Community Liaison Committee Meeting #22
September 12, 2017
Community Liaison Committee Meeting #22 September 12, 2017 Agenda - - PowerPoint PPT Presentation
Community Liaison Committee Meeting #22 September 12, 2017 Agenda 1. Review of June 6, 2017 meeting notes 2. Membership items 3. Site Specific Standards for Particulate, BaP, Benzene 4. Algoma Boat Slip 5. Noise Abatement 6. Current
September 12, 2017
September 2017
3
Current Members and Alternates Representation Primary Member Alternate Algoma Fred Post Dave Clingen Algoma Dave Clingen Fred Post Algoma Chris Galizia Ontario Ministry of Environment Lori Greco Ron Dorscht Public David Trowbridge Ildiko Horvath Public Patt Marquis SSM Tribe of Chippewa Indians Kathie Brosemer Algoma Public Health Kara Flannigan Jonathon Bouma Chippewa County Health Dept. Trevor Quinlan Suzanne Lieurance Batchewana First Nations Dan Sayers Jr. City of Sault Ste. Marie Catherine Taddo Dan Perri United Steel Workers Local 2251 Reginald Dunn
Lisa Derickx
4
accompanied by a Directors Order which sets specific emission limits in cokemaking: – Certified observers (per EPA Method 9 and Method 303) – 5 days per week, 10 Saturdays and 10 Sundays each year – Must observe daily per battery: 4 pushes, 5 charges, all lids, all doors, all standpipes – Must make operational adjustments if over the daily limits and notify MOE
5
6
Daily emissions limit lowered once again in January 2017, making compliance on
7
8
9
Achieved compliance on all batteries in Feb 2016
10
Achieved compliance on all batteries in 2015
11
Achieved compliance on all batteries in August 2017
12
Achieved compliance on all batteries in August 2017
13
Continuous corrective actions on all batteries
emissions from cokemaking
14
There were no public complaints received by the Facility since the last meeting of the CLC that related to a matter addressed in the Order.
15
16
Emission Control (BEC) systems followed by on site monitoring
– Three sources to be controlled by 2017 year end – #8 Tar tank controlled in April – 9b Tar decanter controlled in July – North Raw Liquor Tank to be controlled by year end – Three sources to be controlled by 2020 year end. Planning has started.
benzene sources and develop control plans if required
17
18
contaminated sediment
19
Continuation of road paving activities for dust control Two areas were paved in July and August with 6” asphalt
Additional repairs and maintenance have been completed concurrently Plan to continue progressive paving plan in future years
20
10 sources at the facility. Three source controls installed.
– BOSP excess steam – To be complete in 2017 – Cooling tower fan motors – Gas cleaning plant fan motors
21
– Algoma submitted a priority request for amendment to the landfill ECA to allow for the disposal of larger quantities of dredged river sediment than previously permitted, which will allowed for the boat slip dredging to occur. The ECA was issued in August.
22
reduction projects will be completed in 2017 and will result in real reductions.
23
Community Centre. – Focus was on Cokemaking Site Specific Standard performance and efforts to reduce emissions from Cokemaking.
24
25
MacLeod Mine Water Treatment Plant – Wawa
years
750 gpm since its closure in 1998
treatment plant must be constructed to ensure no untreated mine water is discharged to the environment
in tunnels to prevent outflow and to submerge sulfide ore No.5 Shaft MacLeod Mine
26
Most site infrastructure has been removed and surface rehabilitation measures have been completed
27
MacLeod Mine Water Treatment Plant – Wawa
determine the most appropriate technology for mine water treatment in this specific scenario.
treatment system using lime, is the most suitable technology and would reliably provide required effluent quality.
conducted in 2016 where mine water was extracted from #5 shaft for treatability analysis.
28
MacLeod Mine Water Treatment Plant – Wawa
a water treatment plant and avoid mine water overflow
29
MacLeod Mine Water Treatment Plant – Wawa
ensure no off-site impact and long term recovery
plant is the #5 shaft
feet vertical for pumping of water
the plant for water treatment
30
MacLeod Mine Water Treatment Plant – Wawa
31
32