Community Presentation April 25_26, 2019 Agenda Rebrand 1 Access - PowerPoint PPT Presentation

Community Presentation April 25_26, 2019 Agenda Rebrand 1 Access Pipeline 2 Alberta Carbon Trunk Line (ACTL) 3 2 Rebrand Responsibly Delivering Energy for Generations 3 Wolf Midstream Wolf Alberta Based Company Midstream


  1. Community Presentation April 25_26, 2019

  2. Agenda Rebrand 1 Access Pipeline 2 Alberta Carbon Trunk Line (ACTL) 3 2

  3. Rebrand Responsibly Delivering Energy for Generations 3

  4. Wolf Midstream Wolf • Alberta Based Company Midstream • Focused on investing in Western Canadian energy Carbon Pipeline infrastructure Business Unit Business Unit • Responsible owner, operator and developer of midstream infrastructure projects Access ACTL Pipeline 4

  5. Pipeline Business Unit (Access Pipeline System) 5

  6. Access Pipeline System • Service Conklin area SAGD facilities • 42”/30” Blend Pipeline • 24” Diluent Pipeline • Sturgeon Terminal • Greater Edmonton Area Diluent Gathering System • Operate Stonefell Terminal and Bruderheim Pipeline System 6

  7. Access Pipeline History • Access Pipeline - In-Service 2007 • Major pipeline expansion project complete 2014 • Wolf Midstream acquired 50% ownership 2016 • Wolf Midstream acquired the final 50% 2018 • Rebranded under Wolf Midstream 2019 7

  8. CEPA Member Uncompromising commitment to Health, Safety and the Environment. CEPA members collaborate to continuously advance their operations in 10 key priority areas with a goal of zero incidents. EMERGENCY MANAGEMENT • PIPELINE INTEGRITY • DAMAGE PREVENTION • CONTROL ROOM MANAGEMENT • INDIGENOUS RELATIONS • WATER PROTECTION • ENVIRONMENTAL STEWARDSHIP • SECURITY • LAND USE & ACCESS • MANAGEMENT SYSTEMS • https://cepa.com 8

  9. Carbon Business Unit - Alberta Carbon Trunk Line (ACTL) 9

  10. The Alberta Carbon Trunk Line (ACTL) • 240 km, high pressure 16” CO2 • Connects Alberta Industrial Heartland to oil reservoirs in the Lacombe area • ACTL will be the largest capacity CO2 pipeline in the world once complete in 2020 • Pipeline will initially transport 4,400 tonnes/d with total capacity of 40,000 tonnes/d • Open access CO2 pipeline

  11. Redwater Area Infrastructure Nutrien Capture Facility NWR Booster Compressor NWR Main Compressor ACTL Pipeline NWR Nutrien Redwater To EOR

  12. Why is this Project Important? • Supports improved environmental stewardship › ACTL, at capacity, will allow the removal of 14.6 million tons of CO2 per year › Equal to approx. 2.6 million cars being removed from our roads › “without CCS as part of the solution meeting global climate goals will be practically impossible” - Dr. Fatih Birol, Executive Director, International Energy Agency • In conjunction with EOR, carbon capture provides incremental production and extends the life of existing reservoirs • Greater than $500 million in capital investment.

  13. Project Status - Pipeline • Construction started in October 2018 • Pipe manufactured and coated in Camrose • Approx. 200 km of right of way has been cleared • Approx. 100 km of pipe has already been backfilled • North Saskatchewan River Crossing completed • > 500,000 manhours to date

  14. Project Status - Facilities NWR Booster Compressor • Construction complete, in commissioning phase NWR Main Compressor and Nutrien Capture Facility • Site clearing in progress • Modules being completed in Calgary • Construction commencing soon after site clearing • Commissioning and start-up late 2019/Q1 2020 New Supply • Currently seeking new sources of CO2 supply in the Heartland area

  15. Wolf Midstream Contact Information Website www.wolfmidstream.com Email info@wolfmidstream.com Pipeline Business Unit kroebuck@wolfmidstream.com Carbon Business Unit jpearson@wolfmidstream.com Community Investment community.wp@wolfmidstream.com 15

  16. Thank you 16

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.