible liquefaction 6

  7. San Francisco E10-7 Planning Department Travel Time Estimates Data Highlights Legend Concept One-way Round Trip Rating_________ 2A-2 = 3 mins 7 mins fastest 3-2 Loop = N/A 8 mins fastest loop 2B-1 = 7½ mins 15 mins slowest One-way Round Trip 18 16 14 12 Minutes 10 8 Not Feasible Not Feasible 6 4 2 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1-1 1-2 2A-1 2A-2 2A-3 2A-4 2A-5 2A-6 2B-1 2B-2 2B-3 2B-4 3-1 3-2 Number 1-1 1-2 2A-1 2A-2 2A-3 2A-4 2A-5 2A-6 2B-1 2B-2 2B-3 2B-4 3-1 3-2 Concept Alignments Street (s) Columbus Columbus Powell Powell Powell Powell Powell Powell Powell-Beach Powell-Beach Powell-Beach Powell-Beach One-Way Loop One-Way Loop Columbus One-Way Loop Powell Powell-Beach Subway / Surface Subway / Subway Subway / Subway Subway / Subway Subway / Subway Subway / Subway Subway / Subway / Subway / Subway Surface Surface Surface Surface Surface Surface / Surface Surface / Subway Subway 7 Station (s) North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach Conrad Square Conrad Square Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Conrad Square Conrad Square Conrad Square Conrad Square Conrad Square Conrad Square

  8. E10-8 San Francisco Planning Department Travel Time Comparison Ferry Building to Fisherman’s Wharf Data Highlight Transit 10-15 Bicycle 5-10 Private Auto 3- 5 50% - 65% quicker than existing transit service Chinatown Station Existing Caltrain / Ballpark to Fisherman’s Wharf Transit 30-40 Market St. / Union Square Bicycle 30-40 to Fisherman’s Wharf Private Auto 10-15 Transit 20-30* Bicycle 15-20 Private Auto 10-15 * Plus up to 60 minute wait T-Third Phase 2+3 – Caltrain & Ballpark to Fisherman’s Wharf Columbus 14-17 Powell 13-17 8 Powell-Beach 15-20

  9. San Francisco E10-9 Planning Department Daily Ridership Estimates T-Third Alignment 1-2 Daily Ridership Estimates 140000 Data Highlights 120000 55% increase in T-Line passenger levels • 100000 115,000 41,000 Phase 2 + Phase 3 • At least 1/4 of the increase is from new Passengers 80000 trips on the Muni system 74,000 74,00 0 60000 Phase 2 Up to 3/4 of new trips are passengers • moving to the T-Line, relieving 40000 overcrowding and pass-ups on buses, 20000 cable cars, and the F-Line 0 1 T-Third LRT Passenger Ridership Estimates 9

  10. E10-10 San Francisco Planning Department Peak Ridership and Capacity T-Third Concept Alignment 1-2 Peak Hr. / Peak Direction Data Highlights Ridership Estimates 6000 At the maximum load point (MLP) – • 5,712 T-Line trains spaced no more than 952 2.5 minute trains 5000 3 minutes apart will be required to 4,196 4,760 680 meet projected passenger levels Phase 3 3.0 minute trains 4000 384 4,080 3,812 4,080 3,812 Peak ridership changes less than Passengers • 3.5 minute trains Phase 2 daily ridership due to the all-day 3000 nature of demand in these neighborhoods. 2000 By 2030, T-Line trains are • 1000 scheduled at 2.5 minutes apart in the peak period 0 T-Third LRT 1 2 T-Third LRT Vehicle Passenger Passenger Capacity Ridership Estimates 10

  11. San Francisco E10-11 Planning Department Existing Land Use Data Highlights Planning Department analyzed: • Land Use • Demographic conditions • Development potential 11

  12. E10-12 San Francisco Planning Department Value Capture Opportunities Estimated Bonding Capacity of local financing mechanisms * Concept Alignment 1-2 analysis (* all figures in 2014 dollars) Data Highlights • CFD = $180-$220 million - 2/3 voter approval • IFD = $100-$110 million - 55% voter approval • SpAD = $90 million in - simple majority approval • Modest revenue differences between current zoning and limited zoning increases 12

  13. San Francisco E10-13 Planning Department Capital Costs (2014 $ Estimate) Data Highlights Concept Cost Estimate Rating___________ 2A-1 $ 440 million lowest cost 2B-2 $ 1.410 billion highest cost 1600 1400 Dollars (Millions) 1200 1000 800 Not Feasible Not Feasible 600 400 200 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Number 1-1 1-2 2A-1 2A-2 2A-3 2A-4 2A-5 2A-6 2B-1 2B-2 2B-3 2B-4 3-1 3-2 Street (s) Columbus Columbus Powell Powell Powell Powell Powell Powell Powell-Beach Powell-Beach Powell-Beach Powell-Beach One-Way Loop One-Way Loop One-Way Loop Columbus Powell Powell-Beach Subway / Surface Subway / Subway Subway / Subway Subway / Subway Subway / Subway Subway / Subway Subway / Subway / Subway / Subway Surface Surface Surface Surface Surface Surface / Surface Surface / Subway Subway 13 Station (s) North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach North Beach Conrad Square Conrad Square Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Kirkland Yard Conrad Square Conrad Square Conrad Square Conrad Square Conrad Square Conrad Square

  14. E10-14 San Francisco Planning Department Cost / Benefit Analysis Data Highlight $1.78* - $2.87* = 2040 projected cost per new trip – (FTA Formula) Concept Alignment 1-2 (low cost and high cost estimate) * Costs are in 2014 dollars 14

  15. San Francisco E10-15 Planning Department Potential Funding Federal Sources Federal Transit Administration (FTA) New Starts program Land Use Value Capture Infrastructure Finance District (IFD) Community Facilities District (Mello-Roos) (CFD) Special Assessment District (SpAD) Local Sources Sales Tax (Proposition K) Future Transportation Funding Measures Other Sources Joint Development ? 15

  16. E10-16 San Francisco Planning Department North Beach Station Rail to North Beach Facts • New environ. review process required • Tradeoffs with different construction methods • Offstreet construction access lessens neighborhood disruption Pagoda Palace Site Facts SFMTA has active lease until May 10, 2015 • to use parcel as a TBM retrieval site SFMTA has “right of first refusal” to • purchase if owner decides to sell property Owner preparing to build 19 units of • housing 16

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend