Community Liaison Committee Meeting #21
June 6, 2017
Community Liaison Committee Meeting #21 June 6, 2017 Agenda 1. - - PowerPoint PPT Presentation
Community Liaison Committee Meeting #21 June 6, 2017 Agenda 1. Review of February 21, 2017 meeting notes 2. Membership items 3. Site Specific Standard for Particulate, BaP, Benzene 4. Algoma Boat Slip 5. Export Dock 6. Noise Abatement
June 6, 2017
June 2017
3
4
accompanied by a Directors Order which sets specific emission limits in cokemaking: – Certified observers (per EPA Method 9 and Method 303) – 5 days per week, 10 Saturdays and 10 Sundays each year – Must observe daily per battery: 4 pushes, 5 charges, all lids, all doors, all standpipes – Must make operational adjustments if over the daily limits and notify MOE
5
6
7
8
9
Preventative Measures include: – Adjusting carbon scraper bar – Decarbonizing standpipes, goosenecks and charge holes – Cleaning goosenecks, sleeves to the collector main, and steam jets – Replacing drop sleeve donuts, bellow bags, and carbon seals – Adjusting coal feed systems to optimize coal charging volume – Leveling charge hole bases to ensure proper elevation and tight seal
10
Preventative Measures include: – Applying lid sealant immediately after charging an oven and whenever emissions are observed – Replacing damaged or cracked lids – Repairing, leveling and grouting charge hole bases to ensure proper seal
11
Preventative Measures include: – Replacing the soft seal and adjusting the cap – Cleaning the gooseneck, sleeve to collector main, and steam jet – Re-packing collar or base of the pipe with refractory – Applying masonry seal to small cracks until welding can be completed – Replacing the standpipe at the end of its lifecycle
12
13
Preventative Measures include:
14
15
#7 Battery Revitalization – Progressing with #7 battery Revitalization Project. Work includes:
16
– $9.6Million dollar investment – 6 additional thru-walls planned for 2018
spare door extractor, cameras, radar spotting)
Compliance Plan Overall Cost Impact of 45 million dollars over 4 years
17
There was one complaint received by the Facility since the last meeting of the CLC that related to a matter addressed in the Order.
ensured coking process was fully completed before pushing the oven
18
19
Emission Control (BEC) systems followed by on site monitoring
– Three sources to be controlled by 2017 year end – #8 Tar tank controlled in April – 9b Tar decanter control scheduled in June – North Raw Liquor Tank to be controlled by year end – Three sources to be controlled by 2020 year end.
sources and develop control plans if required
20
21
response protocol was initiated immediately to contain the area with booms
Transport Canada, Canadian Coast Guard and the DFO
ship and were removed immediately along with any other visible contaminants
being sealed by installing large steel plates which will contain any unknown contaminants inside the ship.
22
Continuation of road paving activities for dust control Currently planning to pave two areas with 6” asphalt in 2017
Plan to continue progressive paving plan in future years
23
10 sources at the facility. Three source controls installed.
– Cooling tower fan motors – Gas cleaning plant fan motors – BOSP excess steam
24
– Administrative amendment to the steelmaking effluent treatment system ECA resulted in the MOECC requesting a new site wide ECA for all effluent discharges in order to update the Ministry’s records. – Algoma will be submitting a priority request for amendment to the landfill ECA to allow for the disposal of larger quantities of dredged river sediment than currently permitted, which will allow for the boat slip dredging to occur.
25
initiatives
reduction projects will be completed in 2017 and will result in real reductions.
26
Community Centre. – Focus was on Cokemaking Site Specific Standard performance and efforts to reduce emissions from Cokemaking.
27