Community Liaison Committee Meeting #22 September 12, 2017 Agenda - - PowerPoint PPT Presentation

community liaison committee meeting 22
SMART_READER_LITE
LIVE PREVIEW

Community Liaison Committee Meeting #22 September 12, 2017 Agenda - - PowerPoint PPT Presentation

Community Liaison Committee Meeting #22 September 12, 2017 Agenda 1. Review of June 6, 2017 meeting notes 2. Membership items 3. Site Specific Standards for Particulate, BaP, Benzene 4. Algoma Boat Slip 5. Noise Abatement 6. Current


slide-1
SLIDE 1

Community Liaison Committee Meeting #22

September 12, 2017

slide-2
SLIDE 2

September 2017

1. Review of June 6, 2017 meeting notes 2. Membership items 3. Site Specific Standards for Particulate, BaP, Benzene 4. Algoma Boat Slip 5. Noise Abatement 6. Current planned activities that require an application for an Environmental Compliance Approval (ECA) 7. GHG Cap and Trade 8. Public Open House 9. Next Meetings

Agenda

slide-3
SLIDE 3

3

Membership Items

Current Members and Alternates Representation Primary Member Alternate Algoma Fred Post Dave Clingen Algoma Dave Clingen Fred Post Algoma Chris Galizia Ontario Ministry of Environment Lori Greco Ron Dorscht Public David Trowbridge Ildiko Horvath Public Patt Marquis SSM Tribe of Chippewa Indians Kathie Brosemer Algoma Public Health Kara Flannigan Jonathon Bouma Chippewa County Health Dept. Trevor Quinlan Suzanne Lieurance Batchewana First Nations Dan Sayers Jr. City of Sault Ste. Marie Catherine Taddo Dan Perri United Steel Workers Local 2251 Reginald Dunn

  • St. Mary’s River RAP Coordinator

Lisa Derickx

slide-4
SLIDE 4

4

Site Specific Standard for Particulate and BaP

  • On March 27th, 2015 Essar received a Site Specific Standard for Particulate

accompanied by a Directors Order which sets specific emission limits in cokemaking: – Certified observers (per EPA Method 9 and Method 303) – 5 days per week, 10 Saturdays and 10 Sundays each year – Must observe daily per battery: 4 pushes, 5 charges, all lids, all doors, all standpipes – Must make operational adjustments if over the daily limits and notify MOE

slide-5
SLIDE 5

5

Maximum Anytime Emissions Limits

Conformance calculated daily for each battery

slide-6
SLIDE 6

6

Operational Adjustments - 2017

Daily emissions limit lowered once again in January 2017, making compliance on

  • ngoing challenge for doors
slide-7
SLIDE 7

7

Operational Adjustments for Pushing Emissions

All operation adjustments to date have been successful in reducing pushing emissions within the allowable 30 day timeline

slide-8
SLIDE 8

8

30 Day Rolling Avg. Emission Limits

Conformance calculated daily for each battery

slide-9
SLIDE 9

9

30 Day Rolling Avg. Charge Times

Achieved compliance on all batteries in Feb 2016

slide-10
SLIDE 10

10

30 Day Rolling Avg. Lid Emissions

Achieved compliance on all batteries in 2015

slide-11
SLIDE 11

11

30 Day Rolling Avg. Off-take Emissions

Achieved compliance on all batteries in August 2017

slide-12
SLIDE 12

12

30 Day Rolling Avg. Door Emissions

Achieved compliance on all batteries in August 2017

slide-13
SLIDE 13

13

Stack Opacity

Continuous corrective actions on all batteries

  • Part of the investment plan to achieve compliance with new limits also focuses on reducing stack

emissions from cokemaking

  • Initial focus is on reducing intensity of stack emissions
  • Significant recent improvements being realized
slide-14
SLIDE 14

14

Public Complaints

There were no public complaints received by the Facility since the last meeting of the CLC that related to a matter addressed in the Order.

slide-15
SLIDE 15

15

MOE Comments

slide-16
SLIDE 16

16

Site Specific Standard for Benzene

  • The Benzene SSS approval and order requires continued addition to Benzene

Emission Control (BEC) systems followed by on site monitoring

  • Plan is to connect remaining uncontrolled sources to BEC

– Three sources to be controlled by 2017 year end – #8 Tar tank controlled in April – 9b Tar decanter controlled in July – North Raw Liquor Tank to be controlled by year end – Three sources to be controlled by 2020 year end. Planning has started.

  • Planning underway to conduct ambient monitoring on site to identify further

benzene sources and develop control plans if required

slide-17
SLIDE 17

17

Ambient Air Monitoring

slide-18
SLIDE 18

18

Boat Slip Sediment

  • All permits and approvals obtained
  • Permits include:
  • In-water works
  • Landfill ECA amendment
  • Dredging commenced on Aug 31st
  • The objective is to remove legacy

contaminated sediment

  • A post-dredge sediment assessment will
  • ccur to inform future planning
slide-19
SLIDE 19

19

Road Paving

Continuation of road paving activities for dust control Two areas were paved in July and August with 6” asphalt

  • 150 m on pot-hauler road near #4 gate
  • 200 m near material reprocessing (high traffic area to the west)

Additional repairs and maintenance have been completed concurrently Plan to continue progressive paving plan in future years

slide-20
SLIDE 20

20

Noise Abatement

  • Early in 2014 the MOE accepted a five year plan to reduce noise emissions from

10 sources at the facility. Three source controls installed.

  • 2017 abatement plans are fully approved and funded

– BOSP excess steam – To be complete in 2017 – Cooling tower fan motors – Gas cleaning plant fan motors

slide-21
SLIDE 21

21

New Environmental Compliance Approval Applications

  • Currently the following applications are with the MOE for processing:

– Algoma submitted a priority request for amendment to the landfill ECA to allow for the disposal of larger quantities of dredged river sediment than previously permitted, which will allowed for the boat slip dredging to occur. The ECA was issued in August.

slide-22
SLIDE 22

22

Cap and Trade

  • CO2 emission reduction opportunities continue to be evaluated internally. Some GHG

reduction projects will be completed in 2017 and will result in real reductions.

  • Algoma has applied for funding in support of a reduction opportunity.
slide-23
SLIDE 23

23

Public Open Houses

  • Last open house held on December 14, 2016 at the new Library at the Northern

Community Centre. – Focus was on Cokemaking Site Specific Standard performance and efforts to reduce emissions from Cokemaking.

  • Next open house likely in October/November 2017
slide-24
SLIDE 24

24

Next Meeting

  • Proposed 2017 Schedule:
  • September 12th (today)
  • December 5th , 2017
  • March 6th, 2018
  • June 5th, 2018
slide-25
SLIDE 25

25

MacLeod Mine Water Treatment Plant – Wawa

Other Environment Projects

  • The MacLeod Mine operated for 100

years

  • It has been filling with water at about

750 gpm since its closure in 1998

  • As per the closure plan, a water

treatment plant must be constructed to ensure no untreated mine water is discharged to the environment

  • Concrete bulkheads have been installed

in tunnels to prevent outflow and to submerge sulfide ore No.5 Shaft MacLeod Mine

slide-26
SLIDE 26

26

Most site infrastructure has been removed and surface rehabilitation measures have been completed

Other Environment Projects

slide-27
SLIDE 27

27

MacLeod Mine Water Treatment Plant – Wawa

  • In 2015 and 2016, studies were performed to

determine the most appropriate technology for mine water treatment in this specific scenario.

  • Determination that a high density sludge (HDS)

treatment system using lime, is the most suitable technology and would reliably provide required effluent quality.

  • Bench and pilot water treatment studies were

conducted in 2016 where mine water was extracted from #5 shaft for treatability analysis.

Other Environment Projects

slide-28
SLIDE 28

28

MacLeod Mine Water Treatment Plant – Wawa

  • CCAA made financing of the construction difficult
  • The company has been working with the MNDM to ensure completion of the construction of

a water treatment plant and avoid mine water overflow

  • All permitting is in place and construction commenced in 2017
  • The plant will be commissioned this fall

Other Environment Projects

slide-29
SLIDE 29

29

Other Environment Projects

MacLeod Mine Water Treatment Plant – Wawa

  • Regular water monitoring has been ongoing
  • In the mine shaft to determine flood rates
  • At numerous locations around the site to

ensure no off-site impact and long term recovery

  • The optimal location for the water treatment

plant is the #5 shaft

  • Three 15” diameter boreholes were drilled ~600

feet vertical for pumping of water

  • Power is being brought to the site
  • Lime plant retrofits are being designed to supply

the plant for water treatment

slide-30
SLIDE 30

30

MacLeod Mine Water Treatment Plant – Wawa

  • 1 - 68 ft. dia. X 16ft. high Clarifier
  • 2 - 24 ft. dia. X 27 ft. high Neutralization Tanks
  • 1 - 5500 cu.ft. Lime Silo
  • 1 - 1,000 usg Freshwater Storage Tank (Moran Lake)
  • 5.5 km of 12 inch dia. HDPE Discharge Pipe to Magpie River
  • 6,600 sq.ft. Building

Other Environment Projects

slide-31
SLIDE 31

31

Other Environment Projects

slide-32
SLIDE 32

32

Other Environment Projects