Innovating with 4D MWH Treatment Ltd Case Study Frankley WTW New - - PowerPoint PPT Presentation

innovating with 4d mwh treatment ltd case study frankley
SMART_READER_LITE
LIVE PREVIEW

Innovating with 4D MWH Treatment Ltd Case Study Frankley WTW New - - PowerPoint PPT Presentation

Synchro Conference 2015 London Innovating with 4D MWH Treatment Ltd Case Study Frankley WTW New Lime Plant September 2015 Introduction Opportunities Drivers Project Design Collaboration and Coordination


slide-1
SLIDE 1

Innovating with 4D MWH Treatment Ltd Case Study Frankley WTW New Lime Plant

September 2015

Synchro Conference 2015 London

slide-2
SLIDE 2

Contents

  • Introduction
  • Opportunities
  • Drivers
  • Project
  • Design Collaboration and Coordination
  • Collaborative Planning
  • Outcomes
slide-3
SLIDE 3

Introduction

slide-4
SLIDE 4

Introduction

slide-5
SLIDE 5

Introduction

slide-6
SLIDE 6

Existing Plant

slide-7
SLIDE 7

New Lime Plant

slide-8
SLIDE 8

Opportunities

slide-9
SLIDE 9
  • Safe working
  • De-risk – improve programme
  • Severn Trent Water “Go Digital”
  • Engagement with Client / Client Confidence
  • Improve team communications
slide-10
SLIDE 10
slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17

Collaborative Planning - Results

slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20
slide-21
SLIDE 21
  • Safe Working (Calmness)

– Calmness on site (problems solved virtually – not reactive on site)

  • De-risk / Improve Programme

– Traditional Delivery: 12 weeks on site, 360 man days labour – DfMA Delivery: 10 days on site, 150 man days (off-site) + 60 man days (on-site) – Reduction of 50% out-turn cost (labour)

  • Severn Trent Water “Go Digital”
  • Engagement with Client / Client Confidence

– 4D commissioning – Digital legacy

  • Improve team communications
slide-22
SLIDE 22